CO Springs Fire | Original | A | 11/13/2023 | CSFIRE | CSFIRE | We are pleased to inform you this plan is approved. You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account.
ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | dwithee | CO Springs Fire | 1927650 |
Energy | Original | A | 11/6/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1923684 |
Electrical | Original | A | 11/6/2023 | DANIELG | DANIELG | | | Electrical | 1923683 |
Electronic Plan | Original | / | 11/6/2023 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1923674 |
Construction | Original | A | 11/3/2023 | BPHILLIPS | BPHILLIPS | | | Construction | 1922850 |
CO Springs DRE | Original | A | 11/2/2023 | TBAXTER | TBAXTER | Approved per UDC standards. | | CO Springs DRE | 1922670 |
Zoning/Planning | Original | / | 11/2/2023 | TBAXTER | TBAXTER | In Current Review by TBAXTER | | Zoning/Planning | 1922668 |
Construction | Original | D | 11/2/2023 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1922370 |
Electronic Plan | Original | / | 11/1/2023 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 1921536 |
Enumeration | Original | N | 10/31/2023 | BRENT | BRENT | | | Enumeration | 1921452 |
Electronic Plan | Original | / | 10/31/2023 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 1921451 |
Submittal 2 | Original | / | 10/31/2023 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 1920986 |
CO Springs Fire | Original | D | 10/18/2023 | CSFIRE | CSFIRE | INCOMPLETE SUBMITTAL PER RBD - PROVIDE LIFE SAFETY PLAN | dwithee | CO Springs Fire | 1915802 |
CO Springs Hazmat | Original | N | 10/18/2023 | CSFIRE | CSFIRE | | dwithee | CO Springs Hazmat | 1915801 |
CO Springs DRE | Original | A | 10/13/2023 | APAQUETTE | APAQUETTE | Deck approved per UDC standards. No Excavation or penetration >3 feet in depth will occur per disclaimer. | | CO Springs DRE | 1913574 |
Energy | Original | D | 10/11/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1912016 |
Mechanical | Original | A | 10/11/2023 | JUSTINC | JUSTINC | | | Mechanical | 1912015 |
CSU Water | Original | A | 10/10/2023 | CSUREVIEW | CSUREVIEW | Backflow okay. MLW | mlwilliams | CSU Water | 1911571 |
CSU Waste Water | Original | N | 10/10/2023 | CSUREVIEW | CSUREVIEW | No new wastewater service outside of building. MLW | mlwilliams | CSU Waste Water | 1911567 |
Zoning/Planning | Original | / | 10/10/2023 | APAQUETTE | APAQUETTE | In Current Review by APAQUETTE | | Zoning/Planning | 1911355 |
Electrical | Original | D | 10/10/2023 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1911275 |
Electronic Plan | Original | / | 10/10/2023 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1911270 |
Construction | Original | D | 10/10/2023 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1911267 |
Plumbing | Original | A | 10/5/2023 | SHANEN | SHANEN | | | Plumbing | 1909025 |
Electronic Plan | Original | / | 10/4/2023 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 1908781 |
Enumeration | Original | N | 9/25/2023 | BRENT | BRENT | | | Enumeration | 1904042 |
Electronic Plan | Original | / | 9/25/2023 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 1904040 |
Energy | Original | / | 9/22/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1903207 |
Floodplain | Original | N | 9/22/2023 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6332219018) | | Floodplain | 1903206 |