| Electrical | Splice 01/23/26 | A | 1/28/2026 | BERTHA | BERTHA | Added Panel MS, revised site plan, revised one-line, revised panel schedules | | Electrical | 2261019 |
| Electronic Plan | Splice 01/23/26 | / | 1/28/2026 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2260912 |
| Submittal 2 | Splice 01/23/26 | / | 1/28/2026 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2260677 |
| Electrical | Splice 01/23/26 | D | 1/23/2026 | BERTHA | BERTHA | Provide revised one-line - show conductor size, type and quantity for Panel MS.
Provide available fault current at Panel MS. . * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2259544 |
| Electronic Plan | Splice 01/23/26 | / | 1/23/2026 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2259490 |
| County Zoning | Splice 09/10/25 | N | 9/16/2025 | DSDDEAN2 | DSDDEAN2 | Planning and Community Development approved this Site Development Plan at File No PPR246 on 8/13/2024. PCD has no need to review internal plans for the approved structure. Staff was not able to stamp the Plan Label as there was no spot reserved for County Zoning on the Plan Label. | | County Zoning | 2211498 |
| Electrical | Splice 09/10/25 | A | 9/11/2025 | BERTHA | BERTHA | Revised lift station plans | | Electrical | 2209534 |
| Electronic Plan | Splice 09/10/25 | / | 9/10/2025 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2209253 |
| Zoning/Planning | Splice 09/10/25 | / | 9/10/2025 | DSDDEAN2 | DSDDEAN2 | In Current Review by DSDDEAN2 | | Zoning/Planning | 2209018 |
| Plumbing | Splice 09/10/25 | A | 9/10/2025 | SHANEN | SHANEN | Revised sheet P1.1A, P1.1B, P2.1A, P2.2A and P6.0. | | Plumbing | 2209010 |
| Mechanical | Splice 09/10/25 | A | 9/10/2025 | DALEH | DALEH | Changed from 1 duct to two ducts | | Mechanical | 2208979 |
| Construction | Splice 09/10/25 | A | 9/10/2025 | JUSTINL | JUSTINL | Revised architectural and structural sheets, details, interior and exterior finish and dimensions | | Construction | 2208963 |
| Electronic Plan | Splice 09/10/25 | / | 9/10/2025 | JUSTINL | JUSTINL | In Current Review by JUSTINL | | Electronic Plan | 2208922 |
| Construction | Splice 03/13/25 | A | 3/21/2025 | JUSTINL | JUSTINL | Minor interior finish revisions | | Construction | 2134534 |
| Electronic Plan | Splice 03/13/25 | / | 3/21/2025 | JUSTINL | JUSTINL | In Current Review by JUSTINL | | Electronic Plan | 2134526 |
| Submittal 2 | Splice 03/13/25 | / | 3/21/2025 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2134432 |
| Falcon Fire (CSFD) | Splice 03/13/25 | A | 3/17/2025 | CSFIRE | CSFIRE | Splice approved for clouded revs only | phil.valdez | Falcon Fire (CSFD) | 2132004 |
| Electrical | Splice 03/13/25 | A | 3/17/2025 | BERTHA | BERTHA | Revised lighting and power plans | | Electrical | 2131859 |
| Electronic Plan | Splice 03/13/25 | / | 3/17/2025 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2131854 |
| Construction | Splice 03/13/25 | D | 3/14/2025 | JUSTINL | JUSTINL | Missing design professional stamp * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2131288 |
| Electrical | Splice 02/12/25 | A | 3/12/2025 | BERTHA | BERTHA | Added irrigation controller | | Electrical | 2129819 |
| Electronic Plan | Splice 02/12/25 | / | 3/12/2025 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2129818 |
| Meridian Ranch Water | Splice 02/12/25 | A | 2/27/2025 | MERIDIANRANCH | MERIDIANRANCH | | LawrenceGrahem | Meridian Ranch Water | 2125381 |
| Meridian Ranch Waste Water | Splice 02/12/25 | A | 2/27/2025 | MERIDIANRANCH | MERIDIANRANCH | | LawrenceGrahem | Meridian Ranch Waste Water | 2125380 |
| Mechanical | Splice 02/12/25 | N | 2/26/2025 | DALEH | DALEH | No Mechanical changes per narrative | | Mechanical | 2124892 |
| Plumbing | Splice 02/12/25 | A | 2/26/2025 | SHANEN | SHANEN | Revised sheet P1.1A, P2.1A and P5.0. | | Plumbing | 2124772 |
| Electronic Plan | Splice 02/12/25 | / | 2/26/2025 | SHANEN | SHANEN | In Current Review by SHANEN | | Electronic Plan | 2124771 |
| Elevators | Splice 02/12/25 | N | 2/25/2025 | ROBERTV | ROBERTV | No apparent changes to elevator | | Elevators | 2124575 |
| Falcon Fire (CSFD) | Splice 02/12/25 | A | 2/13/2025 | CSFIRE | CSFIRE | SPLICE FOR 2-12-25 APPROVED FOR CLOUDED REVISIONS ONLY | michael.davis1@color | Falcon Fire (CSFD) | 2120592 |
| County Zoning | Splice 02/12/25 | A | 2/12/2025 | DSDDEAN2 | DSDDEAN2 | Planning and Community Development approved this Site Development Plan at Fil No PPR246 on 10/4/2024. | | County Zoning | 2120430 |
| Zoning/Planning | Splice 02/12/25 | / | 2/12/2025 | DSDDEAN2 | DSDDEAN2 | In Current Review by DSDDEAN2 | | Zoning/Planning | 2120405 |
| Construction | Splice 02/12/25 | A | 2/12/2025 | SHELLEY | SHELLEY | dimensions, details, joints, drain location | | Construction | 2120231 |
| County Zoning | Splice 12/10/24 | A | 1/8/2025 | DSDDEAN2 | DSDDEAN2 | Fees will be due to Woodmen Road Metro District per agency comments on the Site Development Plan review copied below....
This proposed project is located within the Woodmen Road Metropolitan District boundaries. The District assess’ platting and building permit fees for new development within the District Boundaries, the District also assess’ a mill levy on property within the District Boundaries.
The fees for this year are as follows: Platting Fees: Commercial: $1540/acre Residential: $385.00/lot
Building Permit Fees: Commercial: Destination retail/hotel: $1.37/square foot Convenience Commercial: $5.51/Sq Ft All Other Uses: $1.10/square foot | | County Zoning | 2106193 |
| Plumbing | Splice 12/10/24 | A | 12/26/2024 | SHANEN | SHANEN | Revised sheet P1.1A, P2.1A, P3.1A, P3.2B and P6.0. | | Plumbing | 2102664 |
| Submittal 2 | Splice 12/10/24 | / | 12/26/2024 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2102626 |
| Electrical | Splice 12/10/24 | A | 12/19/2024 | BERTHA | BERTHA | Revised power and lighting | | Electrical | 2100960 |
| Electronic Plan | Splice 12/10/24 | / | 12/19/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2100946 |
| County Zoning | Splice 12/10/24 | D | 12/17/2024 | DSDDEAN2 | DSDDEAN2 | Please include approved Site Development Plan from Planning an Community Development at File No PPR246. | | County Zoning | 2100082 |
| Falcon Fire (CSFD) | Splice 12/10/24 | A | 12/12/2024 | CSFIRE | CSFIRE | Splice dated 12.10.24 approved for clouded revs only | phil.valdez | Falcon Fire (CSFD) | 2098038 |
| Zoning/Planning | Splice 12/10/24 | / | 12/11/2024 | DSDDEAN2 | DSDDEAN2 | In Current Review by DSDDEAN2 | | Zoning/Planning | 2097841 |
| Mechanical | Splice 12/10/24 | A | 12/11/2024 | DALEH | DALEH | Clouds | | Mechanical | 2097805 |
| Construction | Splice 12/10/24 | A | 12/11/2024 | SHELLEY | SHELLEY | Dimensions, details, and structural clarifications. | | Construction | 2097791 |
| Plumbing | Splice 12/10/24 | D | 12/11/2024 | SHANEN | SHANEN | * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2097323 |
| Energy | Original | A | 10/16/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2073469 |
| Plumbing | Original | A | 10/16/2024 | SHANEN | SHANEN | | | Plumbing | 2073468 |
| Construction | Original | A | 10/9/2024 | SHELLEY | SHELLEY | | | Construction | 2070523 |
| Enumeration | Original | A | 10/8/2024 | AMY | AMY | | | Enumeration | 2069566 |
| Electronic Plan | Original | / | 10/8/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2069555 |
| | Original | / | 10/8/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2069537 |
| | Original | / | 10/8/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2069369 |
| Submittal 3 | Original | / | 10/8/2024 | QUINTONW | QUINTONW | Submittal #3 | | Submittal 3 | 2069368 |
| Falcon Fire (CSFD) | Original | A | 10/4/2024 | CSFIRE | CSFIRE | You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | Jacob.Watson | Falcon Fire (CSFD) | 2068696 |
| Energy | Original | D | 9/30/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2065914 |
| Plumbing | Original | D | 9/30/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2065913 |
| Electrical | Original | A | 9/23/2024 | BERTHA | BERTHA | | | Electrical | 2063197 |
| Electronic Plan | Original | / | 9/23/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2063111 |
| Health Dept. | Original | N | 9/20/2024 | HEALTHDEPT | HEALTHDEPT | Construction activity permit PT1517 is valid from 08/26/2024 - 02/26/2025. To continue any earthmoving operations after 02/26/2025, please reapply for a new permit online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/. For questions, contact Environmental Health at 719-578-3199 option 3. Per Frank, child care facility is drop off for facility patrons only. TG | tguerrero | Health Dept. | 2063065 |
| Mechanical | Original | A | 9/20/2024 | DALEH | DALEH | | | Mechanical | 2062958 |
| Construction | Original | D | 9/20/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2062814 |
| Elevators | Original | A | 9/19/2024 | ERIC | ERIC | Otis Hydrofit machineroom-less hydraulic elevator w/attached control space. No generator, 2019 code. | | Elevators | 2062418 |
| Enumeration | Original | A | 9/19/2024 | AMY | AMY | | | Enumeration | 2062393 |
| Electronic Plan | Original | / | 9/19/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2062377 |
| Submittal 2 | Original | / | 9/19/2024 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 2062342 |
| County Zoning | Original | A | 8/28/2024 | DSDDEAN2 | DSDDEAN2 | | | County Zoning | 2052673 |
| Falcon Fire (CSFD) | Original | D | 8/26/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | Jacob.Watson | Falcon Fire (CSFD) | 2051630 |
| Electrical | Original | D | 8/20/2024 | BERTHA | BERTHA | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2049123 |
| Energy | Original | D | 8/20/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2049124 |
| Electronic Plan | Original | / | 8/20/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2048966 |
| Health Dept. | Original | D | 8/16/2024 | HEALTHDEPT | HEALTHDEPT | Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/. For questions, contact Environmental Health at 719-578-3199 option 3. KB | KBauer | Health Dept. | 2047617 |
| Mechanical | Original | D | 8/14/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2046571 |
| Electronic Plan | Original | / | 8/13/2024 | DALEH | DALEH | In Current Review by DALEH | | Electronic Plan | 2045921 |
| Zoning/Planning | Original | / | 8/13/2024 | DSDDEAN2 | DSDDEAN2 | In Current Review by DSDDEAN2 | | Zoning/Planning | 2045901 |
| Plumbing | Original | D | 8/13/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2045665 |
| Elevators | Original | D | 8/12/2024 | ERIC | ERIC | Please provide elevator submittals.
See TS2.1, TS1.1 and E2.1A . 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Elevators | 2045263 |
| Construction | Original | D | 8/12/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2045219 |
| Electronic Plan | Original | / | 8/9/2024 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 2044325 |
| Enumeration | Original | A | 8/1/2024 | AMY | AMY | | | Enumeration | 2040394 |
| Electronic Plan | Original | / | 7/31/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2040360 |
| Floodplain | Original | N | 7/31/2024 | KEITH | KEITH | | | Floodplain | 2040270 |
| Energy | Original | / | 7/30/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2039131 |
| Floodplain | Original | / | 7/30/2024 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 4220303093) | | Floodplain | 2039129 |