CO Springs DRE | Original | A | 10/23/2024 | MAMBUUL | MAMBUUL | Approved for commercial interior/exterior remodel. Documentation provided per pre-application summary letter. See previous approval approval comments. (see full review) | | CO Springs DRE | 2076060 |
Zoning/Planning | Original | / | 10/21/2024 | MAMBUUL | MAMBUUL | In Current Review by MAMBUUL | | Zoning/Planning | 2075261 |
Energy | Original | A | 10/21/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2075209 |
Electrical | Original | A | 10/21/2024 | DANIELG | DANIELG | | | Electrical | 2075208 |
Construction | Original | A | 10/21/2024 | BPHILLIPS | BPHILLIPS | | | Construction | 2075195 |
| Original | / | 10/21/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2074989 |
| Original | / | 10/18/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2074508 |
Submittal 3 | Original | / | 10/18/2024 | QUINTONW | QUINTONW | Submittal #3 | | Submittal 3 | 2074507 |
Energy | Original | D | 9/26/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2064982 |
Electrical | Original | D | 9/26/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2064981 |
CO Springs DRE | Original | A | 9/25/2024 | MAMBUUL | MAMBUUL | Approved for commercial interior/exterior remodel. Parking counts per parking table provided for retail sales, medium. Exterior facade requirements met per UDC 7.4.1103. (see full review) | | CO Springs DRE | 2064409 |
Zoning/Planning | Original | / | 9/25/2024 | MAMBUUL | MAMBUUL | In Current Review by MAMBUUL | | Zoning/Planning | 2064247 |
Construction | Original | D | 9/25/2024 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2064186 |
Electronic Plan | Original | / | 9/25/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2064171 |
Enumeration | Original | N | 9/24/2024 | BECKYA | BECKYA | | | Enumeration | 2064128 |
Submittal 2 | Original | / | 9/24/2024 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 2063699 |
CO Springs Fire | Original | A | 8/29/2024 | CSFIRE | CSFIRE | You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | chiptaylor | CO Springs Fire | 2053181 |
CO Springs Hazmat | Original | N | 8/29/2024 | CSFIRE | CSFIRE | | chiptaylor | CO Springs Hazmat | 2053180 |
Energy | Original | D | 8/21/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2049977 |
Electrical | Original | D | 8/21/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2049976 |
Electronic Plan | Original | / | 8/21/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2049928 |
CO Springs DRE | Original | D | 8/14/2024 | MOBRIEN | MOBRIEN | Proposed work includes addition of a pharmacy drive-through, new pickup area, and reconfiguration of parking layout. Land Use entitlement is required. Please request a pre-application meeting (coloradosprings.gov/preapp) or upload approved development plan with Land Use Review stamp. (see full review) | | CO Springs DRE | 2046723 |
Zoning/Planning | Original | / | 8/14/2024 | MOBRIEN | MOBRIEN | In Current Review by MOBRIEN | | Zoning/Planning | 2046708 |
Mechanical | Original | A | 8/14/2024 | TCRIPPEN | TCRIPPEN | Approved | | Mechanical | 2046541 |
CSU Water | Original | N | 8/14/2024 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. No new water service outside of building. MDA | malcuran | CSU Water | 2046287 |
CSU Waste Water | Original | N | 8/14/2024 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. No new wastewater service outside of building. MDA | malcuran | CSU Waste Water | 2046286 |
Plumbing | Original | A | 8/14/2024 | SHANEN | SHANEN | | | Plumbing | 2046281 |
Electronic Plan | Original | / | 8/14/2024 | SHANEN | SHANEN | In Current Review by SHANEN | | Electronic Plan | 2046278 |
Construction | Original | D | 8/13/2024 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2046147 |
Health Dept. | Original | A | 8/12/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment approved in plan review. A pre-operational inspection will be required before final approval for opening is granted. KB | KBauer | Health Dept. | 2045171 |
Electronic Plan | Original | / | 8/12/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2045073 |
Health Dept. | Original | D | 8/8/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment plan review is in process and not yet approved. If your assigned plan reviewer has questions, they will contact you directly. For questions, contact Environmental Health at 719-578-3199 option 3. KB | KBauer | Health Dept. | 2043674 |
Enumeration | Original | N | 7/31/2024 | AMY | AMY | | | Enumeration | 2040305 |
Electronic Plan | Original | / | 7/31/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2040299 |
Energy | Original | / | 7/31/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2039890 |
Floodplain | Original | N | 7/31/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6404318055) | | Floodplain | 2039889 |