Mechanical | Original | A | 10/18/2024 | TREVORH | TREVORH | Approved; | | Mechanical | 2074403 |
Plumbing | Original | D | 10/17/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2073939 |
Gas/Elec. Utils | Original | D | 10/17/2024 | CSUREVIEW | CSUREVIEW | Not in Colorado Springs Utilities' electric or gas service territory. mjg | mgackle | Gas/Elec. Utils | 2073751 |
Construction | Original | A | 10/16/2024 | SHELLEY | SHELLEY | | | Construction | 2073682 |
Enumeration | Original | D | 10/16/2024 | AMY | AMY | Approval of plan in Enumerations is pending the review of the pre-plat, plat fees and a copy of the final recorded plat being sent to this department. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 2073458 |
Electronic Plan | Original | / | 10/16/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2073438 |
Submittal 2 | Original | / | 10/16/2024 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 2073297 |
Security Hazmat | Original | A | 10/10/2024 | SECURITYFIRE | SECURITYFIRE | OK MAS For SFD - NO STAMP The CO2 Beberage System will be a defered submittal. | SecurityFD1 | Security Hazmat | 2071169 |
Security Fire | Original | A | 10/10/2024 | SECURITYFIRE | SECURITYFIRE | OK MAS For SFD - NO STAMP The Hood Supression System will be a defered submittal. | SecurityFD1 | Security Fire | 2071166 |
Enumeration | Original | D | 10/3/2024 | AMY | AMY | It was my understanding that lots 1-6 would be addressed from Center Village Heights. In speaking with my Co-worker, lot 1-5 are addressed from Fontaine Blvd and not Center Village Dr. Please edit all addressing to this address-9664 Fontaine Blvd. Sorry for the confusion. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 2067640 |
Health Dept. | Original | A | 9/26/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment approved in plan review. A pre-operational inspection will be required before final approval for opening is granted. Install handwashing sink in the kitchen area prior to final inspection. MT | mtemple | Health Dept. | 2065228 |
Energy | Original | D | 9/23/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2063110 |
Electrical | Original | D | 9/23/2024 | BERTHA | BERTHA | Provide all conduit/conductor size, type CU or AL and quantity on the one-line
Provide fault current information (SCCR, AIC, SCA) in tabular format for all of the following locations. 1. All new panelboards and switchboards 2. All new transfer equipment 3. All new industrial control panels 4. All new air conditioning and refrigeration equipment 5. At any of the above locations when refed
Provide room names on plans.
Provide footprint (site plan) showing all electrical service equipment and disconnects serving the structure - include ct's, meters, etc
Comply with 2021 IECC
Indicate compliance with C402.5.10 for recessed lighting on the lighting schedule.
Vestibules must be identified on plans as conditioned or unconditioned. If the vestibule is conditioned or an air curtain is specified, show compliance with C403.4.1.4.
Provide a note on the Electrical Plan specifying refrigeration performance per C403.11 and C403.11.3.
Lighting controls must be clearly shown and must comply with C405.2 (Interior), C405.2.7 (Exterior),and C405.2.8 (Parking Garages), where applicable.
Where applicable, Daylight Zones must be shown on the plans per C405.2.4.2 through C405.2.4.4.
Provide a note on the plans indicating that the Electrical design has a maximum volt drop of 5% per C405.10.
Controlled receptacles must be shown on the plan per C405.11 and the symbol used to mark these receptacles must be as shown in article 406.3(E) of the adopted National Electrical Code (NEC).
The following general note must be included on the electrical plans: “A Final Commissioning Report shall be delivered to the building owner per section C408.2.5 of the 2021 IECC.”
1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2063109 |
Widefield Water | Original | D | 9/16/2024 | WIDEFIELDWSD | WIDEFIELDWSD | Need a backflow preventer after the meter. | Widefield_Eng | Widefield Water | 2060590 |
Widefield Waste Water | Original | A | 9/16/2024 | WIDEFIELDWSD | WIDEFIELDWSD | | Widefield_Eng | Widefield Waste Water | 2060583 |
Mechanical | Original | D | 9/13/2024 | TREVORH | TREVORH | Disapproved; 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2060014 |
Health Dept. | Original | D | 9/13/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment plan review is in process and not yet approved. If your assigned plan reviewer has questions, they will contact you directly.
Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/.
For questions, contact Environmental Health at 719-578-3199 option 3. AM | Amanda Furno | Health Dept. | 2059919 |
County Zoning | Original | D | 9/10/2024 | DSDLETKE | DSDLETKE | The site development PPR2427 has not been approved.
PPR approval is required prior to issuance of building permit.
Please call Senior Planner/Project Manager Scott Weeks 719-520-7952 for questions or concerns.
Joe Letke Planner joeletke@elpasoco.com | | County Zoning | 2058041 |
Plumbing | Original | D | 9/10/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2057927 |
Zoning/Planning | Original | / | 9/10/2024 | DSDLETKE | DSDLETKE | In Current Review by DSDLETKE | | Zoning/Planning | 2057887 |
Gas/Elec. Utils | Original | D | 9/10/2024 | CSUREVIEW | CSUREVIEW | Not in Colorado Springs Utilities' electric service territory. ------------------------------------------------------------------------------------------------------------------------ Not in Colorado Springs Utilities' gas service territory. MLW | mlwilliams | Gas/Elec. Utils | 2057854 |
Electronic Plan | Original | / | 9/9/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 2057799 |
CSU Contract Admin. | Original | N | 9/9/2024 | CSUAPPSPRM | CSUAPPSPRM | Outside of CSU service territory. Will need to follow up with correct provider for applicable fees. JMD | jdemello | CSU Contract Admin. | 2057792 |
Construction | Original | D | 9/9/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2057767 |
Electronic Plan | Original | / | 9/9/2024 | DOUGC | DOUGC | In Current Review by DOUGC | | Electronic Plan | 2057477 |
Enumeration | Original | D | 9/9/2024 | AMY | AMY | Provide a site plan of the enter lot within the Architectural sheets for Enumerations purposes. The site plan should include all proposed structures, driveway access, north arrow. Enumerations should not be marking up the development plan. If the trash enclosure exceeds 7’, a separate address will need to be assigned along with a separate permit. Please clarify.
The plat is still pending for this area. Enumerations will need to review the pre-plat, collect plat fees and receive a copy of the final recorded plat prior to approving this plan in the Enumerations department. Email a copy of the recorded plat to Amy@pprbd.org | | Enumeration | 2057402 |
Elevators | Original | N | 9/9/2024 | ERIC | ERIC | No conveyance | | Elevators | 2057362 |
Electronic Plan | Original | / | 9/9/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2057337 |
Hazmat | Original | / | 9/9/2024 | SYSTEM | SYSTEM | You will need to contact Hazmat department for approval prior to permit. This department will not review the plan electronically. | | Hazmat | 2057283 |
Fire | Original | / | 9/9/2024 | SYSTEM | SYSTEM | You will need to contact Fire department for approval prior to permit. This department will not review the plan electronically. | | Fire | 2057284 |
Energy | Original | / | 9/9/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2057282 |
Floodplain | Original | N | 9/9/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 5515413054) | | Floodplain | 2057281 |