| Energy | Original | D | 2/25/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2270828 |
| Mechanical | Original | D | 2/25/2026 | TCRIPPEN | TCRIPPEN | Disapproved see Elevator notes * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2270827 |
| Plumbing | Original | D | 2/20/2026 | SHANEN | SHANEN | Preliminary review. Provide only P sheets. Compliance with 2021 IPC and CO state amendments to 2021 IPC must be stated on the plumbing plans. Show compliance with commercial plumbing plan review additional requirements for 2021 IECC. Each building shall comply with section 403.1 an approved variance will be required otherwise. Provide a two way fitting or two riser clean-out at the junction of the building drain and building sewer in compliance with CO state amendment to section 708.1.3. Elevator sump discharge must show compliance with section 301.6 Exception: Floor drains, sumps and sump pumps shall be permitted at the base of the shaft, provided that they are indirectly connected to the plumbing system. Discharge elevator sump indirectly to a waste receptor capable of handling a minimum of 50 gpm (100 dfu). Provide gpm and/or square footage served by each component of the roof drainage system. Provide enlarged plumbing plans for all restrooms in building A. Alternates not considered. Provide a piping materials schedule. Provide required water pipe size analysis data, see 2021 IPC appendix E. Data must include: service pressure, service size, meter size, pressure loss, available pressure, distribution size, WSFU served, developed length, etc. Provide Isometric drawings for all restrooms in building A. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2268900 |
| Electrical | Original | D | 2/19/2026 | DANIELG | DANIELG | * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2268741 |
| Electronic Plan | Original | / | 2/19/2026 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2268703 |
| Elevators | Original | D | 2/19/2026 | ROBERTV | ROBERTV | Need site specific shop drawings and power data for all elevators being installed. All elevator shop drawing and power data information must be situated in all of the required pages of this planset to include all work by others. Dimensions, notes and layouts must match in all trade pages. These submittals cannot be deferred and cannot use Basis of Design. Without these, a review cannot be performed and will continue to be disapproved
Also see sheets: G001A, A705A, M201A, E500A, P800A . * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Elevators | 2268642 |
| County Zoning | Original | D | 2/18/2026 | DSDUHLER | DSDUHLER | Please contact Miranda Benson in Planning to complete submittal of the Site Development Plan discussed during EA2588. Her contact information is 719-520-7940 and mirandabenson@elpasoco.com. | | County Zoning | 2268108 |
| Zoning/Planning | Original | / | 2/18/2026 | DSDUHLER | DSDUHLER | In Current Review by DSDUHLER | | Zoning/Planning | 2267982 |
| Gas/Elec. Utils | Original | A | 2/13/2026 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. SSH | SHillman | Gas/Elec. Utils | 2266727 |
| EPC Health Dept | Original | D | 2/13/2026 | HEALTHDEPT | HEALTHDEPT | Not applicable to schools program per MLL.
Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/. For questions, contact Environmental Health at 719-578-3199 option 3. AM | Amanda Furno | EPC Health Dept | 2266703 |
| Construction | Original | D | 2/13/2026 | DOUGC | DOUGC | Life Safety Plan // Code Study Form // Architectural * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2266562 |
| Electronic Plan | Original | / | 2/9/2026 | DOUGC | DOUGC | In Current Review by DOUGC | | Electronic Plan | 2264784 |
| Enumeration | Original | D | 1/20/2026 | AMY | AMY | The 10 digit tax schedule number is not exempt but required and can be found on the El Paso County Assessor’s website above the address. A wrecking permit is required to be in place for the existing 6155 Fountain Valley School Road structure, prior to approval of this plan. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Enumeration | 2257545 |
| Electronic Plan | Original | / | 1/20/2026 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2257526 |
| Floodplain | Original | N | 1/19/2026 | KEITH | KEITH | | | Floodplain | 2257504 |
| | Original | / | 1/16/2026 | SYSTEM | SYSTEM | Plan Review fees paid 01/16/2026 for plan submitted 01/15/2026. Submit Date updated to now. Plan now open for review. | | | 2257459 |
| Fire | Original | / | 1/15/2026 | SYSTEM | SYSTEM | You will need to contact Fire department for approval prior to permit. This department will not review the plan electronically. | | Fire | 2256671 |
| Hazmat | Original | / | 1/15/2026 | SYSTEM | SYSTEM | You will need to contact Hazmat department for approval prior to permit. This department will not review the plan electronically. | | Hazmat | 2256670 |
| Energy | Original | / | 1/15/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2256669 |
| Floodplain | Original | / | 1/15/2026 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 5500000164) | | Floodplain | 2256668 |