| Electrical | Original | A | 8/12/2026 | CONNERM | CONNERM | | | Electrical | 2346870 |
| Electronic Plan | Original | / | 8/12/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2346860 |
| Elevators | Original | A | 8/12/2026 | ROBERTV | ROBERTV | Modernization to Conventional Hydraulic Elevator w/ Machine Room. A17.1 - 2019, 2023 RBC | | Elevators | 2346850 |
| | Original | / | 8/3/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2342238 |
| | Original | / | 7/29/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2340522 |
| Submittal 3 | Original | / | 7/29/2026 | TREYW | TREYW | Submittal #3 | | Submittal 3 | 2340521 |
| Electrical | Original | D | 7/21/2026 | CONNERM | CONNERM | Show evidence of selective coordination per 620.62 * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2337199 |
| Electrical | Original | D | 7/21/2026 | CONNERM | CONNERM | Provide panel schedule with demand load in amps
For SCA that exceeds AIC, let-through current of current limiting fuses is not allowed for mitigating the excess fault current.
Clarify as fully rated or series rated. If series rated, provide series rated tested combinations
Provide withstand rating for equipment * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2336861 |
| Electrical | Original | D | 7/21/2026 | CONNERM | CONNERM | Provide panel schedule with demand load in amps * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2336739 |
| Electronic Plan | Original | / | 7/21/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2336730 |
| Mechanical | Original | N | 7/21/2026 | DALEH | DALEH | Per Robert V machine room ventilation is existing | | Mechanical | 2336676 |
| Elevators | Original | D | 7/20/2026 | ROBERTV | ROBERTV | Submittal still incomplete:
- Need to provide all specs and data of equipment being replaced to include Short Circuit Current Rating (SCCR) of elevator controller to be used as described in the PPRBD Modernization Guidance Document. This needs to be uploaded under 'Elevator Equipment Specs and Scope of Work'. Please include Elevator Technicians Scope of Work document at the beginning of this single PDF, we will not accept more than one PDF under 'Elevator Equipment Spec's and Scope Of Work'.
Who is performing the work by others as listed in the PPRBD Survey ? They need to provide you with a letter head document that lists their scope of work and it needs to be uploaded under 'Work by Others Scope'.
Re-Review All
Please read PPRBD Modernization Guidance Document thoroughly and ensure all the information is provided before resubmitting. Copy and Paste link: https://www.pprbd.org/File/ByAlias/Modernizationconveyance . * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Elevators | 2336623 |
| Submittal 2 | Original | / | 7/20/2026 | MELISSAF | MELISSAF | Submittal #2 | | Submittal 2 | 2336287 |
| Plumbing | Original | N | 7/9/2026 | SHANEN | SHANEN | | | Plumbing | 2332444 |
| Mechanical | Original | D | 7/9/2026 | DALEH | DALEH | Provide mechanical drawings showing how equipment room will be ventilated * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2332329 |
| Electrical | Original | D | 7/8/2026 | CONNERM | CONNERM | Pending Elevators approval * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2332109 |
| Electronic Plan | Original | / | 7/8/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2332105 |
| Elevators | Original | D | 7/8/2026 | ROBERTV | ROBERTV | Submittal is incomplete. Please follow Modernization Guidance Document Link: https://www.pprbd.org/File/ByAlias/Modernizationconveyance
Also See Code Study Form Section 1.0 and 4.0 . * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Elevators | 2332059 |
| Construction | Original | N | 7/8/2026 | SHELLEY | SHELLEY | No construction scope | | Construction | 2331993 |
| Floodplain | Original | N | 7/8/2026 | BECKYA | BECKYA | | | Floodplain | 2331555 |
| | Original | / | 7/7/2026 | SYSTEM | SYSTEM | Plan Review fees paid 07/07/2026 for plan submitted 06/30/2026. Submit Date updated to now. Plan now open for review. | | | 2331169 |
| Energy | Original | N | 6/30/2026 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2328807 |
| Floodplain | Original | / | 6/30/2026 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 7413401025) | | Floodplain | 2328806 |