| CO Springs DRE | Original | A | 8/17/2026 | SSADLER | SSADLER | Previous approval comments still apply | | CO Springs DRE | 2348778 |
| Energy | Original | D | 8/17/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2348440 |
| Electrical | Original | D | 8/17/2026 | CONNERM | CONNERM | Show compliance with CSU LESS 5.04 * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2348439 |
| Zoning/Planning | Original | / | 8/17/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2348418 |
| Electronic Plan | Original | / | 8/17/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2348416 |
| Enumeration | Original | A | 8/17/2026 | AMY | AMY | Address assigned to the meter is 1581 Space Center Drive | | Enumeration | 2348372 |
| Electronic Plan | Original | / | 8/17/2026 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2348313 |
| Submittal 2 | Original | / | 8/17/2026 | NICOLASV | NICOLASV | Submittal #2 | | Submittal 2 | 2348306 |
| CO Springs Hazmat | Original | D | 8/4/2026 | CSFIRE | CSFIRE | DFM-C-DC-26-00006 Groouped too many togeter without proper seperation. The 8 vehicles must be separated from all other vehicles. ESO is too far from the last charging station (112FT). Please ensure proper DCFC LV-3 Signage. See markups on the Electrical plan set. FDMUS You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | mark.stanwood@colora | CO Springs Hazmat | 2343094 |
| CO Springs Fire | Original | N | 7/27/2026 | CSFIRE | CSFIRE | No Fire Final
HAZ-MAT REVIEW REQUIRED Based upon the information provided, a hazardous materials review is required. Your plans have been forwarded to the HazMat reviewer.
HAZMAT AND HIGHPILE INSPECTIONS Call 719-385-5978 Option 5 to schedule all hazmat and high pile inspections. | Jacob.Watson | CO Springs Fire | 2339665 |
| CO Springs DRE | Original | A | 7/14/2026 | SSADLER | SSADLER | Approved for proposed Level 3 charging stations. All entitlement approvals are on file. | | CO Springs DRE | 2333874 |
| Zoning/Planning | Original | / | 7/13/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2333304 |
| Gas/Elec. Utils | Original | A | 7/10/2026 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. PSD | PDosch | Gas/Elec. Utils | 2332911 |
| Energy | Original | D | 7/10/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2332898 |
| Electrical | Original | D | 7/10/2026 | CONNERM | CONNERM | Provide fault current information (SCCR, AIC, SCA) at all of the following locations. 1. All new panelboards and switchboards 2. All new transfer equipment 3. All new industrial control panels 4. All new air conditioning and refrigeration equipment 5. At any of the above locations when refed
Comply with 250.122
Verify compliance with CSU LESS 5.04 * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2332897 |
| Electronic Plan | Original | / | 7/10/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2332881 |
| Construction | Original | N | 7/10/2026 | SHELLEY | SHELLEY | No construction scope | | Construction | 2332869 |
| Enumeration | Original | D | 7/8/2026 | AMY | AMY | Provide the location of the meter so that a separate address can be assigned. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Enumeration | 2332026 |
| Electronic Plan | Original | / | 7/8/2026 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2331895 |
| | Original | / | 7/8/2026 | SYSTEM | SYSTEM | Plan Review fees paid 07/08/2026 for plan submitted 07/08/2026. Submit Date updated to now. Plan now open for review. | | | 2331892 |
| Energy | Original | / | 7/8/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2331799 |
| Floodplain | Original | N | 7/8/2026 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6401404016) | | Floodplain | 2331798 |