| CO Springs Fire | Original | A | 11/17/2026 | CSFIRE | CSFIRE | CSFD FCS: You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | chiptaylor | CO Springs Fire | 2383405 |
| CO Springs DRE | Original | D | 11/16/2026 | SSADLER | SSADLER | Upload the following documents: final approved and stamped development plan final approval letter final approved landscaping and irrigation plans final recorded plat Fees will be owed prior to building permit issuance. Contact Charla at charla.hudspeth@coloradosprings.gov for more information. | | CO Springs DRE | 2382739 |
| EPC Health Dept | Original | D | 11/16/2026 | HEALTHDEPT | HEALTHDEPT | Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/. Please submit all applications through https://myhealthdepartment.com/EPCPH.
Retail food establishment approved in plan review. A pre-operational inspection will be required before final approval for opening is granted.
For questions, contact Environmental Health at 719-578-3199 option 3. AB | abrannon | EPC Health Dept | 2382596 |
| Energy | Original | D | 11/16/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2382515 |
| Plumbing | Original | D | 11/16/2026 | SHANEN | SHANEN | CSU approved construction drawings and utility service plan required to verify the plumbing plans correspond with the CSU approved plans for water service sizing, water entry location, building drain sizing, building drain location, grease interceptor location, etc. Toilet facilities must show compliance with CO state amendment to section 403.1 added sentence to end of section. Lavatory to water closet ratios in accordance with table 403.1 shall be maintained in all restrooms. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2382514 |
| City Engr | Original | D | 11/13/2026 | HVO | HVO | See previous comment | | City Engr | 2382291 |
| Mechanical | Original | D | 11/13/2026 | TREVORH | TREVORH | Disapproved; Mechanical approval is pending the site specific Solar ready Roof plan * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2382281 |
| Stormwater | Original | D | 11/13/2026 | JDUNCAN | JDUNCAN | GEC Amendment not approved and GEC assurance increase not yet collected. JMD | | Stormwater | 2382097 |
| Electrical | Original | D | 11/13/2026 | CONNERM | CONNERM | Provide fault current information (SCCR, AIC, SCA) at all of the following locations in tabular form 1. All new panelboards and switchboards 2. All new transfer equipment 3. All new industrial control panels 4. All new air conditioning and refrigeration equipment 5. At any of the above locations when refed
Clarify AIC of equipment. Panel schedules say 42K and 65/10AIC
SCA exceeds AIC
Provide floor plan for office * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2382035 |
| CSU Electric | Original | D | 11/13/2026 | CSUREVIEW | CSUREVIEW | Submit Electric Load Data Form to CSU Field Engineering. Form can be found at: https://www.csu.org/hubfs/Document-Library/ElectricLoadData.pdf?hsLang=en,Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions.-DT | dytrujillo | CSU Electric | 2381927 |
| Electronic Plan | Original | / | 11/13/2026 | SHANEN | SHANEN | In Current Review by SHANEN | | Electronic Plan | 2381919 |
| Zoning/Planning | Original | / | 11/12/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2381789 |
| CSU Contract Admin. | Original | D | 11/12/2026 | CSUAPPSPRM | CSUAPPSPRM | Same comment as previously provided on 10/08/2026: Requires approved Commercial Water Meter Sizing Form (CWMSF) and payment of applicable utility charges and fees. Please contact Customer Contract Administration at 719-668-8111 for additional information on charges/fees and to request an estimate. CWMSF available online at:
https://www.csu.org/CSUDocuments/watermetersizingforminteractive.pdf
AMS | ASweet | CSU Contract Admin. | 2381782 |
| CSU Water | Original | D | 11/12/2026 | CSUREVIEW | CSUREVIEW | Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions. PSD | PDosch | CSU Water | 2381768 |
| CSU Waste Water | Original | D | 11/12/2026 | CSUREVIEW | CSUREVIEW | Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions. PSD | PDosch | CSU Waste Water | 2381765 |
| Electronic Plan | Original | / | 11/12/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2381761 |
| Construction | Original | D | 11/12/2026 | SHELLEY | SHELLEY | Still need solar ready roof plan per Colorado Model Electric Ready and Solar Ready Code. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2381747 |
| Enumeration | Original | A | 11/11/2026 | AMY | AMY | Addressing was added to sheet A1.3, if this page get changed out, add the addresses back to this sheet. The addresses are running parallel to the street they are addressed from. 1 Plan 4 permits are required. 520-store, 522-trash enclosure, 524-ev charger, 526-gas canopy. | | Enumeration | 2381052 |
| Electronic Plan | Original | / | 11/11/2026 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2381026 |
| Submittal 2 | Original | / | 11/11/2026 | MELISSAF | MELISSAF | Submittal #2 | | Submittal 2 | 2380933 |
| CO Springs Hazmat | Original | D | 11/2/2026 | CSFIRE | CSFIRE | Hazmat Record #: DFM-C-HM-26-00048
See markups on plans. Need interior ESO for fuel pumps.
Separate submittals directly to CSFD required for LPG Exchange Cage, CO2 Beverage Dispensing, and UST Storage/Dispensing | smitty91 | CO Springs Hazmat | 2377534 |
| CO Springs Fire | Original | D | 10/15/2026 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | Jacob.Watson | CO Springs Fire | 2371285 |
| Energy | Original | D | 10/13/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2370332 |
| Mechanical | Original | D | 10/13/2026 | TREVORH | TREVORH | Mechanical approval is pending the site specific Solar ready Roof plan * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2370331 |
| CO Springs DRE | Original | D | 10/12/2026 | SSADLER | SSADLER | Upload the following documents: final approved and stamped development plan final approval letter final approved landscaping and irrigation plans final recorded plat Fees will be owed prior to building permit issuance. Contact Charla at charla.hudspeth@coloradosprings.gov for more information. | | CO Springs DRE | 2369668 |
| Electrical | Original | D | 10/12/2026 | CONNERM | CONNERM | Show compliance with 514.11
Provide seal off detail. Must comply with 514.9
Provide fault current information (SCCR, AIC, SCA) - in tabular format - at all of the following locations. 1. All new panelboards and switchboards 2. All new transfer equipment 3. All new industrial control panels 4. All new air conditioning and refrigeration equipment 5. At any of the above locations when refed
Electrical plans must have room names
Provide series rated listed combinations
Provide a note on the Electrical Plan specifying refrigeration performance per C403.11 and C403.11.3.
Where applicable, Daylight Zones must be shown on the plans per C405.2.4.2 through C405.2.4.4.
Controlled receptacles must be shown on the plan per C405.11 and the symbol used to mark these receptacles must be as shown in article 406.3(E) of the adopted National Electrical Code (NEC).
Provide a note on the plans indicating that the Electrical design has a maximum volt drop of 5% per C405.10.
The following general note must be included on the electrical plans: “A Final Commissioning Report shall be delivered to the building owner per section C408.2.5 of the 2021 IECC.”
For a full list of IECC requirements please see: https://www.pprbd.org/File/ByAlias/ElectricalReview
Comply CO MERSRC: -CE301.1 -CS401.1 -CS410.1 -CV501.1
Complete re-review necessary * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2369575 |
| Plumbing | Original | D | 10/9/2026 | SHANEN | SHANEN | CSU approved construction drawings and utility service plan required to verify the plumbing plans correspond with the CSU approved plans for water service sizing, water entry location, building drain sizing, building drain location, grease interceptor location, etc. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2369477 |
| Electronic Plan | Original | / | 10/9/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2369466 |
| Elevators | Original | N | 10/9/2026 | ROBERTV | ROBERTV | No Conveyances | | Elevators | 2369419 |
| Stormwater | Original | D | 10/9/2026 | JDUNCAN | JDUNCAN | Please upload approved PCM plans. | | Stormwater | 2369284 |
| EPC Health Dept | Original | D | 10/9/2026 | HEALTHDEPT | HEALTHDEPT | Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/construction-land-use/construction-activity-permit/. Please submit all applications through https://myhealthdepartment.com/EPCPH.
Retail food establishment plan review is in process and not yet approved. If your assigned plan reviewer has questions, they will contact you directly.
For questions, contact Environmental Health at 719-578-3199 option 3. AM | Amanda Furno | EPC Health Dept | 2369228 |
| City Engr | Original | D | 10/9/2026 | DSOSA | DSOSA | Please upload the approved Development Plan and Construction Drawings to the building permit plan set. | | City Engr | 2369187 |
| CSU Waste Water | Original | D | 10/8/2026 | CSUREVIEW | CSUREVIEW | Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions. PSD | PDosch | CSU Waste Water | 2368945 |
| CSU Water | Original | D | 10/8/2026 | CSUREVIEW | CSUREVIEW | Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions.
Refer to details B4-16 through B4-22 and select an appropriate meter clearance detail to include on the plumbing plans. PSD | PDosch | CSU Water | 2368943 |
| CSU Contract Admin. | Original | D | 10/8/2026 | CSUAPPSPRM | CSUAPPSPRM | Requires approved Commercial Water Meter Sizing Form (CWMSF) and payment of applicable utility charges and fees. Please contact Customer Contract Administration at 719-668-8111 for additional information on charges/fees and to request an estimate. CWMSF available online at:
https://www.csu.org/CSUDocuments/watermetersizingforminteractive.pdf
AMS | ASweet | CSU Contract Admin. | 2368923 |
| CSU Gas | Original | A | 10/8/2026 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas meter, service line location. Contact Field Engineering at 719-668-4985 (Gas) for service line approval form or with any questions. AM | amagoon | CSU Gas | 2368875 |
| CSU Electric | Original | D | 10/8/2026 | CSUREVIEW | CSUREVIEW | Submit Electric Load Data Form to CSU Field Engineering. Form can be found at: https://www.csu.org/hubfs/Document-Library/ElectricLoadData.pdf?hsLang=en,Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions.-DT | dytrujillo | CSU Electric | 2368835 |
| Zoning/Planning | Original | / | 10/8/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2368829 |
| Construction | Original | D | 10/8/2026 | BRIANB | BRIANB | missing solar ready roof plan / see sheets - A1.5 / A2.3 / A2.8 / see code study form * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2368804 |
| Electronic Plan | Original | / | 10/5/2026 | BRIANB | BRIANB | In Current Review by BRIANB | | Electronic Plan | 2366852 |
| Enumeration | Original | A | 10/1/2026 | AMY | AMY | 1 Plan 4 permits are required. 520-store, 522-trash enclosure, 524-ev charger, 526-gas canopy. | | Enumeration | 2365727 |
| Electronic Plan | Original | / | 9/30/2026 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2365707 |
| | Original | / | 9/30/2026 | SYSTEM | SYSTEM | Plan Review fees paid 09/30/2026 for plan submitted 09/30/2026. Submit Date updated to now. Plan now open for review. | | | 2365466 |
| Energy | Original | / | 9/30/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2365351 |
| Floodplain | Original | N | 9/30/2026 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 5408009002) | | Floodplain | 2365350 |