| Energy | Original | D | 11/18/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2384061 |
| Mechanical | Original | D | 11/18/2026 | TREVORH | TREVORH | Disapproved; This Mechanical submittal package is Missing the Gas plans.Need to provide a Roof plan showing the all roof top equipment and how roof top equipment will be accessed. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2384060 |
| Electrical | Original | D | 11/18/2026 | CONNERM | CONNERM | Fault current information (SCCR, AIC, SCA) at all of the following locations in tabular form 1. All new panelboards and switchboards 2. All new transfer equipment 3. All new industrial control panels 4. All new air conditioning and refrigeration equipment 5. At any of the above locations when refed
Provide a note on the plans indicating that the Electrical design has a maximum volt drop of 5% per C405.10
The following general note must be included on the electrical plans: “A Final Commissioning Report shall be delivered to the building owner per section C408.2.5 of the 2021 IECC.” * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2384022 |
| Plumbing | Original | D | 11/18/2026 | SHANEN | SHANEN | Show compliance with commercial plumbing plan review additional requirements for 2021 IECC. Compliance with 2021 IPC and CO state amendments to 2021 IPC must be stated on the plumbing plans. Roof drainage information provided on sheet A103 is incomplete. Provide gpm and/or square footage served by each component of the roof drainage system. Provide a piping materials schedule on the plumbing plans. Provide required water pipe size analysis data, see 2021 IPC appendix E. Data must include: service pressure, service size, meter size, pressure loss, available pressure, distribution size, WSFU served, developed length, etc. All gas piping related items shall be on the mechanical plans. Remove ALL references to gas piping from the plumbing plans. ST-5 is for residential use only per manufacturer. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2383971 |
| Electronic Plan | Original | / | 11/18/2026 | CONNERM | CONNERM | In Current Review by CONNERM | | Electronic Plan | 2383965 |
| Elevators | Original | N | 11/18/2026 | ANDREAL | ANDREAL | No conveyance in this scope of work. | | Elevators | 2383925 |
| CO Springs Fire | Original | D | 11/16/2026 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | Jacob.Watson | CO Springs Fire | 2382940 |
| CO Springs Hazmat | Original | D | 11/16/2026 | CSFIRE | CSFIRE | See Fire Comments | Jacob.Watson | CO Springs Hazmat | 2382938 |
| City Engr | Original | D | 11/13/2026 | HVO | HVO | Please upload the approved development plan and the approved construction drawings for the public street improvements (if applicable). | | City Engr | 2382265 |
| CO Springs DRE | Original | D | 11/12/2026 | SSADLER | SSADLER | Upload the following documents: final approved and stamped development plan final approved landscaping and irrigation plans approval letter final recorded plat Citywide impact fees are due prior to building permit issuance Due to policy changes, assurances for all private improvements are now due at the time of C/O | | CO Springs DRE | 2381843 |
| CSU Electric | Original | D | 11/12/2026 | CSUREVIEW | CSUREVIEW | Submit Electric Load Data Form to CSU Field Engineering. Form can be found at: https://www.csu.org/hubfs/Document-Library/ElectricLoadData.pdf?hsLang=en,Approved Development Plan and CSU-approved Construction Drawings must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions.-DT | dytrujillo | CSU Electric | 2381401 |
| CSU Contract Admin. | Original | D | 11/10/2026 | CSUAPPSPRM | CSUAPPSPRM | Requires submittal and approval of Commercial Water Meter Sizing Form (CWMSF) and payment of development charges/fees. CWMSF available at https://www.csu.org/CSUDocuments/watermetersizingforminteractive.pdf. Contact Customer Contract Administration at 719-668-8111 for more information. JMD | jdemello | CSU Contract Admin. | 2380879 |
| Stormwater | Original | D | 11/10/2026 | GHUNTLEY | GHUNTLEY | Upload approved GEC permit | | Stormwater | 2380807 |
| CSU Gas | Original | A | 11/10/2026 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. JSN 11.10.2026 | jsnoel | CSU Gas | 2380657 |
| CSU Water | Original | A | 11/10/2026 | CSUREVIEW | CSUREVIEW | Approved development plan and utility construction drawings provided with permit set. Meter detail attached.MDA | malcuran | CSU Water | 2380520 |
| CSU Waste Water | Original | A | 11/10/2026 | CSUREVIEW | CSUREVIEW | Approved development plan and utility construction drawings provided with permit set.MDA | malcuran | CSU Waste Water | 2380517 |
| Zoning/Planning | Original | / | 11/10/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2380481 |
| Construction | Original | D | 11/10/2026 | MATTHEWA | MATTHEWA | Code study form // Code section references // Life safety plan // IECC form // Structural code references and soils report * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2380449 |
| Energy | Original | / | 11/9/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2380003 |
| Electronic Plan | Original | / | 11/9/2026 | MATTHEWA | MATTHEWA | In Current Review by MATTHEWA | | Electronic Plan | 2379967 |
| Enumeration | Original | A | 11/3/2026 | BECKYA | BECKYA | | | Enumeration | 2377858 |
| Electronic Plan | Original | / | 11/3/2026 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 2377857 |
| | Original | / | 11/2/2026 | SYSTEM | SYSTEM | Plan Review fees paid 11/02/2026 for plan submitted 11/02/2026. Submit Date updated to now. Plan now open for review. | | | 2377477 |
| Energy | Original | / | 11/2/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2377266 |
| Floodplain | Original | N | 11/2/2026 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 5304301120) | | Floodplain | 2377265 |