Construction | Splice 06/21/23 | A | 6/22/2023 | DANM | DANM | Revised accessible unit locations | | Construction | 1861132 |
Electronic Plan | Splice 06/21/23 | / | 6/22/2023 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1861094 |
Enumeration | Splice 06/21/23 | A | 6/21/2023 | BECKYA | BECKYA | | | Enumeration | 1860045 |
Electrical | Splice 03/30/23 | A | 4/3/2023 | DANIELG | DANIELG | | | Electrical | 1824217 |
Electronic Plan | Splice 03/30/23 | / | 4/3/2023 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1824214 |
Construction | Splice 03/30/23 | A | 3/30/2023 | DANM | DANM | Minor floor plan revisions and revised listed assembly for shaft wall | | Construction | 1823395 |
Electronic Plan | Splice 03/30/23 | / | 3/30/2023 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1823371 |
Zoning/Planning | Original | / | 3/14/2023 | KFENNER | KFENNER | In Current Review by KFENNER | | Zoning/Planning | 1815425 |
CO Springs DRE | Original | A | 3/14/2023 | KFENNER | KFENNER | Note on plan was: "CO hold pending re-review for proposed second kitchen."
NOTE: On 3/13/2023 I was provided a detailed email exchange between them and K Wintz. It was clear in the email chain that the CO was to be approved. For some reason it did not get approved in the system. With Katelyn out of the office, I (Kyle Fenner) went into the permit to approve it. | | CO Springs DRE | 1815423 |
Construction | Splice 02/06/23 | A | 2/7/2023 | DANM | DANM | Revised accessibility plan | | Construction | 1800051 |
Electronic Plan | Splice 02/06/23 | / | 2/7/2023 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1800021 |
Enumeration | Splice 02/06/23 | A | 2/7/2023 | BECKYA | BECKYA | | | Enumeration | 1799841 |
Construction | Splice 12/20/22 | A | 12/20/2022 | DANM | DANM | Hanger schedule that was missing from approved/permitted plans added to structural sheets | | Construction | 1784010 |
Electronic Plan | Splice 12/20/22 | / | 12/20/2022 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1784006 |
Construction | Splice 12/07/22 | A | 12/12/2022 | DANM | DANM | Floor and roof truss engineered profiles that are missing form the approved permitted set | | Construction | 1781259 |
Electronic Plan | Splice 12/07/22 | / | 12/12/2022 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1781239 |
Construction | Splice 12/07/22 | D | 12/12/2022 | DANM | DANM | Engineered roof truss labels do not match truss labels on approved roof framing plan splice
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1781046 |
Electronic Plan | Splice 12/07/22 | / | 12/12/2022 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1781037 |
Submittal 2 | Splice 12/07/22 | / | 12/9/2022 | ANDREAL | ANDREAL | Submittal #2 | | Submittal 2 | 1780644 |
Construction | Splice 12/07/22 | D | 12/8/2022 | DANM | DANM | Floor and roof trusses do not seem to match approved / permitted structural framing plans
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1780043 |
Electronic Plan | Splice 12/07/22 | / | 12/8/2022 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1779967 |
Construction | Splice 10/20/22 | A | 12/2/2022 | CGIECK | CGIECK | Please review plan. | | Construction | 1777378 |
Electronic Plan | Splice 10/20/22 | / | 12/2/2022 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 1777372 |
Submittal 3 | Splice 10/20/22 | / | 12/2/2022 | KALLISTAJ | KALLISTAJ | Submittal #3 | | Submittal 3 | 1777267 |
Mechanical | Splice 10/20/22 | A | 11/30/2022 | JUSTINC | JUSTINC | | | Mechanical | 1776454 |
Electronic Plan | Splice 10/20/22 | / | 11/30/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1776447 |
Mechanical | Splice 10/20/22 | / | 11/29/2022 | WEBSITE | WEBSITE | Overtime Authorized for Mechanical by Patrick Anderson | lokalcommunities | Mechanical | 1776029 |
Construction | Splice 10/20/22 | D | 11/29/2022 | CGIECK | CGIECK | Provide IECC cert. to correspond with Heat loss calc. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1775697 |
Electronic Plan | Splice 10/20/22 | / | 11/18/2022 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 1773132 |
Submittal 2 | Splice 10/20/22 | / | 11/17/2022 | KALLISTAJ | KALLISTAJ | Submittal #2 | | Submittal 2 | 1772095 |
Mechanical | Splice 10/20/22 | D | 10/24/2022 | JUSTINC | JUSTINC | Mechanical review incomplete
Missing revised Manual J for unit B., and only mirrored for unit C? Indicate address on all sheets.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Mechanical | 1760445 |
CO Springs Fire | Splice 10/20/22 | A | 10/23/2022 | CSFIRE | CSFIRE | | rpeterson | CO Springs Fire | 1760431 |
Electrical | Splice 10/20/22 | A | 10/21/2022 | SHELBY | SHELBY | | | Electrical | 1760376 |
Construction | Splice 10/20/22 | D | 10/21/2022 | CGIECK | CGIECK | Provide the correct IECC. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1760158 |
Construction | Original | A | 6/6/2022 | CGIECK | CGIECK | Please review plan. | | Construction | 1693035 |
Electronic Plan | Original | / | 6/6/2022 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 1692907 |
CO Springs DRE | Original | A | 6/6/2022 | KWINTZ | KWINTZ | PLDO fees paid. plans approved KAW 6/6/22 | | CO Springs DRE | 1692813 |
Submittal 4 | Original | / | 6/3/2022 | ANDREAL | ANDREAL | Submittal #4 | | Submittal 4 | 1692668 |
CO Springs DRE | Original | A | 6/3/2022 | DSEXTON | DSEXTON | Approved. School and Park dedication fees have been paid. The building permit plans are in substantial conformance with the approved development, except for some minor facade changes which are administratively approved through this building permit request. Approved by DJS for KAW. 6/3/2022 | | CO Springs DRE | 1692073 |
Zoning/Planning | Original | / | 5/24/2022 | KWINTZ | KWINTZ | In Current Review by KWINTZ | | Zoning/Planning | 1687294 |
Construction | Original | D | 5/24/2022 | CGIECK | CGIECK | Provide Pre-manufactured Truss Calc. for Units D & E. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1687177 |
Enumeration | Original | A | 5/23/2022 | BECKYA | BECKYA | Addressing Plan located in the Accessibility Site plan page. | | Enumeration | 1686076 |
Submittal 3 | Original | / | 5/20/2022 | KALLISTAJ | KALLISTAJ | Submittal #3 | | Submittal 3 | 1685785 |
CO Springs DRE | Original | A | 5/18/2022 | CHUDSPETH | CHUDSPETH | Plans have been approved. Park, school, police and fire fees paid on 5/18/2022 | | CO Springs DRE | 1684421 |
CO Springs DRE | Original | D | 5/13/2022 | KWINTZ | KWINTZ | PLDO fees required. | | CO Springs DRE | 1682207 |
Health Dept. | Original | N | 4/28/2022 | HEALTHDEPT | HEALTHDEPT | Construction activity permit is valid from 02/21/2022-08/21/2022. AF | Amanda Furno | Health Dept. | 1672881 |
Plumbing | Original | A | 4/27/2022 | SHANEN | SHANEN | Living areas not reviewed. Must comply with current adopted codes. | | Plumbing | 1672030 |
CO Springs Fire | Original | A | 4/26/2022 | CSFIRE | CSFIRE | You are responsible for reviewing the APPROVAL comments found on the CSFD website as they contain important inspection information: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – NOTE COMMENTS ARE AVAILABLE FOR 30 DAYS! ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | dwithee | CO Springs Fire | 1671561 |
Mechanical | Original | A | 4/26/2022 | JUSTINC | JUSTINC | | | Mechanical | 1671450 |
Electrical | Original | A | 4/25/2022 | DANIELG | DANIELG | | | Electrical | 1670937 |
Electronic Plan | Original | / | 4/25/2022 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1670931 |
Zoning/Planning | Original | / | 4/25/2022 | KWINTZ | KWINTZ | In Current Review by KWINTZ | | Zoning/Planning | 1670868 |
Construction | Original | D | 4/25/2022 | CGIECK | CGIECK | Missing Roof Truss from plan : A, ACE, AD, AE, AEE, AH, BG, CG, D, DA, H, HE, I, J3, J3A, J6, JM, KE
Missing Roof Truss from Truss Calc: A1G, AM, A6, A4, A5, A6, AHE, AF, AKE, B1, B2, B3, B4, J1, J2A, CG1, C1 (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1670861 |
Enumeration | Original | D | 4/22/2022 | BECKYA | BECKYA | In the Architectural Plans, provide a site plan that shows the entire development, cloud only the area/areas of work for this plan for Enumerations purposes. Site plan is to include surrounding street, north arrow, ect. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Enumeration | 1670173 |
Electronic Plan | Original | / | 4/22/2022 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 1670166 |
Submittal 2 | Original | / | 4/22/2022 | BECKYA | BECKYA | Submittal #2 | | Submittal 2 | 1670057 |
CO Springs Fire | Original | D | 3/2/2022 | CSFIRE | CSFIRE | WALK OK – See our “Virtual” Walk Through process here: https://coloradosprings.gov/sites/default/files/inline-images/walk-thru_memo.pdf You are responsible for reviewing the DISAPPROVAL comments found on the CSFD website and responding to them in your resubmittal: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – COMMENTS ARE AVAILABLE FOR ONLY 30 DAYS! | dwithee | CO Springs Fire | 1644339 |
CO Springs DRE | Original | D | 3/2/2022 | KWINTZ | KWINTZ | Building elevation on the architectural drawing varies slightly from approved DP and is administratively approved. The only remaining comment is to collect PLDO school fees. $368 per unit. Plans are approved and once fees are collected, the building permit can be approved. KAW 3/2/22 | | CO Springs DRE | 1643775 |
Zoning/Planning | Original | / | 2/18/2022 | KWINTZ | KWINTZ | In Current Review by KWINTZ | | Zoning/Planning | 1638862 |
Mechanical | Original | D | 2/15/2022 | JUSTINC | JUSTINC | Provide engineer stamp on each of the HVAC equipment certificates and whole house ventilation pages.
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1637430 |
Electronic Plan | Original | / | 2/15/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1637382 |
Plumbing | Original | D | 2/11/2022 | SHANEN | SHANEN | Show electrical, gas and water meter locations for each floor plan. Note: Sewer and water service to each unit shown on sheet U1.2. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 1635827 |
Electrical | Original | D | 2/11/2022 | DANIELG | DANIELG | Footprint (floor plans) showing all electrical service equipment and disconnects serving the structure (utility meter, disconnecting means, and unit panel).
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 1635707 |
Electronic Plan | Original | / | 2/11/2022 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1635703 |
City Engr | Original | A | 2/10/2022 | PMORRIS | PMORRIS | | | City Engr | 1635430 |
Health Dept. | Original | D | 2/10/2022 | HEALTHDEPT | HEALTHDEPT | Construction activity permit required for projects earthmoving > 1 acre. If the entire project is > 1 acre earthmoving, regardless of being submitted in phases and/or separate building permits, a construction activity permit will be required. Information and application may be accessed online at: https://www.elpasocountyhealth.org/service/air-quality/construction-activity-application For questions, contact Environmental Health at 719-578-3199 option 3. AB | abrannon | Health Dept. | 1635387 |
CSU Contract Admin. | Original | N | 2/9/2022 | CSUAPPSPRM | CSUAPPSPRM | All applicable development fees/charges will be collected at time of individual townhome applications. AG | aguerin | CSU Contract Admin. | 1634534 |
Gas/Elec. Utils | Original | A | 2/8/2022 | CSUREVIEW | CSUREVIEW | AJ | ajuvera | Gas/Elec. Utils | 1634239 |
CSU Water | Original | A | 2/8/2022 | CSUREVIEW | CSUREVIEW | AJ | ajuvera | CSU Water | 1634237 |
CSU Waste Water | Original | A | 2/8/2022 | CSUREVIEW | CSUREVIEW | AJ | ajuvera | CSU Waste Water | 1634234 |
Construction | Original | D | 2/8/2022 | CGIECK | CGIECK | G1.0 - Acc. Plan - Cannot access the accessible unit through the garage.
A1.0a, A1.0b, - Detail 4 Correct entry and closet
A1.0c - Need zoning approval for Second Kitchen in Single Unit.
A4.1a - Missing Dwelling Separation
S102.A - Truss E is Missing from report. Following trusses missing from Plan. A9A, B9I, B9R, C9G, FE, H, HE, KE All girders, floor and roof should be labeled with the number of piles and bearing chord materials. Either on the framing plan or in schedule form.
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1634212 |
Electronic Plan | Original | / | 2/4/2022 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 1632597 |
Enumeration | Original | D | 2/3/2022 | BECKYA | BECKYA | 1. In the Architectural Plans, provide a site plan that shows the entire development, cloud the area/areas of work for this plan for Enumerations purposes. Site plan is to include surrounding street, north arrow, ect.
2. Provide a sheet of paper with the list of addresses, lot numbers along with the tax schedule numbers for each home that is a part of this plan. The plan will be under 1 address and Enumerations will cut and paste this sheet on to the label to reference all addresses that are a part of this plan. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Enumeration | 1631694 |
Electronic Plan | Original | / | 2/3/2022 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 1631686 |
Floodplain | Original | N | 2/1/2022 | KEITH | KEITH | | | Floodplain | 1631038 |