Required Departments: 6
|
|
|
Log Entries: 5
|
|
Out to Review | Original | / | 4/24/2024 | BERTHA | BERTHA | Paul walking 719-684-6599 | | Out to Review | 1994085 | Electrical | Original | D | 4/24/2024 | BERTHA | BERTHA | Provide conduit/conductor size, type CU or AL and quantity beginning at the utility transformer to include all conductors in the chain of supply for the electrical equipment in the scope of work
Provide withstand rating of new panel and available fault current of new panel.
Comply with 230.85 - NEC
Indicate location of all electrical distribution gear on the site/floor plan. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1994084 | Construction (Main) | Original | / | 4/23/2024 | | REBECCAM | Location = Construction (Main) by REBECCAM | | Construction (Main) | 1993285 | Energy | Original | N | 4/23/2024 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A
PAUL 719-684-6599 | | Energy | 1993281 | Floodplain | Original | N | 4/23/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7501101025) | | Floodplain | 1993280 |
|
| |
|