| CO Springs DRE | Original | D | 3/18/2026 | SSADLER | SSADLER | On the site plan there needs to show the Land Use Review Stamp. If you have questions, please contact Caleb at caleb.vanappledorn@coloradosprings.gov | | CO Springs DRE | 2281451 |
| Zoning/Planning | Original | / | 3/16/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2280528 |
| Construction | Original | A | 3/16/2026 | SHELLEY | SHELLEY | | | Construction | 2280315 |
| | Original | / | 3/13/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2280157 |
| | Original | / | 3/13/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2280038 |
| Submittal 4 | Original | / | 3/13/2026 | MELISSAF | MELISSAF | Submittal #4 | | Submittal 4 | 2280037 |
| CO Springs DRE | Original | D | 3/10/2026 | SSADLER | SSADLER | The plan that was submitted with the carport application and is stamped by the Land Use Review needs to be uploaded.
Approval letter is on file. | | CO Springs DRE | 2278252 |
| City Engr | Original | D | 3/10/2026 | JDAGNILLO | JDAGNILLO | Please address previous comment: "Engineering Development Review has determined a geological hazard waiver will be required for this project. It must be submitted directly to EDRD through our electronic review system called ProjectDox. Below is a link to ProjectDox and a user manual.
https://coloradosprings.gov/stormwater/planreview
Revised application forms are available on Public Works web-page. Public Works/City Engineering Hub/New Development/Standards and References/ "References and Research Tools". https://coloradosprings.gov/public-works/page/engineering-standards-and-references" | | City Engr | 2278143 |
| Zoning/Planning | Original | / | 3/9/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2277889 |
| Construction | Original | D | 3/9/2026 | SHELLEY | SHELLEY | This ES report only specifies the product meets the light transmitting requirements of the IBC and does not specify that it meets the structural requirements, nor the exterior cladding requirements, of the IBC. Per section 5.2, product must be proven to meet structural requirements. Provide an engineer stamped analysis showing the product meets requirements. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2277675 |
| | Original | / | 3/9/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2277537 |
| | Original | / | 3/9/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2277330 |
| Submittal 3 | Original | / | 3/9/2026 | MELISSAF | MELISSAF | Submittal #3 | | Submittal 3 | 2277329 |
| CO Springs DRE | Original | D | 3/5/2026 | SSADLER | SSADLER | Upload the approved stamp front yard carport site plan and the approval letter. | | CO Springs DRE | 2276772 |
| Zoning/Planning | Original | / | 3/5/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2276698 |
| City Engr | Original | D | 3/5/2026 | HVO | HVO | Please see previous comment. | | City Engr | 2276680 |
| Construction | Original | D | 3/5/2026 | SHELLEY | SHELLEY | Framing plan, ES report, remove sheets. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2276653 |
| Submittal 2 | Original | / | 3/5/2026 | MELISSAF | MELISSAF | Submittal #2 | | Submittal 2 | 2276572 |
| CO Springs DRE | Original | D | 11/4/2025 | SSADLER | SSADLER | Schedule a pre application meeting to discuss the requirements for the front yard carport application. | | CO Springs DRE | 2232546 |
| Zoning/Planning | Original | / | 10/31/2025 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2231831 |
| City Engr | Original | D | 10/31/2025 | HVO | HVO | EDRD has determined minimal geological hazards exist in this area and will accept a Geologic Hazard Waiver to be submitted for this site. Please submit it to EDRD through our electronic review system called ProjectDox. Below is a link to ProjectDox and a user manual. https://coloradosprings.gov/stormwater/planreview
Once it gets approved please upload the waiver with the building permit submission. | | City Engr | 2231650 |
| Construction | Original | D | 10/30/2025 | SHELLEY | SHELLEY | Provide framing plan. Framing ISO's are not framing plans. See carport and patio/deck cover handout for example. https://www.pprbd.org/File/ByAlias/RoofCover * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2230834 |
| Electronic Plan | Original | / | 10/30/2025 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 2230823 |
| Energy | Original | N | 10/29/2025 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2230397 |
| Floodplain | Original | N | 10/29/2025 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7412324002) | | Floodplain | 2230396 |