AUSTIN COMMERCIAL, L.P. | B= | C | 07/31/1996 | BUILDING FINAL COMPLETE | RICH | RICH | | B= | C | 955379 |
AUSTIN COMMERCIAL, L.P. | B= | P | 04/29/1996 | TCO 60 DAYS,SEE OTHER INTERIOR FINISH PERMITS | RICH | RICH | | B= | P | 955372 |
AUSTIN COMMERCIAL, L.P. | BFR | C | 03/27/1996 | MAIN SHELL | RICH | RICH | | BFR | C | 955364 |
AUSTIN COMMERCIAL, L.P. | BFR | P | 07/06/1995 | OK PENT HOUSE FRAMING PARAPETT WALLS ONLY/ | FRANK | FRANK | | BFR | P | 955356 |
AUSTIN COMMERCIAL, L.P. | BFR | R | 06/21/1995 | no plans or permit--this was supposed to be for 4th floor framing, plans are not out of plan check yet. this inspection should not have been on permit c38811. | BILLC | BILLC | | BFR | R | 955349 |
AUSTIN COMMERCIAL, L.P. | BFR | P | 05/23/1995 | FILLER KNEE WALL AT ROOF LEVEL NON STRUCTURAL,BUTTS BUILT UP ROOF | RICH | RICH | | BFR | P | 955341 |
RIVIERA ELECTRIC, INC. | E= | C | 04/10/1996 | | RON | RON | | E= | C | 955333 |
RIVIERA ELECTRIC, INC. | ER | P | 08/25/1995 | soffits. | RON | RON | | ER | P | 955321 |
RIVIERA ELECTRIC, INC. | ER | P | 08/18/1995 | 1st floor slab, 2nd floor building c, north half, 4th floor soffets | TERRY | TERRY | | ER | P | 955314 |
RIVIERA ELECTRIC, INC. | ER | P | 08/04/1995 | walls by norht 3rd floor stairwell | TERRY | TERRY | | ER | P | 955308 |
RIVIERA ELECTRIC, INC. | ER | P | 07/13/1995 | 2nd,3rd,walls b. | RON | RON | | ER | P | 955301 |
RIVIERA ELECTRIC, INC. | ER | P | 07/11/1995 | walls 4th floor. | RON | RON | | ER | P | 955292 |
RIVIERA ELECTRIC, INC. | ESL | P | 06/28/1995 | eug. parking garage. | RON | RON | | ESL | P | 955284 |
RIVIERA ELECTRIC, INC. | ER | P | 06/14/1995 | 4th fl.walls,penthouse slab. | RON | RON | | ER | P | 955276 |
RIVIERA ELECTRIC, INC. | ER | P | 06/01/1995 | roof deck. | RON | RON | | ER | P | 955269 |
RIVIERA ELECTRIC, INC. | ER | P | 05/26/1995 | decks. | RON | RON | | ER | P | 955261 |
RIVIERA ELECTRIC, INC. | ER | P | 05/22/1995 | 2nd floor 3rd pour | RED | RED | | ER | P | 955253 |
RIVIERA ELECTRIC, INC. | ER | P | 05/05/1995 | 3RD FLOOR DECK. | RON | RON | | ER | P | 955245 |
RIVIERA ELECTRIC, INC. | ER | P | 05/01/1995 | IST FLOOR DECK. | RON | RON | | ER | P | 955238 |
RIVIERA ELECTRIC, INC. | ER | P | 04/19/1995 | not 4th floor,3rd floor done 4/18/95. | RON | RON | | ER | P | 955229 |
RIVIERA ELECTRIC, INC. | ER | P | 04/18/1995 | 3rd floor deck. | RON | RON | | ER | P | 955221 |
RIVIERA ELECTRIC, INC. | ER | P | 04/13/1995 | 2nd floor deck | RON | RON | | ER | P | 955213 |
RIVIERA ELECTRIC, INC. | ER | P | 04/07/1995 | slab bld c 1st floor north end-went back to job insp slab talked with gary-foundjob ok | ARNOLD | ARNOLD | | ER | P | 955205 |
RIVIERA ELECTRIC, INC. | ER | P | 03/21/1995 | 3rd fl. deck. | RON | RON | | ER | P | 955197 |
RIVIERA ELECTRIC, INC. | ER | P | 03/20/1995 | 2nd fl.deck. | RON | RON | | ER | P | 955181 |
RIVIERA ELECTRIC, INC. | EUG | P | 03/20/1995 | | RON | RON | | EUG | P | 955190 |
RIVIERA ELECTRIC, INC. | ER | P | 03/16/1995 | 1st.floor.esl | RON | RON | | ER | P | 955175 |
RIVIERA ELECTRIC, INC. | ER | P | 03/10/1995 | 4TH FLOOR PARTIAL | RED | RED | | ER | P | 955168 |
RIVIERA ELECTRIC, INC. | ER | P | 03/02/1995 | 3rd fl. | RON | RON | | ER | P | 955160 |
RIVIERA ELECTRIC, INC. | ER | P | 02/22/1995 | | RON | RON | | ER | P | 955151 |
RIVIERA ELECTRIC, INC. | ESL | P | 02/16/1995 | partial deck . | RON | RON | | ESL | P | 955144 |
RIVIERA ELECTRIC, INC. | ER | P | 02/10/1995 | slab. | RON | RON | | ER | P | 955136 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 07/30/1996 | | JOHNW | JOHNW | | H= | C | 954806 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 07/08/1996 | roll up door was opened when I was doing this inspection , they must remain closed all the time. need door closure on exit door into chiller room. pennitrations thru waterheater room and thru 1hr wall that seperate chiller room from dock area need to be of 1hr construction | JOHNW | JOHNW | | H= | P | 954798 |
HEATING & PLUMBING ENGINEERS, INC | HD | C | 07/01/1996 | CHILLER ROOM EXHAUST DUCTWORK MODIFICATIONS | BOBM | BOBM | | HD | C | 954790 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 04/05/1996 | ok for T.C.O./ | JOHNW | JOHNW | | H= | P | 954782 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 04/02/1996 | HVAC in bridge area complete | JOHNW | JOHNW | | H= | P | 954775 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 03/21/1996 | ok for T.C.O./need to complete chiller room changes and inner locks on kitchen equipment before T.C.O. on kitchen area | JOHNW | JOHNW | | H= | P | 954768 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 02/27/1996 | 1ST LEVEL ROUGH COMPLETE AND ALMOST FLEXED OUT | JOHNW | JOHNW | | HD | P | 954760 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 01/30/1996 | 1ST level day care above ceiling rough ok | JOHNW | JOHNW | | HD | P | 954752 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 01/10/1996 | met with engineer on chiller room | JOHNW | JOHNW | | HD | P | 954744 |
HEATING & PLUMBING ENGINEERS, INC | HO | C | 01/04/1996 | complete chilled water system 120 P.S.I. | JOHNW | JOHNW | | HO | C | 954738 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 12/20/1995 | discussed child care area/plans for childcare and permit have been approve and obtained | JOHNW | JOHNW | | HD | P | 954729 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 12/15/1995 | shaft in c section ok | JOHNW | JOHNW | | HD | P | 954722 |
HEATING & PLUMBING ENGINEERS, INC | HO | P | 11/30/1995 | process piping for heating system, OK | JIMV | JIMV | | HO | P | 954715 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 11/14/1995 | FLOORS 1,2,3,C ALSO SHAFT ON 1 AND KITCHEN HOODS | JOHNW | JOHNW | | HD | P | 954709 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 10/31/1995 | all but 1 grease hood tied in | JOHNW | JOHNW | | HD | P | 954701 |
HEATING & PLUMBING ENGINEERS, INC | HI | P | 10/26/1995 | line from basement mech room to cook line | JOHNW | JOHNW | | HI | P | 954693 |
HEATING & PLUMBING ENGINEERS, INC | HE | C | 10/25/1995 | | JOHNW | JOHNW | | HE | C | 954684 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 10/24/1995 | GREASE DUCT ROUGH OK | JOHNW | JOHNW | | HD | P | 954677 |
HEATING & PLUMBING ENGINEERS, INC | HC | C | 10/24/1995 | OK FOR METER / [TO START EQUIPMENT] | JOHNW | JOHNW | | HC | C | 954669 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 10/06/1995 | all boiler & WH vents; penthouse B shaft F. dampers; C shaft basemnt F. dampers; parking structure elev room & exhaust | JIMV | JIMV | | HD | P | 954661 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/26/1995 | grease duct in penthouse ok also shafts in basement in A,B,C, OK | JOHNW | JOHNW | | HD | P | 954654 |
HEATING & PLUMBING ENGINEERS, INC | HI | P | 09/21/1995 | additional welded line to water heaters | JOHNW | JOHNW | | HI | P | 954647 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/20/1995 | 2nd and 3rd levels 90% comp/2nd and 3rd levels in "C" section shafts ok | JOHNW | JOHNW | | HD | P | 954632 |
HEATING & PLUMBING ENGINEERS, INC | HV | P | 09/20/1995 | "C" section penthouse boiler vents ok | JOHNW | JOHNW | | HV | P | 954639 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/11/1995 | 4th level above ceiling rough ok inc. shaft/2nd & 3rd levels 90% above ceiling rough.1st level grease duct rough ok | JOHNW | JOHNW | | HD | P | 954623 |
HEATING & PLUMBING ENGINEERS, INC | HO | P | 08/18/1995 | 60# test on line that runs between parking garage and main building/ "K,K." welders stamp | JOHNW | JOHNW | | HO | P | 954616 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/15/1995 | B area above ceiling rough complete 2,3,4 levels /C area high pressure duct complete.Bathrooms and soffitt in these areas ok duct. | JOHNW | JOHNW | | HD | P | 954610 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/11/1995 | basement boiler vent up to penthouse OK | JIMV | JIMV | | HD | P | 954602 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 07/28/1995 | DISCUSSED CHILLER ROOM REQUIRMENTS | JOHNW | JOHNW | | HD | P | 954594 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 07/25/1995 | 2nd 3rd & 4th levels c area shaft walls ok/4th level c area 75% duct | JOHNW | JOHNW | | HD | P | 954586 |
HEATING & PLUMBING ENGINEERS, INC | HV | P | 07/11/1995 | 3rd & 4th floor main & 3rd floor restroom shafts | JIMV | JIMV | | HV | P | 954578 |
HEATING & PLUMBING ENGINEERS, INC | HI | P | 07/05/1995 | 60# test welded from basement to penthouse ok | JOHNW | JOHNW | | HI | P | 954571 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 07/05/1995 | 4th level shaft wall firedamper framing ok | JOHNW | JOHNW | | HD | P | 954562 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 06/20/1995 | 4th floor above ceiling rough 75%/discussed firedampers | JOHNW | JOHNW | | HD | P | 954554 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 06/16/1995 | 2nd,3rd & 4th floors in section B 75% rough in/also welded grease duct and stainless duct rough in ok/problem with fire damper framing | JOHNW | JOHNW | | HD | P | 954547 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 05/22/1996 | | JIMV | JIMV | | P= | C | 955130 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 04/26/1996 | | JIMV | JIMV | | P= | P | 955122 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 04/19/1996 | need SS sink in mech area; TCO | JIMV | JIMV | | P= | P | 955114 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 04/10/1996 | need basement floor | JIMV | JIMV | | P= | P | 955106 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 03/20/1996 | TCO for floors 2,3, & 4; need BFP drain to floor drain for snow melt system dock area | JIMV | JIMV | | P= | P | 955074 |
HEATING & PLUMBING ENGINEERS, INC | PB | C | 03/20/1996 | | JIMV | JIMV | | PB | C | 955084 |
HEATING & PLUMBING ENGINEERS, INC | PRD | C | 03/20/1996 | | JIMV | JIMV | | PRD | C | 955090 |
HEATING & PLUMBING ENGINEERS, INC | PTO | C | 03/20/1996 | | JIMV | JIMV | | PTO | C | 955099 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 12/11/1995 | fitness area ok | JIMV | JIMV | | PTO | P | 955066 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 10/09/1995 | WASTE AND VENT AND WTR PIPING | PAT | PAT | | PTO | P | 955060 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 09/29/1995 | AREA C--VENDING AREA 1ST THRU 4TH FLR/ 1ST FLR AND SERVICE LEVEL RESTROOMS-- | PAT | PAT | | PTO | P | 955052 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/28/1995 | RESTROOMS ONLY-- WATER PIPING-- | PAT | PAT | | PTO | P | 955044 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/08/1995 | | PAT | PAT | | PTO | P | 955037 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/03/1995 | WASTE AND VENT ONLY | PAT | PAT | | PTO | P | 955029 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/01/1995 | | PAT | PAT | | PTO | P | 955023 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 07/28/1995 | RESTROOM AND MOP BASIN AREA----3C---- | PAT | PAT | | PTO | P | 955015 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 07/25/1995 | | PAT | PAT | | PTO | P | 955007 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 07/21/1995 | PENTHOUSE C--ROOF DRAINS | PAT | PAT | | PRD | P | 954985 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 07/21/1995 | 4-C RESTROOM GROUP | PAT | PAT | | PTO | P | 954997 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 07/20/1995 | 4TH FLOOR C SECTION SANITARY VENTS ONLY AND THE COMBONATION WASTE AND VENT FLOOR DRAINS TO THE MECHANICAL ROOM ABOVE THE C SECTION ONLY..200 POUND HYDRO-STATIC TEST ON WATER PIPE FOR C SECTION CONFIRMED 15 MIN TEST WHILE I WAS THERE | BILL | BILL | | PTO | P | 954976 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 07/11/1995 | DOMESTIC WATER-2ND 3RD AND 4TH FLRS--B AREA-- | PAT | PAT | | PTO | P | 954969 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 07/06/1995 | 8" RISERS-2ND TO 4TH FLOORS | PAT | PAT | | PRD | P | 954962 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 06/30/1995 | AREA 4-C ROOF DRAINS | PAT | PAT | | PRD | P | 954955 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 06/21/1995 | STORM RISERS IN SHAFTS/WASTE AND VENT RISERS IN SHAFTS/BATH GROUP WASTE AND VENTS | PAT | PAT | | PTO | P | 954948 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 06/20/1995 | 3RD LEVEL/B AREA--BATH GROUP WASTE AND VENT/VENDING AREA/STORM RISERS IN SHAFTS/VENT RISERS IN SHAFTS | PAT | PAT | | PTO | P | 954940 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 06/19/1995 | 4TH FLR-"B"/COMB WATE AND VENT SYS..-BATH GROUP WASTE AND VENT/WEST SIDE MISC WASTE AND VENT | PAT | PAT | | PTO | P | 954931 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 06/15/1995 | 4TH FLR OVERHEAD ROOF DRNS AND DWV FOR RESTROOMS/ "B" AREA--NORTH END-- | PAT | PAT | | PRD | P | 954924 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 06/14/1995 | PENTHOUSE--B / ROOF DRAINS | PAT | PAT | | PRD | P | 954917 |
HEATING & PLUMBING ENGINEERS, INC | PRD | R | 06/13/1995 | CANCELLED | PAT | PAT | | PRD | R | 954910 |
HEATING & PLUMBING ENGINEERS, INC | PB | R | 05/16/1995 | CANCELLED--MET WITH PLUMBERS--- | PAT | PAT | | PB | R | 954902 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 04/21/1995 | | PAT | PAT | | PB | P | 954894 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 04/13/1995 | SEE HPE PLANS IN TRAILER | PAT | PAT | | PB | P | 954886 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/15/1995 | SEE PLANS | PAT | PAT | | PB | P | 954877 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/23/1995 | see plans | PAT | PAT | | PB | P | 954869 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/21/1995 | SEE PLANS | PAT | PAT | | PB | P | 954863 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/15/1995 | SEE PLANS | PAT | PAT | | PB | P | 954854 |
HEATING & PLUMBING ENGINEERS, INC | PB | R | 01/30/1995 | not ready | PAT | PAT | | PB | R | 954846 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/19/1995 | see plans | PAT | PAT | | PB | P | 954838 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/17/1995 | SEE PLANS | PAT | PAT | | PB | P | 954830 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/13/1995 | SEE PLANS | PAT | PAT | | PB | P | 954822 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/10/1995 | SEE PLBRS DRAWINGS | JIMV | JIMV | | PB | P | 954814 |