COLORADO STRUCTURES INC | B= | C | 01/04/2001 | ok with other final inspections | BOBB | BOBB | | B= | C | 1741831 |
COLORADO STRUCTURES INC | B= | P | 12/14/2000 | COMPLETED MOST ITEMS LISTED ON PREVIOUS INSPECTIONS | BOBB | BOBB | | B= | P | 1741950 |
COLORADO STRUCTURES INC | B= | R | 12/12/2000 | inspection not requested today ? | BOBB | BOBB | | B= | R | 1741822 |
COLORADO STRUCTURES INC | B= | P | 12/11/2000 | MOST CORRECTIONS MADE FROM PREVIOUS INSPECTIONS / STILL NEED ALL OTHER FINALS COMPLETED | BOBB | BOBB | | B= | P | 1741943 |
COLORADO STRUCTURES INC | B= | P | 12/08/2000 | THEATRES # 1, 17 & BATHROOMS ; NEED HANDRAILS , EXIT LITES , SOME CEILING TILES INSTALLED | BOBB | BOBB | | B= | P | 1741935 |
COLORADO STRUCTURES INC | B= | P | 12/07/2000 | THEATRES # 10, 11, 12, 13, 14, 15 / NEED EXIT LIGHTING COMPLETE / COMPLETE SOME HANDRAILS / NEED SOME DESIGNATION LITES COMPLETE ON ENTRANCES | BOBB | BOBB | | B= | P | 1741926 |
COLORADO STRUCTURES INC | B= | P | 12/06/2000 | THEATRES # 6, 7, 8, &9 ; NEED ALL OTHER FINAL INSPECTIONS , NEED EXIT LITES IN VESTIBUELES | BOBB | BOBB | | B= | P | 1741918 |
COLORADO STRUCTURES INC | B= | P | 12/05/2000 | NEED ALL OTHER FINAL INSPECTIONS / COMPLETE EXIT LITES / LITES IN VESTIBULES / THEATRE # 3 , 4 , 5 | BOBB | BOBB | | B= | P | 1741911 |
COLORADO STRUCTURES INC | B= | P | 12/04/2000 | MISSING HANDRAIL AT STAIRS TO PROJECTION ROOM / EMERGINCEY EXIT LITES FOR SAME AREA / NEED ELEVATOR COMPLETE / VESTIBULE LIGHTING / NEED ALL OTHER FINAL INSPECTIONS / GRID CEILING COMPLETE / 1ST THEATRE ONLY | BOBB | BOBB | | B= | P | 1741903 |
COLORADO STRUCTURES INC | BFR | C | 11/14/2000 | frame inspection ok with electric rough inspection . | BOBB | BOBB | | BFR | C | 1741814 |
COLORADO STRUCTURES INC | BFR | P | 10/24/2000 | #16 WALLS OK & # 13 WALLS OK | BOBB | BOBB | | BFR | P | 1741887 |
COLORADO STRUCTURES INC | BFR | P | 10/24/2000 | OK SOFFITS BETWEEN 10 & 11 BETWEEN A & E / WALLS BETWEEN D & B ON 6 & 7 | BOBB | BOBB | | BFR | P | 1741894 |
COLORADO STRUCTURES INC | BFR | P | 10/02/2000 | ok canopy walls between 9 & 12 / ok walls at # 11, 12, 14, & 15 | BOBB | BOBB | | BFR | P | 1741807 |
COLORADO STRUCTURES INC | BFN | P | 09/12/2000 | ok walls on 8, 9, 10, 11 | BOBB | BOBB | | BFN | P | 1741798 |
COLORADO STRUCTURES INC | BFR | P | 08/31/2000 | ok walls between 1 to 10 & C to K | BOBB | BOBB | | BFR | P | 1741790 |
COLORADO STRUCTURES INC | BFT | P | 08/14/2000 | ok footer for north east trash enclosure | BOBB | BOBB | | BFT | P | 1741783 |
COLORADO STRUCTURES INC | BSP | P | 07/31/2000 | ok, 5/8'' rated sheetrock , south half of roof , photos on file for flame spread protection | BOBB | BOBB | | BSP | P | 1741775 |
COLORADO STRUCTURES INC | BFN | R | 07/30/2000 | no inspection called | BOBB | BOBB | | BFN | R | 1741768 |
COLORADO STRUCTURES INC | BFR | P | 07/19/2000 | ok, walls on column line 5 to 17 between C & B | BOBB | BOBB | | BFR | P | 1741760 |
COLORADO STRUCTURES INC | B16 | P | 07/17/2000 | PLAN CHECK FEE PAID OK FOR INSPECTIONS ALL TRADES | DAVEL | DAVEL | | B16 | P | 1741878 |
COLORADO STRUCTURES INC | BSP | T | 07/14/2000 | PAID (REC#373899)ADDITIONAL PLAN REVIEW TIME: $90.000 From: SEAN | SEAN | SEAN | | BSP | T | 1741870 |
COLORADO STRUCTURES INC | BFT | P | 04/13/2000 | ok, all pilasters w. of A on 14 & 15 | BOBB | BOBB | | BFT | P | 1741752 |
COLORADO STRUCTURES INC | BFN | P | 04/13/2000 | OK, ELEV. WALLS BETWEEN DD & EE , 3.8 & 4 | BOBB | BOBB | | BFN | P | 1741862 |
COLORADO STRUCTURES INC | BFT | P | 04/12/2000 | all pads ok W. of column line B between 5 & 16 ; ok, w/ 2- 7'- 6'' x 7'- 6'' x 2'- 8'' & 2- 5' x 12' x 2'- 8'' & 5- 5' x 5' x 1'- 3'' & 2- 5' x 9' x 2'- 8'' & 2- 5' x 5' x 2'- 8'' pads | BOBB | BOBB | | BFT | P | 1741743 |
COLORADO STRUCTURES INC | BFT | P | 04/07/2000 | see site set for pads and pilasters location,s | FRANK | FRANK | | BFT | P | 1741736 |
COLORADO STRUCTURES INC | BFT | P | 04/06/2000 | col line 5.9 AA to EE | JOE | JOE | | BFT | P | 1741727 |
COLORADO STRUCTURES INC | BFN | P | 03/21/2000 | elev. walls , per: detail 12/ S2. 11 | BOBB | BOBB | | BFN | P | 1741719 |
COLORADO STRUCTURES INC | BFT | P | 03/15/2000 | 0k, w/ 1- 12'- 4'' x 14'- 4'' x 2' elevator pad , per: detail - 12/ S2. 11 | BOBB | BOBB | | BFT | P | 1741711 |
COLORADO STRUCTURES INC | BFT | P | 03/14/2000 | all pads ok 0n column lines 6 to 15 & 8' E. of B / all pads ok, at 9'- 1 1/2 '' E. of C to E. / all pads ok on BB to B8 between 3 & 4 / 5.1 AA & DD | BOBB | BOBB | | BFT | P | 1741703 |
COLORADO STRUCTURES INC | BFT | P | 03/07/2000 | column lines ; 5 & 6 between G & E.7 : ok w/ 2- 6' x 6' x 1'- 9'' & 2- 5' x 9' x 2'- 8'' & 1- 3'- 6'' x 3'- 6'' x 1' & 1- 5' x 5' x 1'- 3'' pads | BOBB | BOBB | | BFT | P | 1741681 |
COLORADO STRUCTURES INC | BFD | C | 03/07/2000 | FROM COLUMN LINE C TO CC | BOBB | BOBB | | BFD | C | 1741854 |
COLORADO STRUCTURES INC | BFT | R | 02/15/2000 | NO INSPECTION TODAY | DAVE JONES | DAVE JONES | | BFT | R | 1741672 |
COLORADO STRUCTURES INC | BFT | P | 02/08/2000 | column lines ; C.2 & B.7 on 14 & 15 : ok, w/ 7- 4' x 4' x 1' & 3- 5' x 5' x 1' & 2- 6' x 6' x 1'- 9'' & 1- 4'- 6'' x 4'- 6'' x 1' / column lines ; C.2 & B.7 between 11 & 14 : ok, w/ 2- 5'-6'' x 5' - 6'' x 1'- 3'' & 1- 5' x 5' x 1'- 3'' & 1- 9' x 9' x 2' | BOBB | BOBB | | BFT | P | 1741664 |
COLORADO STRUCTURES INC | BFT | R | 02/03/2000 | canceled at 9:01 am by Dallas | BOBB | BOBB | | BFT | R | 1741657 |
COLORADO STRUCTURES INC | BFT | P | 02/02/2000 | column lines ; D & B, C-2, B-7 on 6.4, 8, 8.9, 9 ; ok w/ 3- 5'- 6'' x 5'- 6'' x 1'- 3'' & 1-8' x 8' x 1'- 9'' & 7- 4' x 4' x 1' & 1- 3'- 6'' x 3'- 6'' x 1' & 5- 5' x 5' x 1'- 3'' & 2- 6' x6' x 1'- 9'' pads | BOBB | BOBB | | BFT | P | 1741649 |
COLORADO STRUCTURES INC | BFT | P | 02/01/2000 | column lines; 10- 11- 14 on D n. to s. ; ok, w/ 3- 11'- 6'' x 11'- 6'' x 2'- 3'' pads / w. of D line ; ok, w/ 1- 5' x 5' x 1'-3'' & 1- 3'- 6'' x 3'- 6'' x 1' & 1- 3' x 3' x 1' | BOBB | BOBB | | BFT | P | 1741641 |
COLORADO STRUCTURES INC | BFT | P | 01/26/2000 | between column lines 6 & 7 to E.3 ; ok, w/ 5-4' x 4' x 1' & 1- 4'- 6'' x 4'- 6'' x 1' & 1- 5'- 6'' x 5'- 6'' x 1'- 3'' pads | BOBB | BOBB | | BFT | P | 1741632 |
COLORADO STRUCTURES INC | BFT | P | 01/25/2000 | between 7 & 10 to E.3 ; ok, w/ 2-3'- 6'' x 3'- 6'' x 1' & 2- 3' x 3' x 1' & 2- 6' x 6' x 1'- 9'' & 2- 7' x 7' x 2'- 3'' & 3- 4'- 6'' x 4'- 6'' x 1' & 2- 5'- 6'' x 5'- 6'' x 1'- 3'' & 1- 8' x 8' x 1'- 9'' pads / between column lines E & C to 17 ; ok, w/ 2- 6' x 6' x 1'- 9'' & 2- 7' x 7' x 2'- 3'' & 1- 5'- 6'' x 5'- 6'' x 1' & 5- 4'- 6'' x 4'- 6'' x 1' & 1- 5' x 5' x 1'- 3'' pads | BOBB | BOBB | | BFT | P | 1741696 |
COLORADO STRUCTURES INC | BFT | P | 01/24/2000 | between column lines 10 & 11 to E.3 ; ok, w/ 2-4'- 6'' x 4'- 6'' x 1' & 2- 6' x 6' x 1'- 9'' & 3- 5'-6'' x 5'-6'' x 1'-3'' & 1- 3'- 6'' x 3'- 6'' x 1' & 2- 4' x 4' x 1' & 1- 5' x 5' x 1' pads / between column lines F & E to 17 ; ok, w/ 2- 6' x 6' x 1- 9'' & 2- 7' x 7' x 2'-3'' & 4- 4' x 4' x 1' & 2- 4'- 6'' x 4'- 6'' x 1' & 1- 5' x 5' x 1'- 3'' pads | BOBB | BOBB | | BFT | P | 1741689 |
COLORADO STRUCTURES INC | BFT | P | 01/21/2000 | between column lines 14 & 15 to E.3 ; ok, w/ 5- 4' x 4' x 1' & 1- 3' x 3' x 1' & 1- 4'-6'' x 4'- 6'' x 1' & 1- 5'- 6'' x 5'- 6'' x 1'- 3'' pads / between column lines 15 & 16 to E.-7 ; ok w/ 2- 5' x 9' x 2'- 8'' & 2- 6' x 6' x 1'-9'' & 3- 3' x 3' x 1' & 1- 3'-6'' x 3'-6'' x 1' & 1- 5' x 5' x 1'-3'' pads | BOBB | BOBB | | BFT | P | 1741624 |
COLORADO STRUCTURES INC | BFT | P | 01/19/2000 | between column lines ; J & F-- 17 & 20 : ok, w/ 3-- 4'- 6'' x 4'- 6'' x 1' & 5-- 3'- 6'' x 3'- 6'' x 1' & 3-- 3' x 3' x 1' / C & A-- 17 & 18 : ok, w/ 5-3' x 3' x 1' & 2- 4'- 6'' x 4'- 6'' x 1' & 1- 4' x 4' x 1' | BOBB | BOBB | | BFT | P | 1741617 |
COLORADO STRUCTURES INC | BFT | P | 01/14/2000 | between column lines; J & F to 4: ok w/ 2-3' x 3' x 1' & 5-3'- 6'' x 3'- 6'' x 1' & 1- 4' x 4' x 1' & 4- 4'- 6'' x 4'- 6'' x 1' & 1- 5' x 5' x 1'- 3'' pads. between column lines; F & E to 4: ok w/ 2- 3' x 3' x 1' & 2- t' x 7' x 2'- 3'' & 2- 6'- 6'' x 6'- 6'' x 1'- 9'' & 3- 4' x 4' x 1' & 2- 4'- 6'' x 4'- 6'' x 1' & 1- 5'-5'' x 5'-5'' x 1'- 3'' pads | BOBB | BOBB | | BFT | P | 1741609 |
COLORADO STRUCTURES INC | BFN | P | 01/12/2000 | 23' n to s on CC / 77' e to w on 1 / 22' n to s on C / 18' e to w at 22' point of C | BOBB | BOBB | | BFN | P | 1741600 |
COLORADO STRUCTURES INC | BFT | P | 01/07/2000 | 22' e to w on 3 / 36' n to s on CC / 89' n to s on EE | BOBB | BOBB | | BFT | P | 1741593 |
COLORADO STRUCTURES INC | BFT | P | 01/05/2000 | 33' n to s on C / 80' e to w on 3.8 / 40' n to s on CC | BOBB | BOBB | | BFT | P | 1741585 |
COLORADO STRUCTURES INC | BFT | P | 12/29/1999 | 41' n to s on C / 40' n to s on CC / 78' e to w on 1 | BOBB | BOBB | | BFT | P | 1741577 |
COLORADO STRUCTURES INC | BFT | R | 12/21/1999 | excavation in process / not ready | BOBB | BOBB | | BFT | R | 1741569 |
COLORADO STRUCTURES INC | BFT | P | 12/20/1999 | 61' s to n on D / 82' s to n on B / 68' w to e on 16 | BOBB | BOBB | | BFT | P | 1741561 |
COLORADO STRUCTURES INC | BFT | P | 12/19/1999 | 67' n to s on E / 82' n to s on F / 60' e to w on 5 | BOBB | BOBB | | BFT | P | 1741552 |
COLORADO STRUCTURES INC | BFT | P | 12/16/1999 | B to D / 60' s to n on D / 113' s to n on B | BOBB | BOBB | | BFT | P | 1741545 |
COLORADO STRUCTURES INC | BFT | P | 12/15/1999 | check previous inspected areas for frost / no conc pour for footings today | BOBB | BOBB | | BFT | P | 1741537 |
COLORADO STRUCTURES INC | BFT | P | 12/13/1999 | 61' e to w on 10 / 62' e to w on 7 | BOBB | BOBB | | BFT | P | 1741528 |
COLORADO STRUCTURES INC | BFT | P | 12/10/1999 | 63' w to e on E / 67' w to e on C / 63' e to w on 14 / 63' e to w on 15 / 65' e to w on 11 | BOBB | BOBB | | BFT | P | 1741520 |
COLORADO STRUCTURES INC | BFT | P | 12/09/1999 | cmplt 20-line , e-7 to 10' n of 19 / 10' n of 19 to 31' s of 14 / 80' n of f / 91' w on 16 | BOBB | BOBB | | BFT | P | 1741513 |
COLORADO STRUCTURES INC | BFT | P | 12/06/1999 | finish J line on 20 / 20- line ; J to F / 7 to 6 line on G | BOBB | BOBB | | BFT | P | 1741505 |
COLORADO STRUCTURES INC | BFT | P | 12/02/1999 | EAST SIDE OF BLD. , COLUMN LINES; J, H, G, K ---- GRID LINES; 10, 11, 14, 15, 16, 17 | BOBB | BOBB | | BFT | P | 1741846 |
COLORADO STRUCTURES INC | BSP | P | 11/29/1999 | ENTECH TO INSPECT REBAR IN BLOCK FOUND WALLS | ROLF | ROLF | | BSP | P | 1741839 |
RIVIERA ELECTRIC, INC. | E= | C | 01/03/2001 | PER RED ALL ELECTRIC COMPLETED
| TERRY | TERRY | | E= | C | 1742472 |
L. G. ELECTRIC | E= | C | 01/03/2001 | | TERRY | TERRY | | E= | C | 1742781 |
L. G. ELECTRIC | E= | C | 01/03/2001 | | TERRY | TERRY | | E= | C | 1742836 |
L. G. ELECTRIC | ER | C | 01/03/2001 | | TERRY | TERRY | | ER | C | 1742790 |
L. G. ELECTRIC | E= | R | 01/01/2001 | ADD ADDITIONAL WIRES AND DON'T USE THE EXISTING WIRES TO SUPPORT THE WIRING UNLESS THE MANUFACTURER SAYS IT'S OK | TERRY | TERRY | | E= | R | 1742830 |
L. G. ELECTRIC | E= | P | 12/11/2000 | TCO OK PER RED
| KEN | KEN | | E= | P | 1742821 |
L. G. ELECTRIC | E= | P | 12/11/2000 | spent 2 hours here | TERRY | TERRY | | E= | P | 1742773 |
L. G. ELECTRIC | ER | P | 12/11/2000 | systems ok . panels and switch gear temporary labled | IKE | IKE | | ER | P | 1742766 |
L. G. ELECTRIC | ER | P | 12/10/2000 | STILL NOT READY FOR THE LOWER LEVEL AND SPOT CHECK CEILING IN THE PROJECTOR AREA | TERRY | TERRY | | ER | P | 1742814 |
L. G. ELECTRIC | ER | P | 12/09/2000 | MOST OF THE CEILING AND UPSTAIRS OK'D, WILL HAVE TO SPOT CHECK CEILNG BECAUSE THEY ARE ADDING A LOT OF WIRING IN THE CEILING | TERRY | TERRY | | ER | P | 1742805 |
L. G. ELECTRIC | ER | P | 12/08/2000 | not complete. | IKE | IKE | | ER | P | 1742757 |
L. G. ELECTRIC | ER | P | 12/07/2000 | ceiling south hallway runs east and west. main hallway south from main entry. | IKE | IKE | | ER | P | 1742747 |
L. G. ELECTRIC | ER | P | 12/06/2000 | no. hallway ok. east hallway ok to elevatorok. straping cable in ceiling. | IKE | IKE | | ER | P | 1742740 |
RIVIERA ELECTRIC, INC. | E= | P | 12/06/2000 | service lp1 is complete. | IKE | IKE | | E= | P | 1742464 |
L. G. ELECTRIC | ER | R | 12/05/2000 | m/c cable low voltage wireing on grid.ceiling not complete. | IKE | IKE | | ER | R | 1742734 |
L. G. ELECTRIC | ER | R | 12/04/2000 | need support wires for electrical systems. ceiling. | IKE | IKE | | ER | R | 1742724 |
L. G. ELECTRIC | ER | P | 11/29/2000 | ceiling so. bath. soffits so. west entry. ceiling east entry. | IKE | IKE | | ER | P | 1742716 |
L. G. ELECTRIC | ER | P | 11/20/2000 | soffits center section. west entry soffits north half. remove m/c from in brick wall. | IKE | IKE | | ER | P | 1742707 |
L. G. ELECTRIC | ER | P | 11/15/2000 | walls snack bar conseccions area. | IKE | IKE | | ER | P | 1742699 |
L. G. ELECTRIC | ER | P | 11/14/2000 | hard lid center section north and south and curved soffit. | IKE | IKE | | ER | P | 1742692 |
L. G. ELECTRIC | ER | P | 11/09/2000 | studio eats scullary. bath walls. | IKE | IKE | | ER | P | 1742684 |
L. G. ELECTRIC | ER | P | 10/25/2000 | hard lid ceilings in I-max lobby-funroom walls in cinemark area-bathroom walls-bathroom walls | ARNOLD | ARNOLD | | ER | P | 1742676 |
L. G. ELECTRIC | ER | P | 10/24/2000 | i-max wall in front | ARNOLD | ARNOLD | | ER | P | 1742670 |
RIVIERA ELECTRIC, INC. | ER | P | 10/24/2000 | two sub panels and transformer north and south parking lot. for phone. | IKE | IKE | | ER | P | 1742456 |
L. G. ELECTRIC | ER | P | 10/18/2000 | entry soffits 12,13,14,16. aud 13, 14, walls. walls break rm. party rm. closet. | IKE | IKE | | ER | P | 1742661 |
L. G. ELECTRIC | ER | P | 10/17/2000 | walls hallway 15,16, panels s1, r, ri, hd, ok. | RON | RON | | ER | P | 1742654 |
L. G. ELECTRIC | ER | P | 10/16/2000 | walls consession 3, south restrooms, | RON | RON | | ER | P | 1742647 |
L. G. ELECTRIC | ER | P | 10/11/2000 | ceilings, check permit. | RON | RON | | ER | P | 1742640 |
L. G. ELECTRIC | ER | P | 10/09/2000 | main concession area a walls. | RON | RON | | ER | P | 1742632 |
RIVIERA ELECTRIC, INC. | ES | C | 09/29/2000 | 4w/ug 400 amp. 277/480. riviera. | RON | RON | | ES | C | 1742448 |
L. G. ELECTRIC | ER | P | 09/27/2000 | panels ha,hc,li, b,c,d,e,f, lvdp 2, ok. | RON | RON | | ER | P | 1742624 |
L. G. ELECTRIC | ER | P | 09/21/2000 | transformer lvdp 1 ok. | RON | RON | | ER | P | 1742616 |
L. G. ELECTRIC | ES | C | 09/20/2000 | 4w/ug 2500 amp. 277/480. L.G. ELECTRIC. | RON | RON | | ES | C | 1742609 |
L. G. ELECTRIC | ER | P | 09/14/2000 | wall, imax mezz, concession 2, poster cases, stadium 10. | RON | RON | | ER | P | 1742598 |
RIVIERA ELECTRIC, INC. | EUG | P | 09/14/2000 | traffic round area ok. | RON | RON | | EUG | P | 1742441 |
RIVIERA ELECTRIC, INC. | EUG | R | 09/13/2000 | not deep enough. | RON | RON | | EUG | R | 1742433 |
L. G. ELECTRIC | ER | P | 09/05/2000 | imax, ceiling, walls, corridor prominod. ceiling theatre 16. | RON | RON | | ER | P | 1742590 |
L. G. ELECTRIC | ER | P | 09/01/2000 | walls,ceiling # 15. | RON | RON | | ER | P | 1742582 |
L. G. ELECTRIC | ER | P | 08/31/2000 | north bath rooms, janitor closet. prominod wall corridor. | IKE | IKE | | ER | P | 1742574 |
L. G. ELECTRIC | ER | P | 08/23/2000 | theatres ceiling 12,13,14. SEATING lights theatres 4,5,6. | RON | RON | | ER | P | 1742567 |
L. G. ELECTRIC | ER | P | 08/08/2000 | south bath walls, office entry wall. | IKE | IKE | | ER | P | 1742558 |
RIVIERA ELECTRIC, INC. | EUG | P | 08/08/2000 | pole lights, ditch south west. | IKE | IKE | | EUG | P | 1742425 |
L. G. ELECTRIC | ER | P | 08/07/2000 | ceilings theater 9,10,11, + corridor wall. | RON | RON | | ER | P | 1742551 |
L. G. ELECTRIC | ER | P | 07/31/2000 | walls, 14,15,16, demissing walls, north offices, corridor. | RON | RON | | ER | P | 1742543 |
L. G. ELECTRIC | ER | P | 07/27/2000 | wall #13, ceilings 4,5,6,7,8,. | RON | RON | | ER | P | 1742534 |
RIVIERA ELECTRIC, INC. | EUG | P | 07/18/2000 | parking lot lights. | RON | RON | | EUG | P | 1742418 |
L. G. ELECTRIC | ER | P | 07/14/2000 | WALLS DEMISE 11,12, + OFFICES, CEILING THEATRE. | RON | RON | | ER | P | 1742798 |
L. G. ELECTRIC | EUG | P | 07/05/2000 | eug I max lobby, wall partial upsstairs | RON | RON | | EUG | P | 1742526 |
L. G. ELECTRIC | ESL | R | 07/03/2000 | wall support conduit, needs sheetrock stand offs, needs plaster rings, could not finned any electricans on job. | RON | RON | | ESL | R | 1742518 |
L. G. ELECTRIC | ESL | P | 06/14/2000 | slab for studio e coffee bar south center | ARNOLD | ARNOLD | | ESL | P | 1742510 |
L. G. ELECTRIC | EST | P | 05/11/2000 | feeders, aud. # 5 | IKE | IKE | | EST | P | 1742502 |
L. G. ELECTRIC | ESL | P | 04/21/2000 | concession stands 1 +3. | RON | RON | | ESL | P | 1742494 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 01/04/2001 | | JOHNW | JOHNW | | H= | C | 1742377 |
HEATING & PLUMBING ENGINEERS, INC | HD | C | 01/04/2001 | | JOHNW | JOHNW | | HD | C | 1742384 |
HEADLEY MECH HGT & AIR COND | H= | C | 12/14/2000 | GREASE HOOD COMPLETE | JOHNW | JOHNW | | H= | C | 1742487 |
HEADLEY MECH HGT & AIR COND | HD | C | 12/14/2000 | duct connection was done by HPE | JOHNW | JOHNW | | HD | C | 1742479 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 12/06/2000 | need permit for type 1 hood completed by others / label RTU'S , exhaust fans and med pressure gas lines / complete trinm angles for firedampers and diffusers | JOHNW | JOHNW | | H= | P | 1742352 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 11/20/2000 | duct work complete in lobby area | JOHNW | JOHNW | | HD | P | 1742345 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 11/13/2000 | firedamper framing lobby and coridor south end of lobby ok | JOHNW | JOHNW | | HD | P | 1742330 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 11/08/2000 | south end 1st floor and lobby restrooms duct rough in ok , but problem with framing on firedampers [12" and a 68"x18"] | JOHNW | JOHNW | | HD | P | 1742323 |
HEATING & PLUMBING ENGINEERS, INC | HI | C | 11/07/2000 | | JIMV | JIMV | | HI | C | 1742309 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 10/20/2000 | I | JOHNW | JOHNW | | H= | P | 1742295 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 10/11/2000 | AUDITORIUM 1 OK FOR MECH FINAL | JOHNW | JOHNW | | H= | P | 1742401 |
HEATING & PLUMBING ENGINEERS, INC | H= | R | 10/10/2000 | WIRES MISSING ON RADIATION DAMPERS IN THE RATED PART OF CEILING | JOHNW | JOHNW | | H= | R | 1742392 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 10/05/2000 | all mezzanine except for Imax filters also above ceiling rough ok in 1st floor lobby inc. grease duct | JOHNW | JOHNW | | HD | P | 1742274 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 10/03/2000 | radiation dampers in mezzanine center to north end ok | JOHNW | JOHNW | | HD | P | 1742267 |
HEATING & PLUMBING ENGINEERS, INC | HC | C | 10/03/2000 | | JOHNW | JOHNW | | HC | C | 1742260 |
HEATING & PLUMBING ENGINEERS, INC | H= | R | 09/25/2000 | all radiation dampers require support on all 4 cornners | JOHNW | JOHNW | | H= | R | 1742238 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/25/2000 | duct in 1st floor north end and in IMAX mezzanine above ceiling rough ok | JOHNW | JOHNW | | HD | P | 1742246 |
HEATING & PLUMBING ENGINEERS, INC | HI | P | 09/22/2000 | 60# test ok | JOHNW | JOHNW | | HI | P | 1742230 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/21/2000 | framing for fire damper south end only that required double studs | JOHNW | JOHNW | | HD | P | 1742214 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/14/2000 | AUDITORIUM 1 OK FOR INSULATION | JOHNW | JOHNW | | HD | P | 1742208 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 09/13/2000 | | JOHNW | JOHNW | | HD | P | 1742201 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 09/01/2000 | Imax , 15 & 16 complete | JOHNW | JOHNW | | H= | P | 1742163 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/31/2000 | auditorium 17 duct ok / radiation dampers still need support all 4 cornners | JOHNW | JOHNW | | HD | P | 1742156 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/23/2000 | above ceiling rough ok | JOHNW | JOHNW | | HD | P | 1742139 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/23/2000 | auditoriums 11 ,12 , 13 , 14 complete | JOHNW | JOHNW | | H= | P | 1742132 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/11/2000 | Aud. #9 and #10 final. | LYNNS | LYNNS | | H= | P | 1742099 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/11/2000 | Auditorum #2 Duct above ceiling OK to insulate. | LYNNS | LYNNS | | HD | P | 1742108 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 08/07/2000 | above ceiling rough on 13 , 14 , 15 and 16 ok | JOHNW | JOHNW | | HD | P | 1742091 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/07/2000 | 3 , 4 , 5 , 6 ,7 ,8 final | JOHNW | JOHNW | | H= | P | 1742084 |
HEATING & PLUMBING ENGINEERS, INC | H= | R | 07/31/2000 | still not right ceiling guy still has a problem | JOHNW | JOHNW | | H= | R | 1742074 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 07/28/2000 | need to streighten support on radiation dampers not all but some arn't | JOHNW | JOHNW | | H= | P | 1742066 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 07/21/2000 | aut 8,9,10 11& 12 ok above ceiling rough and ok for wrap | JOHNW | JOHNW | | HD | P | 1742059 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 07/06/2000 | auditorium 3,4,5,6,& 7 above ceiling rough complete ok to insulate | JOHNW | JOHNW | | HD | P | 1742052 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 12/11/2000 | | JIMV | JIMV | | P= | C | 1742370 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 12/08/2000 | | JIMV | JIMV | | P= | P | 1742363 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 12/07/2000 | need SS BFP for soda dispensers, 6" critical level for urinals, all else ok | JIMV | JIMV | | P= | P | 1742359 |
HEATING & PLUMBING ENGINEERS, INC | PRD | C | 11/17/2000 | | JIMV | JIMV | | PRD | C | 1742339 |
HEATING & PLUMBING ENGINEERS, INC | PTO | C | 11/07/2000 | | JIMV | JIMV | | PTO | C | 1742316 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 10/25/2000 | N. side main restrooms | JIMV | JIMV | | PTO | P | 1742302 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 10/12/2000 | 2 - 6" roof drains in entry area | JIMV | JIMV | | PRD | P | 1742289 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 10/10/2000 | S. restrooms & concession | JIMV | JIMV | | PTO | P | 1742282 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 10/02/2000 | NE concession area floor sinks ok | JIMV | JIMV | | PB | P | 1742253 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 09/22/2000 | main concession area ok | JIMV | JIMV | | PTO | P | 1742222 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 09/13/2000 | Concession (B) -- DWV and H20 ok, 2- 3" roof drains in I-Max lobby by west door, ok | LEE | LEE | | PTO | P | 1742171 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/30/2000 | Lower-level Mens and Womens restrooms DWV and H20, ok, Note: End of line common c/o for urnals on left side of urnal bank, also I-Max restrooms H20 ok | LEE | LEE | | PTO | P | 1742148 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 08/14/2000 | misc restrooms | JIMV | JIMV | | PTO | P | 1742124 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 08/14/2000 | 6" at mezzanine | JIMV | JIMV | | PRD | P | 1742115 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 06/22/2000 | drains in theatres 3 - 5 ok | JIMV | JIMV | | PRD | P | 1742045 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 06/02/2000 | northwest corner ,base only , | ELDON | ELDON | | PB | P | 1742037 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/23/2000 | center concession, ok | JIMV | JIMV | | PB | P | 1742029 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/15/2000 | main concession | JIMV | JIMV | | PB | P | 1742021 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/13/2000 | theatre restrooms | JIMV | JIMV | | PB | P | 1742014 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/08/2000 | concession C ok | JIMV | JIMV | | PB | P | 1742005 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/06/2000 | 4" GREASE & SANITARY | JIMV | JIMV | | PB | P | 1741997 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/29/2000 | GREASE ON CONCESSION B & 1 RESTROOM OK | JIMV | JIMV | | PB | P | 1742406 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/29/2000 | 4X6 STUB N. END | JIMV | JIMV | | PRD | P | 1742410 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/22/2000 | underground lateral & stub SW corner | JIMV | JIMV | | PRD | P | 1741990 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/22/2000 | 4" trunks & risers san & grease / see plumbers drawings | JIMV | JIMV | | PB | P | 1741982 |
HEATING & PLUMBING ENGINEERS, INC | PRD | P | 02/15/2000 | E wall underground stubs OK | JIMV | JIMV | | PRD | P | 1741974 |
COLORADO STRUCTURES INC | V= | P | 12/08/2000 | DOVER CAR INSPECTION & CONSTRUCTION FINAL--GFI IN MACH RM & PIT--HOISTWAY CEILING/DOORS/WALL PENETRATIONS--PROGRAM PHONE (SECURITY LINK)--PIT LIGHT--CLEAN--PIT FLOOR/MACH RM /CAR TOPS--MOVE OIL SENSORS TO MACH RM | TOM | TOM | | V= | P | 1741967 |
COLORADO STRUCTURES INC | VHW | P | 12/04/2000 | INITIAL INSPECTION--MACH RM--HOISTWAY & PIT | TOM | TOM | | VHW | P | 1741959 |