COLORADO HOME BUILDERS | B= | C | 07/30/2002 | | JIMP | JIMP | | B= | C | 1961696 |
COLORADO HOME BUILDERS | B= | R | 06/18/2002 | guard rails up, handrails up, insulation cert., deck railing complete at rock, rock complete | JIMP | JIMP | | B= | R | 1961689 |
COLORADO HOME BUILDERS | BLA | C | 02/05/2002 | | JIMP | JIMP | | BLA | C | 1961682 |
COLORADO HOME BUILDERS | BFR | C | 01/23/2002 | | JIMP | JIMP | | BFR | C | 1961675 |
COLORADO HOME BUILDERS | BFR | R | 01/10/2002 | floor framing detail at game room, engineering at pantry for header, columns west end of girder at master bedroom, column at T04, 2x4 walls upstairs with truss setting from each direction, (west bedroom), heel bearing same, follow point loads at T02A | JIMP | JIMP | | BFR | R | 1961668 |
COLORADO HOME BUILDERS | BSP | P | 10/10/2001 | two piers at entry east of house | JIMP | JIMP | | BSP | P | 1961654 |
COLORADO HOME BUILDERS | BFD | C | 01/26/2001 | no permit on site | JIMP | JIMP | | BFD | C | 1961647 |
COLORADO HOME BUILDERS | BFN | C | 01/05/2001 | STILL NEED FRONT PADS, TWO EACH 32"X32" WITH 18" SONO RISE; DRAIN, ENTIRE, ISO, FLOAT; 5% SLOPE; DESIGN AND LETTER WITH INSPECTOR | DANF | DANF | | BFN | C | 1961640 |
COLORADO HOME BUILDERS | BFT | C | 12/05/2000 | | JIMP | JIMP | | BFT | C | 1961633 |
MERIT ELECTRIC INC | E= | C | 06/11/2002 | | RED | RED | | E= | C | 1961626 |
MERIT ELECTRIC INC | ER | C | 01/07/2002 | | GARY | GARY | | ER | C | 1961612 |
MERIT ELECTRIC INC | ES | C | 01/07/2002 | ok to reseal, 2- 200 amp 3/w u/g by merit electric, inc | GARY | GARY | | ES | C | 1961619 |
MERIT ELECTRIC INC | EUG | C | 11/15/2001 | ok to cover trench, tri rated | GARY | GARY | | EUG | C | 1961605 |
CB'S CLIMATE CONTROL | H= | C | 06/17/2002 | 1-3 high combustion air | JEFF | JEFF | | H= | C | 1961759 |
CB'S CLIMATE CONTROL | H= | P | 06/14/2002 | cancelled on site per contractor | JEFF | JEFF | | H= | P | 1961752 |
CB'S CLIMATE CONTROL | H= | R | 06/13/2002 | combustion air opening to be full sized and screened with 1/4" mess as per code, 3 gas stubs at deck rough only | JEFF | JEFF | | H= | R | 1961746 |
CB'S CLIMATE CONTROL | H= | R | 06/12/2002 | cancelled by super | DOUGR | DOUGR | | H= | R | 1961739 |
CB'S CLIMATE CONTROL | H= | R | 06/11/2002 | cancelled | DOUGR | DOUGR | | H= | R | 1961731 |
CB'S CLIMATE CONTROL | H= | P | 06/07/2002 | check listing on combustion air hood, provide spec's on range or set, finish fireplaces, provide drain at humidifier main level, boiler trapped, finish strapping entran in mechanical room, secure and support csst manifolds, check unit heater garage, rest ok, 3 gas lines to deck rough only, 1-3 high combustion air | JEFF | JEFF | | H= | P | 1961724 |
CB'S CLIMATE CONTROL | HC | C | 01/04/2002 | ok to release 2 lb. meter | JEFF | JEFF | | HC | C | 1961710 |
CB'S CLIMATE CONTROL | HRR | C | 01/04/2002 | by final verify 3 remote fan accesses and reverse hood fan, still need variance on entertainment exhaust, need HRR+ if fireplace and deck heater installed before final, verify humidifier indirect waste and access, unit heater vent clearances at final, finished basement, fireplaces flush no mantels and master fireplace vent termination ok(impossible to see from surrounding grade), 4 bath fans; 3 to soffit 1 to wall cap, entertainment make up air by mechanical combustion air | JEFF | JEFF | | HRR | C | 1961717 |
CB'S CLIMATE CONTROL | HRR | R | 12/21/2001 | TRIP-FEE PER JEFF @ 21-DEC-2001 15:27:26 (NOT READY): TRIP FEE, SECOND TIME OUT, NOT READY, LIST TOO LONG, ISSUES FROM FIRST LIST STILL NOT ADDRESSED, ADDED NEW ISSUES, LEFT SECOND INSPECTION LOG | JEFF | JEFF | | HRR | R | 1961765 |
SCHNEIDER PLUMBING & HEATING | HWP | C | 12/21/2001 | verify manifold and boiler at final | JEFF | JEFF | | HWP | C | 1961570 |
HOMEOWNER | H11 | C | 12/18/2001 | HOMEOWNER HAS APPLIED FOR VARIENCE FOR EXHAUST OUTLET, SEE KYE | KYE | KYE | | H11 | C | 1961494 |
SCHNEIDER PLUMBING & HEATING | HI | C | 12/17/2001 | release from peoples, regulators, flanges at deck appliances at final, 1 30K fireplace(noted on HRR to be there and approved!) 1 40K deck heater 1 65K bbq | JEFF | JEFF | | HI | C | 1961556 |
SCHNEIDER PLUMBING & HEATING | HWP | R | 12/17/2001 | cancelled on site per contractor | JEFF | JEFF | | HWP | R | 1961563 |
CB'S CLIMATE CONTROL | HRR | R | 12/17/2001 | waive trip fee, there on HI, not ready, list too long, left partial inspection log, reinspect all | JEFF | JEFF | | HRR | R | 1961703 |
SCHNEIDER PLUMBING & HEATING | HI | P | 12/12/2001 | btu loads for 3 unknown appliances at deck, also need flanges, keep on test, need release from peoples for 2 lb. system, rest ok, 1 boiler 2 fireplaces 1 range 1 unit heater 3 ??? | JEFF | JEFF | | HI | P | 1961542 |
SCHNEIDER PLUMBING & HEATING | HO | C | 11/13/2001 | 410' of 2" yard line, 60 lb. test, may need release for 2 lb. system? | JEFF | JEFF | | HO | C | 1961535 |
SCHNEIDER PLUMBING & HEATING | HWP | P | 03/29/2001 | 65# test ok Visual ok under slab only. | JON | JON | | HWP | P | 1961528 |
SCHNEIDER PLUMBING & HEATING | P= | C | 06/17/2002 | contractor to reinstall fixtures when counter tops arrive | JEFF | JEFF | | P= | C | 1961598 |
SCHNEIDER PLUMBING & HEATING | P= | P | 06/14/2002 | cancelled on site per contractor | JEFF | JEFF | | P= | P | 1961591 |
SCHNEIDER PLUMBING & HEATING | P= | P | 06/13/2002 | need to terminate t&p and drain off steamer in basement to shower pan, rest ok | JEFF | JEFF | | P= | P | 1961584 |
SCHNEIDER PLUMBING & HEATING | P= | R | 06/11/2002 | cancelled | DOUGR | DOUGR | | P= | R | 1961577 |
SCHNEIDER PLUMBING & HEATING | PTO | C | 12/12/2001 | fall protection by next inspection or trip fee, finished basement | JEFF | JEFF | | PTO | C | 1961549 |
COLORADO HOME BUILDERS | PWO | P | 10/22/2001 | ok to corner of garage, need well installed, no permit on site | JEFF | JEFF | | PWO | P | 1961661 |
SCHNEIDER PLUMBING & HEATING | PB | C | 03/07/2001 | 4" building drain, no permit in site | DALE | DALE | | PB | C | 1961502 |