THE COPESTONE COMPANY | B= | C | 06/21/2002 | FIRE FINAL COMPLETED | KEN | KEN | | B= | C | 2125580 |
THE COPESTONE COMPANY | B= | P | 05/23/2002 | ELECTRIC FINAL OK; STILL NEED FIRE FINAL | DANF | DANF | | B= | P | 2125558 |
THE COPESTONE COMPANY | B= | P | 05/01/2002 | E=, FIRE FINAL ARE PARTIAL | RICH | RICH | | B= | P | 2125552 |
THE COPESTONE COMPANY | BSP | T | 04/04/2002 | PAID (REC#456134)ADDITIONAL PLAN REVIEW TIME: $40.000 From: RUSSELL | RUSSELL | RUSSELL | | BSP | T | 2125573 |
THE COPESTONE COMPANY | BSP | T | 03/27/2002 | PAID (REC#456133)ADDITIONAL PLAN REVIEW TIME: $40.000 From: RUSSELL | RUSSELL | RUSSELL | | BSP | T | 2125566 |
THE COPESTONE COMPANY | BFR | C | 03/06/2002 | interior non rated pc rooms, engineers letter on file structural steel | RICH | RICH | | BFR | C | 2125546 |
THE COPESTONE COMPANY | BFR | P | 02/08/2002 | PERIMETER WALLS OK | RICH | RICH | | BFR | P | 2125539 |
THE COPESTONE COMPANY | BFR | P | 01/25/2002 | INTERIOR WALLS AND LIDS | RICH | RICH | | BFR | P | 2125533 |
THE COPESTONE COMPANY | BFR | P | 01/17/2002 | 4 upper vault hard lid and soffit fronts ok | RICH | RICH | | BFR | P | 2125527 |
THE COPESTONE COMPANY | BFN | C | 09/13/2001 | COMPLETE | RICH | RICH | | BFN | C | 2125514 |
THE COPESTONE COMPANY | BFT | C | 09/13/2001 | OK | RICH | RICH | | BFT | C | 2125521 |
THE COPESTONE COMPANY | BFN | P | 09/10/2001 | SEE SHT S1 | RICH | RICH | | BFN | P | 2125509 |
THE COPESTONE COMPANY | BFT | P | 08/31/2001 | FOOTER AND PADS, SEE S-1 | RICH | RICH | | BFT | P | 2125502 |
BAKER WHITE ELECTRIC CO., INC. | E= | C | 05/21/2002 | | JERRY | JERRY | | E= | C | 2125766 |
BAKER WHITE ELECTRIC CO., INC. | E= | T | 05/20/2002 | PAID (REC#460438)install bond for pole lights correctly | JERRY | JERRY | | E= | T | 2125760 |
BAKER WHITE ELECTRIC CO., INC. | E= | P | 05/17/2002 | for final poles for parking lot lights are to be bonded and have them all open | JERRY | JERRY | | E= | P | 2125754 |
BAKER WHITE ELECTRIC CO., INC. | E= | P | 04/23/2002 | use correct ground clamps,use correct covers for floor boxes,all bath duplex receptacles to have gfci,bath shower lights to have spec sheet or fixtures to have gfci,need all outside and rooftop | JERRY | JERRY | | E= | P | 2125748 |
BAKER WHITE ELECTRIC CO., INC. | ER | C | 04/11/2002 | ceilings ok | TIMA | TIMA | | ER | C | 2125743 |
BAKER WHITE ELECTRIC CO., INC. | ER | P | 04/01/2002 | west large room and offices grid ceiling | JERRY | JERRY | | ER | P | 2125736 |
BAKER WHITE ELECTRIC CO., INC. | ES | C | 03/28/2002 | 4-wire underground,1200 amp,ct meter,baker white electric,new office building | JERRY | JERRY | | ES | C | 2125729 |
BAKER WHITE ELECTRIC CO., INC. | ES | R | 03/22/2002 | contractor made list,complete reinspection | JERRY | JERRY | | ES | R | 2125722 |
BAKER WHITE ELECTRIC CO., INC. | ER | P | 03/05/2002 | walls complete | JERRY | JERRY | | ER | P | 2125714 |
BAKER WHITE ELECTRIC CO., INC. | ER | P | 02/08/2002 | west and south outside walls | JERRY | JERRY | | ER | P | 2125707 |
BAKER WHITE ELECTRIC CO., INC. | ER | P | 01/23/2002 | walls | JERRY | JERRY | | ER | P | 2125700 |
BAKER WHITE ELECTRIC CO., INC. | ER | P | 01/16/2002 | 4 vaulted ceiling area hard lids | JERRY | JERRY | | ER | P | 2125694 |
BAKER WHITE ELECTRIC CO., INC. | EUG | P | 10/10/2001 | 4 pole lights on each end of building | JERRY | JERRY | | EUG | P | 2125686 |
BAKER WHITE ELECTRIC CO., INC. | EUG | P | 10/01/2001 | interior slab | JERRY | JERRY | | EUG | P | 2125679 |
ROBINSON MECHANICAL CO. | H= | C | 04/10/2002 | | JOHNW | JOHNW | | H= | C | 2125672 |
ROBINSON MECHANICAL CO. | HD | P | 04/03/2002 | south east cornner of the building ok for ceiling | JOHNW | JOHNW | | HD | P | 2125665 |
ROBINSON MECHANICAL CO. | HD | P | 03/28/2002 | MIDDLE AND WEST END COMPLETE INC. SMOKE DETECTORS | JOHNW | JOHNW | | HD | P | 2125658 |
S & S MECHANICAL | H= | C | 03/28/2002 | MED PRES GAS | JOHNW | JOHNW | | H= | C | 2125776 |
ROBINSON MECHANICAL CO. | HD | P | 03/26/2002 | duct in but is not sealed need to seal joints and spin-ins and then recall | JOHNW | JOHNW | | HD | P | 2125651 |
ROBINSON MECHANICAL CO. | HC | C | 02/19/2002 | SET METER FOR TEMP HEATERS | JOHNW | JOHNW | | HC | C | 2125643 |
S & S MECHANICAL | HI | C | 02/06/2002 | med pressure gas | JOHNW | JOHNW | | HI | C | 2125773 |
ROBINSON MECHANICAL CO. | HD | P | 01/22/2002 | above ceiling rough ok be sure all S&D joints are sealed / ? on 3 firesmoke dampers into elect. room | JOHNW | JOHNW | | HD | P | 2125636 |
CHEYENNE PLUMBING & HEATING, INC. | P= | C | 04/11/2002 | | LEE | LEE | | P= | C | 2125629 |
CHEYENNE PLUMBING & HEATING, INC. | P= | P | 04/10/2002 | Need 30" in front of water-heater, cap off future sink drain, complete RP spk drain | LEE | LEE | | P= | P | 2125622 |
CHEYENNE PLUMBING & HEATING, INC. | PRD | C | 01/28/2002 | Note: underground roof drains had no inspection prior to cover, above slab ok | LEE | LEE | | PRD | C | 2125615 |
CHEYENNE PLUMBING & HEATING, INC. | PTO | C | 01/25/2002 | Still need roof drain inspection | LEE | LEE | | PTO | C | 2125608 |
CHEYENNE PLUMBING & HEATING, INC. | PTO | P | 01/24/2002 | Complete H20 and test, fix leaks on w/c nipples, support horiz vents in carrier wall. 4" EOL c/outs in mens restrooms x-2 | LEE | LEE | | PTO | P | 2125601 |
CHEYENNE PLUMBING & HEATING, INC. | PB | C | 09/20/2001 | 2" water entry and test ok | LEE | LEE | | PB | C | 2125594 |
CHEYENNE PLUMBING & HEATING, INC. | PB | P | 09/19/2001 | DWV ok, need H20 | LEE | LEE | | PB | P | 2125587 |