MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | B= | C | 11/17/2003 | | TERRYB | TERRYB | | B= | C | 2233380 |
MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | B= | P | 06/26/2002 | OK TO OCCUPY, NEED TO CLEAR MECHANICAL FINAL WHEN DECISION IS MADE ON INSULATING EXPOSED GREASE DUCT | TERRYB | TERRYB | | B= | P | 2233375 |
MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | B= | P | 06/24/2002 | ok,when other finals are signed off | TERRYB | TERRYB | | B= | P | 2233368 |
MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | BFR | P | 04/30/2002 | barrel ceiling and hardlid ceiling framong north half and over stairs | TERRYB | TERRYB | | BFR | P | 2233361 |
MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | BFR | P | 04/23/2002 | bathrooms and kitchen walls | TERRYB | TERRYB | | BFR | P | 2233354 |
MURPHY CONSTRUCTORS OF COLORADO SPRINGS, INC. | BFR | P | 03/19/2002 | Platforms main level | RICK | RICK | | BFR | P | 2233347 |
JUST JENN INC | E= | C | 06/21/2002 | | TERRY | TERRY | | E= | C | 2233545 |
JUST JENN INC | E= | R | 06/20/2002 | move disconnect for makeup air | TERRY | TERRY | | E= | R | 2233540 |
JUST JENN INC | ER | C | 06/10/2002 | kitchen ceiling approved | TERRY | TERRY | | ER | C | 2233535 |
JUST JENN INC | ER | P | 05/13/2002 | bar ok'd | TERRY | TERRY | | ER | P | 2233528 |
JUST JENN INC | ER | P | 05/02/2002 | all ceilings minus the kitchen ceiling area | TERRY | TERRY | | ER | P | 2233510 |
JUST JENN INC | ER | P | 04/29/2002 | center soffet, north ceiling & kitchen walls | TERRY | TERRY | | ER | P | 2233503 |
JUST JENN INC | ER | P | 03/20/2002 | bath wall, and lid ok. no side raised area ok. | IKE | IKE | | ER | P | 2233497 |
BOCHNAK MECHANICAL, INC. | H= | C | 10/16/2003 | FINAL CAN BE COMPLETED UPON RECEIPT OF A LETTER FROM THE CITY ON AN ELEVATED PRESSURE SYSTEM. LETTER RECEIVED 10/28/03 LS. | LYNNS | LYNNS | | H= | C | 2233462 |
REFRIGERATION ENGINEERS,INC | H= | C | 05/13/2003 | BALANCE REPORT RECEIVED 5/14/03 LS. | LYNNS | LYNNS | | H= | C | 2233491 |
BOCHNAK MECHANICAL, INC. | HC | C | 06/25/2002 | SET METER | JOHNW | JOHNW | | HC | C | 2233456 |
REFRIGERATION ENGINEERS,INC | H= | P | 06/21/2002 | Corrections made, final pending decision on insulation of exposed grease duct, balance report received. | LYNNS | LYNNS | | H= | P | 2233486 |
REFRIGERATION ENGINEERS,INC | HD | P | 06/07/2002 | Need to install a back draft damper in the bathexhaust, insulate MUA duct to R-12, insyall a clean-out door in the horizontal grease duct, insulate grease duct to fan in exposed areas. | LYNNS | LYNNS | | HD | P | 2233480 |
REFRIGERATION ENGINEERS,INC | HD | P | 05/23/2002 | Grease duct OK to wrap. | LYNNS | LYNNS | | HD | P | 2233473 |
BOCHNAK MECHANICAL, INC. | HI | C | 05/21/2002 | 60# test and sizing per approved plans. Need letter on elevated pressure. | LYNNS | LYNNS | | HI | C | 2233436 |
REFRIGERATION ENGINEERS,INC | HD | P | 04/25/2002 | Duct in front under canopy and bathroom area- OK to cover. Need to revise permit to include Type 1 hood and duct. | LYNNS | LYNNS | | HD | P | 2233469 |
BOCHNAK MECHANICAL, INC. | P= | C | 06/25/2002 | | JACK | JACK | | P= | C | 2233449 |
BOCHNAK MECHANICAL, INC. | P= | P | 06/21/2002 | need handicap toilet in mens room and cleanouts under hand sinks | JACK | JACK | | P= | P | 2233443 |
BOCHNAK MECHANICAL, INC. | PTO | C | 05/15/2002 | | JACK | JACK | | PTO | C | 2233428 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/14/2002 | bar area can be closed in | JACK | JACK | | PTO | P | 2233421 |
BOCHNAK MECHANICAL, INC. | PTO | P | 04/19/2002 | 1st floor complete, need to see vtr and basement tie ins | JACK | JACK | | PTO | P | 2233414 |
BOCHNAK MECHANICAL, INC. | PTO | P | 04/18/2002 | no test on piping, no approved plans on site | JACK | JACK | | PTO | P | 2233408 |