HAMMERS CONSTRUCTION, INC | BFR | P | 08/22/2005 | WALLS OK,OTHER ROUGHS | RICH | RICH | | BFR | P | 3085471 |
HAMMERS CONSTRUCTION, INC | BFR | P | 08/22/2005 | WALLS OK, OTHER ROUGHS | RICH | RICH | | BFR | P | 3085461 |
FOSTER ELECTRIC CORPORATION | E= | C | 09/14/2005 | | MIKEC | MIKEC | | E= | C | 3085524 |
FOSTER ELECTRIC CORPORATION | E= | P | 09/07/2005 | FOR FINAL----INSTALL POWER POLES AND I D PANEL SCHEDULE CORRECTLY | JERRY | JERRY | | E= | P | 3085516 |
FOSTER ELECTRIC CORPORATION | ES | C | 08/31/2005 | COMMERCIAL SERVICE: THIS IS THE FINAL FOR THE SERVCE CHANGE FOR 3502 HARTSEL UNITS 100--110--120 THAT YOU HAVE A PARTIAL FOR AND HAVE ALREADY CONNECTED AND SET METERS,I RESEALED EVERYTHING | JERRY | JERRY | | ES | C | 3085508 |
FOSTER ELECTRIC CORPORATION | ES | P | 08/29/2005 | COMMERCIAL SERVICE: WIRE NOT PULLED TO SUB-PANEL YET | MIKEC | MIKEC | | ES | P | 3085500 |
FOSTER ELECTRIC CORPORATION | ES | P | 08/23/2005 | COMMERCIAL SERVICE: UPGRADE SERVICE FOR EXISTING STRIP MALL,THE CONTRACTOR WILL COMPLETE THE WORK AFTER YOU TURN THE POWER OFF ON FRIDAY? AND I WILL DO A COMPLETE REINSPECTION ON MONDAY,OK TO SET METERS | JERRY | JERRY | | ES | P | 3085492 |
FOSTER ELECTRIC CORPORATION | ER | P | 08/22/2005 | WALLS | JERRY | JERRY | | ER | P | 3085484 |
FOSTER ELECTRIC CORPORATION | ES | P | 08/17/2005 | COMMERCIAL SERVICE: 4-WIRE UNDERGROUND,120/208,3 DISCONNECTS AND 3 METERS,#100 IS 200 AMP,#110 IS 400 AMP WITH CT METER,#120 IS 400 WITH CT METER,UPGRADE FOR NEW RETAIL SPACES,POWER TO BE SHUT DOWN ON SUNDAY,OK TO RERECONNECT,MET WITH CONTRACTOR AND I WILL DO A COMPLETE INSPECTION ON MONDAY | JERRY | JERRY | | ES | P | 3085476 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 09/15/2005 | HVAC FINAL. | LYNNS | LYNNS | | H= | C | 3085452 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 09/14/2005 | SEE HV INSPECTION. | LYNNS | LYNNS | | H= | P | 3085443 |
PEAK HEATING & AIR CONDITIONING, INC. | HV | P | 09/14/2005 | WATER HEATER VENT THROUGH ROOF OK, NEED COLLAR AND CAP ON B-VENT AND SCREEN IN COMBUSTION AIR, SEPERATE B-VENT AND COMBUSTION AIR BY 3' VERTICAL. NEED SCREEN IN ALL EXHAUST FAN TERMINATIONS. | LYNNS | LYNNS | | HV | P | 3085436 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | C | 09/13/2005 | OAF DUCT AND FAN OK. | LYNNS | LYNNS | | HD | C | 3085429 |
PEAK HEATING & AIR CONDITIONING, INC. | HV | P | 09/13/2005 | BATH FAN EXHAUST OK. NEED TO PERMIT WATER HEATER VENT AND COMBUSTION AIR TO W/H. | LYNNS | LYNNS | | HV | P | 3085420 |
CONTRACT MECHANICAL SVC INC | P= | C | 09/23/2005 | | LEE | LEE | | P= | C | 3085413 |
CONTRACT MECHANICAL SVC INC | PTO | C | 08/18/2005 | | LEE | LEE | | PTO | C | 3085405 |
CONTRACT MECHANICAL SVC INC | PB | C | 08/08/2005 | | LEE | LEE | | PB | C | 3085397 |
CONTRACT MECHANICAL SVC INC | PB | C | 07/26/2005 | ADD W/H TO PERMIT FIXTURE LIST | LEE | LEE | | PB | C | 3085392 |