PCL CONSTRUCTION SERVICES, INC | B= | P | 12/28/2007 | Temp CO: PUBLIC IMPROVEMENTS SIGNED OFF, ZONING SIGNED OFF. LETTERS ON FILE FOR FIREPROOFING, STRUCTURAL STEEL, FRAMING, MASONARY CON, STRUCTURAL CONCRETE, AND CP672 JOINT SPRAY SEALANT, ON THE 5TH FLOOR CORE AND SHELL, AREAS ABOVE THE EXPANSION JOINTS, NEED TO FIRETAPE DRYWALL, INSTALL SMOKE SEAL AT DOOR THAT LEADS INTO STORAGE AREA.WELL CHECK IT AT TI FINALS. | JAN | JAN | | B= | P | 3091875 |
PCL CONSTRUCTION SERVICES, INC | B= | P | 12/21/2007 | Temp CO: EXTENT TCO TO 12-25-07 | JAN | JAN | | B= | P | 3091868 |
PCL CONSTRUCTION SERVICES, INC | B= | P | 11/20/2007 | EXTENT TCO TO 12-25-07 | JAN | JAN | | B= | P | 3092443 |
PCL CONSTRUCTION SERVICES, INC | B= | C | 10/24/2007 | PUBLIC IMPROVEMENTS SIGNED OFF, ZONING SIGNED OFF. LETTERS ON FILE FOR FIREPROOFING, STRUCTURAL STEEL, FRAMING, MASONARY CON, STRUCTURAL CONCRETE, AND CP672 JOINT SPRAY SEALANT, ON THE 5TH FLOOR CORE AND SHELL, AREAS ABOVE THE EXPANSION JOINTS, NEED TO FIRETAPE DRYWALL, INSTALL SMOKE SEAL AT DOOR THAT LEADS INTO STORAGE AREA.WELL CHECK IT AT TI FINALS. | ED | ED | | B= | C | 3092435 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 10/12/2007 | FIRE CAULK LEVEL 2 ABOVE CEILING O.K. / STILL NEED TO PICK UP (UL) LISTING FOR APPLICATION OF HILTI FIRE SPRAY | JEREMY | JEREMY | | BSP | P | 3092425 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 10/11/2007 | PENETRATIONS @ 6 AND 7 FLOOR O.K. | JEREMY | JEREMY | | BFR | P | 3092417 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 10/01/2007 | SEAMS @ SHAFT O.K. / STILL NEED TO FILL AND FIRE CAULK PENETRATIONS @ ABOVE FLOOR LINE | JEREMY | JEREMY | | BSP | P | 3092411 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 09/27/2007 | LEFT 2 MESSAGES ON CELL PHONE #303-667-1703 NO ANSWERE PLAES RECALL INSPECTION | BERTW | BERTW | | BSP | R | 3092401 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 09/17/2007 | SHAFT @ LOWER LEVEL PHASE 3 CORE BOARD OK/ELEVATOR LOBBY AREA FLOORS 6 AND 7 PHASE 3 TYPE-X SHEETROCK OK___________NOTICE____________ADMINISTRATION AREA CEILING GRIDS DROPPED IN WITHOUT AN ABOVE GRID INSPECTION-NEED FIRESTOPPING DETAIL FOR SYSTEM THAT HAS BEEN APPLIED BY CONTRACTOR @ 2 HOUR SEPERATION WALL - REMOVE GRIDS FOR INSPECTION | BERTW | BERTW | | BSP | P | 3092393 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 09/05/2007 | CORE BOARD @ PHASE #2 SOUTH WALL ADMINISTRATION AREA AND CORE BOARD @ LEVEL #0 CORRIDOR SEPERATION OK | BERTW | BERTW | | BSP | P | 3092385 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 08/27/2007 | SHAFT WALLS CORE BOARD OK ELEVATOR #9 LEVELS #1-2-3 OK | BERTW | BERTW | | BSP | P | 3092377 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/24/2007 | EXTERIOR FRAMING IS COMPLETE________NOTICE_______NEED STRUCTURAL WELD REPORT FOR ALL ATTACHMENTS/STILL HAVE OTHER FRAMING INSPECTIONS TO LOOK @ FOR THIS PERMIT | BERTW | BERTW | | BFR | P | 3092371 |
PCL CONSTRUCTION SERVICES, INC | BLA | P | 08/17/2007 | NORTH AND WEST PARAPET WALL @ AIR HANDLER ABOVE ADMINISTRATIVE AREA | BERTW | BERTW | | BLA | P | 3092364 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/16/2007 | 2ND FLOOR ADMIN AREA FRAMING AND 1ST LAYER CORE BOARD @ SOUTH WALL OK | BERTW | BERTW | | BFR | P | 3092356 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 08/15/2007 | FIRECAULKING @ 2ND FLOOR ADMIN AREA SHAFT CORE BOARD 1ST LAYER SHAFTS 3 AND 4 OK | BERTW | BERTW | | BSP | P | 3092347 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 08/14/2007 | FIRE CAULKING OK ON LEVEL 2 WESTERN SHAFT NEED EASTERN SHAFT COMPLETED AND FIRECAULKED/GIVE CALL AHEAD # FOR INSPECTIONS | BERTW | BERTW | | BSP | P | 3092339 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 08/10/2007 | NOT READY- FIRE CAULKING FOR LEVEL 2 AREA 3 AND 4 SHAFT | BLAKE | BLAKE | | BSP | R | 3092332 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/08/2007 | OK TO ONE SIDE 2ND FLOOR ADMIN AREA WITH SHEETROCK/SATIR TOWER FRAMING COMPLETE________DO NOT COVER WITH SHEETROCK UNTIL MONO COAT FIRE PROTECTION HAS BEEN REAPPLIED AND INSPECTED BY 3RD PARTY | BERTW | BERTW | | BFR | P | 3092325 |
PCL CONSTRUCTION SERVICES, INC | BLA | P | 08/07/2007 | LATH @ STAIR TOWER OK | BERTW | BERTW | | BLA | P | 3092317 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/02/2007 | WEST WALL SHAFT CORE BOARD @ ADMITTING AREA AND RETAIL SPACE FRAMING OK/NEED MONO-COAT REAPPLIED TO RED IRON IN FIRE ESCAPE AREA | BERTW | BERTW | | BFR | P | 3092309 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/01/2007 | WAITED FOR SUPER TO SHOW PLEASE RECALL/LEFT 2 MESSAGES | BERTW | BERTW | | BFR | P | 3092301 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/25/2007 | LOBBY AREA EXTERIOR FRAMING SOUTHWEST AREA AND SOUTH FACING PARAPET OK/RETAIL AREAS INTERIOR FRAMING LID OK-NEED 1 1/2" MINIMUM BEARING @ BOX BEAM TO COLUMNS CONNECTIONS | BERTW | BERTW | | BFR | P | 3092293 |
COBB MECHANICAL CONTRACTORS, INC. | BSP | T | 07/18/2007 | PAID (REC#761189)ADDITIONAL PLAN REVIEW TIME: $100.000 From: DARYL See updated pages M5.03, M5.33, M5.31, M5.23, M5.13 | DARYL | DARYL | | BSP | T | 3089823 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/12/2007 | NORTH WALL AT ADMINISTRATION 2ND AND 3RD FLOORS, EAST WALLS AT ELOEVATOR FLOORS 1 THRU 4, SOUTH WEST WALLS 4TH THRU 6TH FLOORS AT ELEVATOR | TERRYB | TERRYB | | BFR | P | 3092285 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/05/2007 | CORE SHELL PERMIT/ STAIR-TOWER/ EXTERIOR WALL FRAMING @ NORTH AREA - FLOORS 1 THRU 3 AND 1ST FLOOR UNDER RAMP @ NORTH AREA/NEED STRUCTURAL OBSERVATION REPORT FOR CLIPS WELDED TO STEEL BEAMS @ ALL EXTERIOR FRAMING WHERE THIS ATTACHMENT CONDITION EXSIST | BERTW | BERTW | | BFR | P | 3092277 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 05/22/2007 | PAID (REC#753566)ADDITIONAL PLAN REVIEW TIME: $150.000 From: RUSSELL Revised mechanical & plumbing | RUSSELL | RUSSELL | | BSP | T | 3092269 |
COBB MECHANICAL CONTRACTORS, INC. | BSP | T | 04/25/2007 | PAID (REC#747870)ADDITIONAL PLAN REVIEW TIME: $50.000 From: DARYL Remove overflow drains add scuppers | DARYL | DARYL | | BSP | T | 3089817 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/17/2007 | 5TH THRU 7TH FLOORS SHAFTS,STAIRS AND ELEVATOR LOBBIES | TERRYB | TERRYB | | BFR | P | 3092262 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 12/12/2006 | PAID (REC#738172)ADDITIONAL PLAN REVIEW TIME: $50.000 FROM: KYE REVISED M5.21, M5.31, ADDED RONALD MCDONALD AREA. | KYE | KYE | | BSP | T | 3092246 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 12/12/2006 | PAID (REC#738173)ADDITIONAL PLAN REVIEW TIME: $50.000 From: RUSSELL Ronald McDonald area finish | RUSSELL | RUSSELL | | BSP | T | 3092254 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 12/07/2006 | PAID (REC#738170)ADDITIONAL PLAN REVIEW TIME: $50.000 From: TIMC Added TF for Ronald McDonald House | TIMC | TIMC | | BSP | T | 3092231 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 12/07/2006 | PAID (REC#729214)ADDITIONAL PLAN REVIEW TIME: $50.00 FROM: JERRY,FOR ADDITIONAL PLAN REVIEW ON 12-7-06 | JERRY | JERRY | | BSP | T | 3092239 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 12/06/2006 | PAID (REC#729214)ADDITIONAL PLAN REVIEW TIME: $250.00 FROM: JERRY ADDITIONAL ELECTRICAL PLAN REVIEW | JERRY | JERRY | | BSP | T | 3092223 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 12/04/2006 | TCO APPROVAL FOR 1ST FLOOR , EMEGENCY/ LOBBY GOOD TILL JUNE 1ST 2007 | JOHNJ | JOHNJ | | BSP | P | 3092215 |
PCL CONSTRUCTION SERVICES, INC | B= | P | 11/22/2006 | FLOOR 'O' AND '1' OK | TERRYB | TERRYB | | B= | P | 3092207 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 11/20/2006 | PAID (REC#725917)ADDITIONAL PLAN REVIEW TIME: $300.000 FROM: GARYL ADDITIONAL TIME FOR PLAN REVIEW, PINTS NOT COMPLETE, CEI IS GOING TO GET 2 COMPLETE SETS . | GARYL | GARYL | | BSP | T | 3092199 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 11/14/2006 | NEED MORE INFORMATION REGARDING AREA TO BE INSPECTED OR CALL AHEAD NUMBER TO MEET CONTRACTOR ON SITE | TERRYB | TERRYB | | BSP | R | 3092191 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 11/02/2006 | ELECTRIC NEEDS FIRECAULKIED AT NORTH ENTRY FIRST FLOOR | TERRYB | TERRYB | | BSP | R | 3092181 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 10/20/2006 | THESE AREAS I INSPECTED AND ARE OK :1. AREA 2B, 2. SHAFT WALL AT LEVEL TWO, STAIR TWO / DID NOT SIGN ORANGE PERMIT CARD BECAUSE NO ONE AT PCL KNEW WHERE IT WAS OR WHICH ONE TERRY USUALLY SIGNS | MELANIE | MELANIE | | BFR | P | 3092172 |
PCL CONSTRUCTION SERVICES, INC | BFR | R | 10/16/2006 | NEED TO KNOW WHAT AREA OF HOSPITAL YOU WANT INSPECTED | TERRYB | TERRYB | | BFR | R | 3092164 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 10/13/2006 | AREA 3B NEED TO FINISH FIRECAULKING WALLS OVER CORRIDOR DOORS | TERRYB | TERRYB | | BSP | P | 3092157 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 10/10/2006 | WEST ENTRY HARD LID FRAMING, AND NORTH ENTRY HARDLID FRAMING OK TO INSULATE | TERRYB | TERRYB | | BFR | P | 3092148 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 10/05/2006 | ABOVE CEILING AT AREA 3A AND FIRE COMMAND ROOM | TERRYB | TERRYB | | BSP | P | 3092141 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 10/02/2006 | FOURTH FLOOR PATIENT ROOM WALLS | TERRYB | TERRYB | | BFR | P | 3092134 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 10/02/2006 | ABOVE CEILING AREA 2E | TERRYB | TERRYB | | BSP | P | 3092127 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 09/14/2006 | FIRECAULKING AT 2D | TERRYB | TERRYB | | BFR | P | 3092120 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 09/12/2006 | ABOVE CEILING AREA 2 D | TERRYB | TERRYB | | BSP | P | 3092107 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 09/01/2006 | ABOVE CEILING AREA 2B OK | TERRYB | TERRYB | | BFR | P | 3092099 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 08/31/2006 | PAID (REC#713749)ADDITIONAL PLAN REVIEW TIME: $50.000 FROM: JERRY ELECTRICAL | JERRY | JERRY | | BSP | T | 3092091 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 08/28/2006 | AREA 3C OK | TERRYB | TERRYB | | BFR | P | 3092084 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 08/28/2006 | ABOVE CEILING AT AREA 2B NOT READY | TERRYB | TERRYB | | BSP | R | 3092077 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/31/2006 | OFFICES AT MAIN ENTRY SECOND FLOOR | TERRYB | TERRYB | | BFR | P | 3092069 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 07/31/2006 | ABOVE CEILING AT AREA 2B | TERRYB | TERRYB | | BSP | P | 3092060 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/21/2006 | FIX AREA 1 A AT DOORS 1154 1156 CAULK CONDUIT ABOVE DOOR 1220, FRAMING AT 3RD FLOOR AREA 2 OK | TERRYB | TERRYB | | BFR | P | 3092053 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/20/2006 | PENTHOUSE WALLS AT SOUTH STAIR TOWER | TERRYB | TERRYB | | BFR | P | 3092046 |
PCL CONSTRUCTION SERVICES, INC | BFN | P | 07/10/2006 | AREA 1D SMOKE WALLS OK, NEED TI FINISHISH 1 HR PROTECTION AT ROOM 1276 AND DOORS 1185 AND 1196 | TERRYB | TERRYB | | BFN | P | 3091862 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 07/06/2006 | ABOVE CEILING FIRECAULKING AT PATIENT ROOMS AREA 1C | TERRYB | TERRYB | | BSP | P | 3092039 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 06/27/2006 | ABOVE CEILING AT FIRST FLOOR, FRAMING AT AREA 1 OK | TERRYB | TERRYB | | BSP | P | 3092032 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 06/26/2006 | COULD NOT PERFORM INSPECTION NO POWER ON FIRST FLOOR | TERRYB | TERRYB | | BSP | R | 3092024 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 06/13/2006 | SECOND FLOOR SHAFTS T MECHANICAL AND ELEVATOR | TERRYB | TERRYB | | BFR | P | 3092018 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 06/07/2006 | SOUTH STAIR # 1 EXTERIOR FRAME / EXTERIOR SOFFIT 1ST LEVEL SW CORNER AT THE GARDEN AREA / NORTH ENTRANCE CANOPY SWOFFIT. | ED | ED | | BFR | P | 3092009 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 05/22/2006 | SECOND FLOOR AREA 2 | TERRYB | TERRYB | | BFR | P | 3092003 |
PCL CONSTRUCTION SERVICES, INC | BFR | R | 05/17/2006 | Didnot show called ahead | TERRYB | TERRYB | | BFR | R | 3091995 |
PCL CONSTRUCTION SERVICES, INC | BFR | R | 05/16/2006 | CALLED AHEAD, CONTACT DID NOT SHOW | TERRYB | TERRYB | | BFR | R | 3091987 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 05/12/2006 | RATED SHAFTWALL CEILING AT CORRIDOR 1364 | TERRYB | TERRYB | | BFR | P | 3091980 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 05/05/2006 | FIRESAFING AT CURTAIN WALLS,SECOND FLOOR AND PART OF THIRD FLOOR | TERRYB | TERRYB | | BSP | P | 3091972 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/24/2006 | AREA 1 FIRST FLOOR ELEVATOR SHAFTS FIRST FLOOR | TERRYB | TERRYB | | BFR | P | 3091964 |
PCL CONSTRUCTION SERVICES, INC | BSP | R | 04/07/2006 | SCREW INSPECTION NOT REQUIRED | TERRYB | TERRYB | | BSP | R | 3091957 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/05/2006 | DENSEGLASS AT CEILING IN TUNNEL, FRAMING BASEMENT LEVEL, SHAFT ELECTRIC ROOM #2700 | TERRYB | TERRYB | | BFR | P | 3091949 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 03/30/2006 | FIRST FLOOR AREA 2 | TERRYB | TERRYB | | BFR | P | 3091940 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 03/22/2006 | HARD LID FRAMING AT FRESH AIR TUNNEL AND WALLS AT TUNNEL OK TO COVER WHEN ELECTRIC IS SIGNED OFF | TERRYB | TERRYB | | BFR | P | 3091932 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 03/13/2006 | NORTH SHAFT AND TWO WALLS AT SECOND SHAFT AT ELECTRIC ROOM FIRST FLOOR ROOM 1007 | TERRYB | TERRYB | | BSP | P | 3091924 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 03/10/2006 | EXTERIOR WALLS AT SOUTH END OF BUILDING, | TERRYB | TERRYB | | BFR | P | 3091916 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 01/23/2006 | WALL AT AREA 0023 AIR INTAKE AREA | TERRYB | TERRYB | | BFR | P | 3091909 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 12/12/2005 | DENSGLASS AT AIR INTAKE HALL IN BASEMENT | TERRYB | TERRYB | | BSP | P | 3091900 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 12/12/2005 | OK TO PREROCK AT DUCTWORK AREAS IN BASEMENT | TERRYB | TERRYB | | BFR | P | 3091892 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 10/28/2005 | PAID (REC#671858)ADDITIONAL PLAN REVIEW TIME: $100.000 From: RUSSELL Added additional underground piping | RUSSELL | RUSSELL | | BSP | T | 3091882 |
J. E. DUNN CONSTRUCTION COMPANY | BFN | P | 09/23/2005 | PICKED UP ENGINEERS REPORT FOR INSPETIONS PERFORMED FOR TURNER CONST AND JE DUNN FROM THE BEGINNING THRU AUGUST | TERRYB | TERRYB | | BFN | P | 3092606 |
J. E. DUNN CONSTRUCTION COMPANY | BSP | P | 08/05/2005 | MET WITH TONY, THE SUPERVISOR HE WILL PROVIDE ME WITH ENGINEERING REPORTS FOR WORK PERFORMED BY TURNER CONSTRUCTION PRIOR TO THE JOB BEING TAKEN OVER BY JE DUNN | TERRYB | TERRYB | | BSP | P | 3092597 |
RIVIERA ELECTRIC | E= | C | 11/16/2007 | HEADWALLS WILL BE INSTALLED UNDER PERMIT # G46249 | MATTHEW | MATTHEW | | E= | C | 3093545 |
RIVIERA ELECTRIC | E= | P | 11/01/2007 | COMPLETE EXCEPT HEADBOARDS NOT INSTALLED IN PODS 3315 AND 3336 | MATTHEW | MATTHEW | | E= | P | 3093537 |
RIVIERA ELECTRIC | E= | P | 10/31/2007 | COMPLETE EXCEPT FOR EQUIPMENT HOOK UP IN ROOM 7086 | MATTHEW | MATTHEW | | E= | P | 3093529 |
RIVIERA ELECTRIC | E= | P | 10/19/2007 | SIXTH FLOOR EXIT SIGNS COMPLETED, SUPPORT WIRES FOR PENDANT LIGHTS COMPLETED, SECOND FLOOR ROOM MARKED ON PLANS E3.22 COMPLETED | MATTHEW | MATTHEW | | E= | P | 3093521 |
RIVIERA ELECTRIC | E= | P | 10/18/2007 | MARKED ON PLANS E3.13, E3.21, E3.23 STAIRWELL PHASE 3 AND ROOF TOP---- CHECK OCPD FOR CU WITH HEAT 30 AMP FUSES INSTALLED NAME PLATE SHOWS MAX OF 25 AT 208 V | MATTHEW | MATTHEW | | E= | P | 3093513 |
RIVIERA ELECTRIC | ER | P | 10/18/2007 | SECOND FLOOR CEILING ON PLANS E4.22A AND LEVEL 1 ENTRY CEILING OK | MATTHEW | MATTHEW | | ER | P | 3093503 |
RIVIERA ELECTRIC | E= | P | 10/17/2007 | NOT READY | MATTHEW | MATTHEW | | E= | P | 3093496 |
RIVIERA ELECTRIC | E= | P | 10/17/2007 | FIFTH FLOOR ELECTRIC ROOMS OK---SEVENTH FLOOR ELECTRIC ROOM: NEED PANEL BLANKS, #10 BOND BETWEEN PANELS, SPRINKLER PIPE OVER PANELS; SEVENTH FLOOR IT ROOM: REMOUNT 4 SQ BOX, TIGHTEN GEC AT GROUND BAR, BOND IT RACKS | MATTHEW | MATTHEW | | E= | P | 3093488 |
RIVIERA ELECTRIC | E= | P | 10/17/2007 | INSTALL LOCKNUTS TO RTU 2R VFD, NEED IN-USE COVERS FOR OUTLETS, DISCONNECT FOR ACC-8 REQUIRED TO BE READILY ACCESSIBLE | MATTHEW | MATTHEW | | E= | P | 3093480 |
RIVIERA ELECTRIC | E= | P | 10/15/2007 | ADMITTANCE & GIFT SHOP | THOMAS | THOMAS | | E= | P | 3093472 |
RIVIERA ELECTRIC | E= | P | 10/15/2007 | SIXTH FLOOR ELECTRIC ROOMS AND SEVENTH FLOOR NORTH OK EXCEPT 1 PANEL BOARD NOT BONDED WITH #10, FINISH PANEL SCHEDULES AND INSTALL BREAKER BLANKS, SEVENTH FLOOR IT ROOM AND 6018 CORE AND SHELL OK | MATTHEW | MATTHEW | | E= | P | 3093467 |
RIVIERA ELECTRIC | E= | P | 10/11/2007 | ALL 5 GOOD EXCLUDING REMOVING TEMTORARY LIGHTS & POWER----TELEPHONE ROOMS & ELECTRIC PANELS [CORRECT LABELING] | THOMAS | THOMAS | | E= | P | 3093459 |
RIVIERA ELECTRIC | E= | P | 10/10/2007 | LEVEL 0 PHASE 3 -- MARKED ON PLANS E3.03 OK | MATTHEW | MATTHEW | | E= | P | 3093454 |
RIVIERA ELECTRIC | E= | P | 10/08/2007 | CORE AND SHELL TE3.62 AND E 3.62-- SIXTH FLOOR MARKED ON PLANS ------- MISSING 3 VIEW BOXES AND PROVIDE PAPERWORK ON E MON D MON (NEED OCPD AND CHECK SPLICES) | MATTHEW | MATTHEW | | E= | P | 3093445 |
RIVIERA ELECTRIC | ER | P | 10/08/2007 | WALLS ROOM 2437 | MATTHEW | MATTHEW | | ER | P | 3093436 |
RIVIERA ELECTRIC | ER | P | 10/08/2007 | WALLS ROOM 2437 AND CEILING TE4.62 OK | MATTHEW | MATTHEW | | ER | P | 3093428 |
RIVIERA ELECTRIC | E= | P | 10/05/2007 | SIXTH FLOOR FINAL MARKED ON PLANS TE 3.61 OK ---- WALL ROUGH MARKED ON PLANS E3.13 OK | MATTHEW | MATTHEW | | E= | P | 3093420 |
RIVIERA ELECTRIC | E= | P | 10/04/2007 | FOURTH FLOOR MARKED ON PLANS E3.41-- THIRD FLOOR ELECTRIC ROOMS OK | MATTHEW | MATTHEW | | E= | P | 3093412 |
RIVIERA ELECTRIC | E= | P | 10/02/2007 | THIRD FLOOR EXCLUDING ELEC ROOMS AND ROOMS 3N3111, 3N3112- STILL NEED TO INSTALL HEAD BOARDS IN ROOMS NOTED IN PREVIOUS INSPECTION | MATTHEW | MATTHEW | | E= | P | 3093406 |
RIVIERA ELECTRIC | E= | P | 10/01/2007 | CANCELLED BY CONTRACTOR | MATTHEW | MATTHEW | | E= | P | 3093400 |
RIVIERA ELECTRIC | E= | P | 09/28/2007 | AREA MARKED ON PLANS E4.32A OK | MATTHEW | MATTHEW | | E= | P | 3093397 |
RIVIERA ELECTRIC | E= | P | 09/27/2007 | rooms marked on e4.31a ok ------ need headboards installed in pods 3315 and 3336---- before final | MATTHEW | MATTHEW | | E= | P | 3093391 |
RIVIERA ELECTRIC | E= | P | 09/26/2007 | third floor marked e4.31a | MATTHEW | MATTHEW | | E= | P | 3093385 |
RIVIERA ELECTRIC | E= | P | 09/21/2007 | second floor marked on plans e4.21 | MATTHEW | MATTHEW | | E= | P | 3093379 |
RIVIERA ELECTRIC | E= | P | 09/20/2007 | second floor north marked on plans ok | MATTHEW | MATTHEW | | E= | P | 3093373 |
RIVIERA ELECTRIC | ER | P | 09/19/2007 | GRID CIELINGS E 4.23 | THOMAS | THOMAS | | ER | P | 3093369 |
RIVIERA ELECTRIC | ER | R | 09/18/2007 | cancelled by contractor at time of call ahead | MATTHEW | MATTHEW | | ER | R | 3093363 |
RIVIERA ELECTRIC | ER | P | 09/17/2007 | CEILING MARKED ON PLANS E4.23 | MATTHEW | MATTHEW | | ER | P | 3093357 |
RIVIERA ELECTRIC | E= | P | 09/17/2007 | SECOND FLOOR AREA MARKED ON PLANS OK ------ NEED TO CHECK PENDANT LIGHTS ABOVE SINKS FOR SUPPORT WIRES ------ | MATTHEW | MATTHEW | | E= | P | 3093352 |
RIVIERA ELECTRIC | ER | P | 09/14/2007 | CEILING 4.23 AND 4.22B | MATTHEW | MATTHEW | | ER | P | 3093345 |
RIVIERA ELECTRIC | E= | P | 09/13/2007 | SECOND FLOOR--PRINTS E 4.21A & E 3.21A | THOMAS | THOMAS | | E= | P | 3093340 |
RIVIERA ELECTRIC | ER | P | 09/12/2007 | HARDLIDS ON 4.23 | MATTHEW | MATTHEW | | ER | P | 3093334 |
RIVIERA ELECTRIC | EUG | P | 09/07/2007 | EUG NORTH DRIVEWAY COMPLETE | THOMAS | THOMAS | | EUG | P | 3093328 |
RIVIERA ELECTRIC | ER | P | 09/06/2007 | WALLS 4.23 &3.23 | THOMAS | THOMAS | | ER | P | 3093322 |
RIVIERA ELECTRIC | ER | P | 09/05/2007 | GRID CIELING E 4.23 | THOMAS | THOMAS | | ER | P | 3093316 |
RIVIERA ELECTRIC | EUG | P | 09/05/2007 | NORTH DRIVEWAY | THOMAS | THOMAS | | EUG | P | 3093310 |
RIVIERA ELECTRIC | ER | P | 09/05/2007 | GRID CIELINGS---E 4.23 | THOMAS | THOMAS | | ER | P | 3093304 |
RIVIERA ELECTRIC | ER | P | 08/31/2007 | WALL AND HARDLID MARKED ON 3.23 AND 4.23 | MATTHEW | MATTHEW | | ER | P | 3093298 |
RIVIERA ELECTRIC | ER | P | 08/30/2007 | WALLS 3.23 | THOMAS | THOMAS | | ER | P | 3093292 |
RIVIERA ELECTRIC | ER | P | 08/24/2007 | SOFFITS E4.23 AND WALL E3.23 OK | MATTHEW | MATTHEW | | ER | P | 3093288 |
RIVIERA ELECTRIC | ER | P | 08/22/2007 | WALLS AND HARDLID MARKED ON E3.23 | MATTHEW | MATTHEW | | ER | P | 3093282 |
RIVIERA ELECTRIC | ER | P | 08/20/2007 | WALLS ON E 3.23, HARDLID ON E 4.23 OK | MATTHEW | MATTHEW | | ER | P | 3093276 |
RIVIERA ELECTRIC | ER | P | 08/13/2007 | WALLS E3.23 AND NW STAIRWELL PHASE 3 LEVEL 7 OK | MATTHEW | MATTHEW | | ER | P | 3092657 |
RIVIERA ELECTRIC | ER | P | 08/09/2007 | WALLS MARKED ON PLANS E3.23, HARDLID E4.23, NW STAIRWELL PHASE 3 LEVEL 1 THRU 6 0K | MATTHEW | MATTHEW | | ER | P | 3093269 |
RIVIERA ELECTRIC | ER | P | 08/06/2007 | WALLS E5.03 OK | MATTHEW | MATTHEW | | ER | P | 3093262 |
RIVIERA ELECTRIC | ER | P | 08/01/2007 | WALLS & SOFFITS E3.23 | THOMAS | THOMAS | | ER | P | 3093255 |
RIVIERA ELECTRIC | ER | P | 07/27/2007 | WALLS 3.22 | THOMAS | THOMAS | | ER | P | 3093249 |
RIVIERA ELECTRIC | ER | P | 07/23/2007 | WALLS E3.13 | THOMAS | THOMAS | | ER | P | 3093244 |
RIVIERA ELECTRIC | ER | P | 07/17/2007 | WALLS 3.03 | THOMAS | THOMAS | | ER | P | 3093236 |
RIVIERA ELECTRIC | ER | P | 06/21/2007 | WEST EXTERIOR SOFFIT MARKED ON OFFICE PLANS E4.23, MISSING BALLAST ON FIXTURE MARKED ON PLANS, NEED TO VERIFY BALLAST INSTALLED | MATTHEW | MATTHEW | | ER | P | 3093228 |
RIVIERA ELECTRIC | ER | P | 05/31/2007 | GRID CIELINGS E 4.41A | THOMAS | THOMAS | | ER | P | 3093221 |
RIVIERA ELECTRIC | ER | P | 03/28/2007 | WALLS 3.31
| THOMAS | THOMAS | | ER | P | 3093213 |
RIVIERA ELECTRIC | ER | P | 01/09/2007 | WALLS E3.41 CIELINGS E4.42A | THOMAS | THOMAS | | ER | P | 3093205 |
RIVIERA ELECTRIC | ER | P | 12/06/2006 | CEILING MARKED ON PLANS E4.31A OK | MATTHEW | MATTHEW | | ER | P | 3093197 |
RIVIERA ELECTRIC | ER | P | 12/05/2006 | WALLS & CIELINGS--3.31 & 4.31 | THOMAS | THOMAS | | ER | P | 3093190 |
RIVIERA ELECTRIC | ER | P | 12/04/2006 | WALLS, 3.31 & 3.41 | THOMAS | THOMAS | | ER | P | 3093183 |
RIVIERA ELECTRIC | E= | P | 11/21/2006 | FIRST FLOOR COMPLETE [ALL PLATES MARKED & INSTALLED] | THOMAS | THOMAS | | E= | P | 3093176 |
RIVIERA ELECTRIC | ER | P | 11/20/2006 | WALLS & SOFFITS 3.41----CORE & SHELL FLOOR 3.52 & 3.51 [WALLS ONLY | THOMAS | THOMAS | | ER | P | 3093169 |
RIVIERA ELECTRIC | E= | P | 11/16/2006 | PHASE 2 , LEVEL 1---CT ROOM LEVEL 1 | THOMAS | THOMAS | | E= | P | 3093161 |
RIVIERA ELECTRIC | ER | P | 11/15/2006 | CIELINGS 3.14 | THOMAS | THOMAS | | ER | P | 3093155 |
RIVIERA ELECTRIC | ER | P | 11/09/2006 | FOURTH FLOOR WALLS AND HARDLIDS MARKED ON PLANS | MATTHEW | MATTHEW | | ER | P | 3093147 |
RIVIERA ELECTRIC | E= | P | 11/09/2006 | FIRST FLOOR AND FIRST FLOOR RAD ROOMS, RESUCITATION ROOMS AND IT ROOM OK---- EXCLUDING PHASE 2 B, AND ROOMS WITH EMERGENCY CIRCUITS NOT LABELED | MATTHEW | MATTHEW | | E= | P | 3093139 |
RIVIERA ELECTRIC | E= | P | 11/07/2006 | FIRST FLOOR EXCLUDING RADIOLOGY, PHONE ROOM,,RESUSITATION. CAT | THOMAS | THOMAS | | E= | P | 3093132 |
RIVIERA ELECTRIC | E= | P | 11/07/2006 | FIRST FLOOR OK EXCLUDING: RAD CT ROOMS, IT ROOM, RESUCITATION ROOM AND SE SHELL | MATTHEW | MATTHEW | | E= | P | 3093126 |
RIVIERA ELECTRIC | E= | P | 11/02/2006 | NORTH FIRST FLOOR, EXCLUDING RADIOLOGY---CORRECT PANEL SCHEDULES | THOMAS | THOMAS | | E= | P | 3093116 |
RIVIERA ELECTRIC | E= | P | 11/02/2006 | FIRST FLOOR NORTH OK | MATTHEW | MATTHEW | | E= | P | 3093108 |
RIVIERA ELECTRIC | ER | P | 11/01/2006 | WALLS MARKED ON E3.41 AND E3.42 OK---- CEILINGS MARKED ON E4.31 AND E4.32 OK | MATTHEW | MATTHEW | | ER | P | 3092648 |
RIVIERA ELECTRIC | ER | P | 10/25/2006 | CIELINGS E4.12A | THOMAS | THOMAS | | ER | P | 3093100 |
RIVIERA ELECTRIC | ER | R | 10/24/2006 | DEFECTIVE GFCI AHU-5 | THOMAS | THOMAS | | ER | R | 3093092 |
RIVIERA ELECTRIC | E= | P | 10/24/2006 | LEVEL 0 OK | MATTHEW | MATTHEW | | E= | P | 3093085 |
RIVIERA ELECTRIC | ER | P | 10/23/2006 | WALLS E3.42 & SOFFITS E4.42B | THOMAS | THOMAS | | ER | P | 3093076 |
RIVIERA ELECTRIC | ER | P | 10/20/2006 | WALLS 3.13 | THOMAS | THOMAS | | ER | P | 3093071 |
RIVIERA ELECTRIC | E= | R | 10/20/2006 | CHANGE FUSES ON 2 PUMPS----CORRECT PANEL SCHEDULES [SOME BREAKERS NOT MARKED---ADD SIGNAGE FOR MAIN SWITCHGEAR---MARK ALL PANELS & DISCONNECTS-----COVERS FOR 4 FIRE ALARM BOXES | THOMAS | THOMAS | | E= | R | 3093063 |
RIVIERA ELECTRIC | ER | P | 10/13/2006 | WALLS 4.21A | THOMAS | THOMAS | | ER | P | 3093055 |
RIVIERA ELECTRIC | ER | P | 10/13/2006 | WALLS E3.42 | JOSEPH | JOSEPH | | ER | P | 3093047 |
RIVIERA ELECTRIC | ER | P | 10/11/2006 | WALLS --- HARDLIDS---CEILINGS E3.42--4.31A---4.21A | THOMAS | THOMAS | | ER | P | 3093039 |
RIVIERA ELECTRIC | ER | P | 10/05/2006 | WALLS & CIELINGS E3.32 | THOMAS | THOMAS | | ER | P | 3093031 |
RIVIERA ELECTRIC | ER | P | 09/29/2006 | WALLS & HARDLIDS E 3.42 | THOMAS | THOMAS | | ER | P | 3093021 |
RIVIERA ELECTRIC | ER | P | 09/27/2006 | WALLS 3.31 & 3.32--HARDLIDS 4.31A | THOMAS | THOMAS | | ER | P | 3093013 |
RIVIERA ELECTRIC | ER | P | 09/20/2006 | WALLS & HARDLIDS 3.31 --- 4.31A | THOMAS | THOMAS | | ER | P | 3093006 |
RIVIERA ELECTRIC | ER | P | 09/12/2006 | WALLS E3.31 | THOMAS | THOMAS | | ER | P | 3092637 |
RIVIERA ELECTRIC | ER | P | 09/08/2006 | CIELING & SOFFITS E4.21A | THOMAS | THOMAS | | ER | P | 3092998 |
RIVIERA ELECTRIC | EP | R | 09/05/2006 | TRANSFORMER TECSDP-5, NEEDS LONGER BOLTS & LOOSEN TRANSPORT BOLTS----PANELS COMPLETE, NBSDP-1, NBSDP-2, EEQBSDP-3, TEQ-1, ECBSDP-4, ECBSD-5, | THOMAS | THOMAS | | EP | R | 3092991 |
RIVIERA ELECTRIC | ER | P | 08/31/2006 | CHECK WITH FACTORY REGARDING LINE LOAD OF FIRE PUMP EMERGENCY BREAKER----PULL GROUND WIRE BETWEEN FIRE PUMP DISCONNECT & TRANSFORMER | THOMAS | THOMAS | | ER | P | 3092985 |
RIVIERA ELECTRIC | ER | P | 08/29/2006 | CIELINGS -4.22A&B WALLS 3.11 | THOMAS | THOMAS | | ER | P | 3092976 |
RIVIERA ELECTRIC | EP | P | 08/17/2006 | ALL PANELS FIRST FLOOR [EXLUDING 1 NOT INSTALLED] | THOMAS | THOMAS | | EP | P | 3092969 |
RIVIERA ELECTRIC | ER | P | 08/17/2006 | CEILINGS MARKED ON ELECTRICIANS PLANS E4.11A OK | MATTHEW | MATTHEW | | ER | P | 3092960 |
RIVIERA ELECTRIC | EP | P | 08/16/2006 | PANELS EEQ-2==ELSBSDP-2==EEQ1 ATS==TLSB==EEQBLA==EEQBRA==ELSBRA==ELSBLA==ELSBSDP-1==ELS-1 ATS==EC-2 ATS==TLS==ECBSDP-2==EEQBSDP-2==EC-1 ATS==TECSDP-4==TNBSDP-1==NBRSDP-1 | THOMAS | THOMAS | | EP | P | 3092629 |
RIVIERA ELECTRIC | ER | P | 08/16/2006 | WALLS E6.14---CIELINGS 4.11A---WALLS & HARDLIDS E3.32---CIELINGS E4.22A | THOMAS | THOMAS | | ER | P | 3092622 |
RIVIERA ELECTRIC | ER | P | 08/14/2006 | WALLS 3.32---HARDLIDS 4.32A & B---CIELINGS 4.11A & B | THOMAS | THOMAS | | ER | P | 3092953 |
RIVIERA ELECTRIC | ER | P | 08/10/2006 | WALLS 3.32----HARDLIDS 4.32A----CIELINGS4.IIB | THOMAS | THOMAS | | ER | P | 3092945 |
RIVIERA ELECTRIC | EP | P | 08/08/2006 | PANELS NBMCCI, NBSDP-1, EEQ-2, EEQBMCC-1, NBMA, NBMB---TRANSFORMER TNBSDP-2 [NOT ALL BRANCH CIRCUITS HAVE BEEN PULLED IN SOME PANELS] | THOMAS | THOMAS | | EP | P | 3092936 |
RIVIERA ELECTRIC | ER | P | 08/04/2006 | CIELINGS 4.11A & SOFFIT 4.21.B | THOMAS | THOMAS | | ER | P | 3092929 |
RIVIERA ELECTRIC | ES | C | 08/01/2006 | COMMERCIAL SERVICE: 7000 AMP 3 PHASE 480 V SERVICE FOR HOSPITAL ADDITION BY RIVIERA ELECTRIC: SET METER | MATTHEW | MATTHEW | | ES | C | 3092921 |
RIVIERA ELECTRIC | ER | P | 08/01/2006 | WALLS & SERVICE REVIEW | THOMAS | THOMAS | | ER | P | 3092913 |
RIVIERA ELECTRIC | ER | P | 08/01/2006 | WALLS IN RAD ROOM MARKED ON PLANS E6.14 AND WALLS ON PLANS E3.22 OK | MATTHEW | MATTHEW | | ER | P | 3092904 |
RIVIERA ELECTRIC | ES | P | 07/31/2006 | REVIEW SERVICE GROUNDING----CIELINGS 4.11A & B----CIELINGS E4.21B | THOMAS | THOMAS | | ES | P | 3092897 |
RIVIERA ELECTRIC | ER | P | 07/31/2006 | SWITCHGEAR GROUNDING | SHELBY | SHELBY | | ER | P | 3092889 |
RIVIERA ELECTRIC | ER | P | 07/28/2006 | WALLS AREA 2C E3.21-----WALLS & HARDLIDS AREA 3B E3.32 | THOMAS | THOMAS | | ER | P | 3092881 |
RIVIERA ELECTRIC | ER | P | 07/26/2006 | CEILINGS MARKED ON PLANS E4.12B, E4.12A AND E4.11A OK--- LEAVE 1 TILE OUT IN EXAM ROOMS TO CHECK EXAM LIGHTS | MATTHEW | MATTHEW | | ER | P | 3092873 |
RIVIERA ELECTRIC | ER | P | 07/21/2006 | WALLS E4.32A AND HARDLIDS ON E3.32 OK | MATTHEW | MATTHEW | | ER | P | 3092864 |
RIVIERA ELECTRIC | ER | P | 07/18/2006 | CIELINGS E4.11A---HARDLIDS E4.21A----NURSES STATION E3.22 | THOMAS | THOMAS | | ER | P | 3092856 |
RIVIERA ELECTRIC | ER | P | 07/18/2006 | | SHELBY | SHELBY | | ER | P | 3092848 |
RIVIERA ELECTRIC | ER | P | 07/13/2006 | CIELINGS---E4.11A & E4.12A | THOMAS | THOMAS | | ER | P | 3092840 |
RIVIERA ELECTRIC | ER | P | 07/11/2006 | HARDLIDS E4.21A-----CIELINGS E4.12A | THOMAS | THOMAS | | ER | P | 3092833 |
RIVIERA ELECTRIC | ER | P | 07/07/2006 | CIELINGS & HARDLIDS E4.12A & B---SOFFITS 4.21A & B---HARDLIDS 4.21A | THOMAS | THOMAS | | ER | P | 3092825 |
RIVIERA ELECTRIC | ER | P | 07/05/2006 | CIELINGS E4.I2, AREA 1C----NURSE STATIONS, 1B-1A-1E, E3.11---WALLS 2E, E3.21----HARD LIDS E4.21A | THOMAS | THOMAS | | ER | P | 3092816 |
RIVIERA ELECTRIC | ER | P | 06/30/2006 | CIELINGS E4.12A WALLS E3.21 | THOMAS | THOMAS | | ER | P | 3092808 |
RIVIERA ELECTRIC | ER | P | 06/26/2006 | AREA 1-B CIELINGS PARTIAL SHEET E 4.12A | THOMAS | THOMAS | | ER | P | 3092613 |
RIVIERA ELECTRIC | ER | P | 06/23/2006 | EXTENSION OF JUNE 22 INSPECTION | THOMAS | THOMAS | | ER | P | 3092801 |
RIVIERA ELECTRIC | ER | P | 06/22/2006 | AREA 2D, SHEET E3.21 & E3.22---WALLS & 2 HARDLIDS SOUTHEST AREA [3/4 OF SECOND FLOOR] | THOMAS | THOMAS | | ER | P | 3092793 |
RIVIERA ELECTRIC | ER | P | 06/21/2006 | LEVEL 1 AREA 1B SECURITY OFFICE WALLS---E6.II PLATFORMS---SOUTH WEST SOFFITS [COURTYARD] | THOMAS | THOMAS | | ER | P | 3092785 |
RIVIERA ELECTRIC | EUG | P | 06/16/2006 | TRANSFORMER SECONDARIES ,INCLUDING GRC FIRE PUMP FEED [BOULDER STREET TRANSFORMER] | THOMAS | THOMAS | | EUG | P | 3092777 |
RIVIERA ELECTRIC | ER | P | 06/15/2006 | HARD LIDS MARKED ON SHEET E3.22 EXCLUDING2516 ALSO WALLS ONLY 2171 & 2172 | THOMAS | THOMAS | | ER | P | 3092766 |
RIVIERA ELECTRIC | ER | P | 05/31/2006 | SECOND FLOOR WALLS MARKED ON PLANS E3.22 AND NURSES STATIONS MARKED ON PLANS E6.13 DETAILS 11 AND 12 OK | MATTHEW | MATTHEW | | ER | P | 3092758 |
RIVIERA ELECTRIC | ER | P | 05/26/2006 | WALLS AND HARD LIDS IN AREA 1A MARKED ON PLANS E3.11 OK | MATTHEW | MATTHEW | | ER | P | 3092750 |
RIVIERA ELECTRIC | ER | P | 05/16/2006 | ALL HARDLIDS ON FIRST FLOOR, WALLS ON LEVEL 2 MARKED ON E3.22; HARDLIDS IN AREA 2A MARKED ON E4.22A; HARDLIDS AREA 1B MARKED ON E4.12A | MATTHEW | MATTHEW | | ER | P | 3092743 |
RIVIERA ELECTRIC | ER | P | 05/11/2006 | HARD LIDS MARKED ON PLANS E4.11 OK TO COVER AND WALLS MARKED ON E3.11 AND E6.11 OK | MATTHEW | MATTHEW | | ER | P | 3092735 |
RIVIERA ELECTRIC | EUG | P | 05/04/2006 | BLDG TO BLDG OK TO COVER | MATTHEW | MATTHEW | | EUG | P | 3092726 |
RIVIERA ELECTRIC | EUG | R | 04/27/2006 | EUG FROM BLDG TO 10' SOUTH OF FORM OK TO COVER | MATTHEW | MATTHEW | | EUG | R | 3092718 |
RIVIERA ELECTRIC | ER | P | 04/19/2006 | WALLS LEVEL 1 AREA 1A AND 1E ON PLANS E3.11 AND HARD LIDS LEVEL 1 AREA 1B ON PLANS E4.12A AND E4.12B OK | MATTHEW | MATTHEW | | ER | P | 3092711 |
RIVIERA ELECTRIC | ER | P | 04/10/2006 | WALLS IN LEVEL 1 AREA 1 D, PLANS E 3.11 OK | MATTHEW | MATTHEW | | ER | P | 3092703 |
RIVIERA ELECTRIC | ER | P | 04/06/2006 | WALLS LEVEL 0- E3.02 AND HARDLIDS LEVEL 1 AREA 1B AND 1C- E.412A ON ELECTRICIANS PLANS OK TO COVER | MATTHEW | MATTHEW | | ER | P | 3092694 |
RIVIERA ELECTRIC | ER | P | 03/28/2006 | WALLS MARKED ON ELECTRICIAN PLANS E 3.13 LEVEL 1-1C OK | MATTHEW | MATTHEW | | ER | P | 3092687 |
RIVIERA ELECTRIC | ER | P | 03/24/2006 | HARD LIDS MARKED ON ELECTRICIANS PLANS E 4.02, E 4.01, AND E 4.12---- WALLS MARKED ON E 3.01 AND E 3.02 OK | MATTHEW | MATTHEW | | ER | P | 3092680 |
RIVIERA ELECTRIC | ER | P | 03/21/2006 | WALLS FIRST FLOOR MARKED ON ELECTRICIANS PLANS E3.12 | MATTHEW | MATTHEW | | ER | P | 3092673 |
RIVIERA ELECTRIC | ER | P | 02/07/2006 | WALLS MARKED ON ELEC WORKING SET E3.01 AND E3.02-----POC BRIAN 499-9515; ROYAL 499-2879; BROOK 499-9434 | MATTHEW | MATTHEW | | ER | P | 3092666 |
DYNALECTRIC COMPANY | EUG | P | 06/17/2005 | UFER | BRET | BRET | | EUG | P | 3091853 |
DYNALECTRIC COMPANY | E= | C | 06/17/2005 | THIS PORTION OF THE PERMIT IS COMPLETED NOW | BRET | BRET | | E= | C | 3091845 |
DYNALECTRIC COMPANY | EUG | C | 06/07/2005 | | BRET | BRET | | EUG | C | 3091838 |
DYNALECTRIC COMPANY | EUG | P | 05/23/2005 | EUG UNDER SLB | BRET | BRET | | EUG | P | 3091829 |
DYNALECTRIC COMPANY | EUG | L | 05/20/2005 | 5:00PM, LOCKED CALLED TONY SEVERAL TIMES LEFT MESSAGES 491-8913 | GARYL | GARYL | | EUG | L | 3091822 |
COBB MECHANICAL CONTRACTORS, INC. | H= | C | 11/05/2007 | RECEIVED BALANCE REPORT. | LYNNS | LYNNS | | H= | C | 3090245 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 10/16/2007 | PARTIAL FINAL FOR HVAC AND HWP, PHASE 3, PENDING BALANCE REPORTS. | LYNNS | LYNNS | | H= | P | 3090236 |
COBB MECHANICAL CONTRACTORS, INC. | HV | P | 09/11/2007 | Partial rough on 2nd floor, phase II. | LYNNS | LYNNS | | HV | P | 3090227 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 08/17/2007 | ALL OF LEVEL II PHASE III, RETAIL AND OFFICE COILS. STILL NEED RADIANT | JIMV | JIMV | | HWP | P | 3090221 |
COBB MECHANICAL CONTRACTORS, INC. | HRP | P | 08/15/2007 | 300# TEST ON REFRIGERATION LINES TO LEVEL 1, PHASE 3 OK. | LYNNS | LYNNS | | HRP | P | 3090212 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 08/14/2007 | ROUGH DUCT ON LEVEL 1, PHASE 3, OK TO INSULATE. ROUGH DUCT ON LEVEL 2, PHASE 3, LOW PRESSURE, OK TO INSULATE. | LYNNS | LYNNS | | HD | P | 3090205 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 08/09/2007 | LEVEL 4, HVAC AND HWP FINALS. NEED BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3090195 |
COBB MECHANICAL CONTRACTORS, INC. | HV | P | 08/02/2007 | ROUGH DUCT ON PHASE 3, ADMIN. AREA HIGH DUCT AND RETAIL SPACE DUCT OK TO INSULATE. | LYNNS | LYNNS | | HV | P | 3090187 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 08/02/2007 | 2-100# TESTS ON HEATING WATER SUPPLY AND RETURN ON PHASE 3, 2- 100# TESTS ON CHILL WATER SUPPLY AND RETURN, 2- 100# TESTS ON GLYCOL SUPPLY AND RETURN TO RTU OK. | LYNNS | LYNNS | | HWP | P | 3090179 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 07/27/2007 | ROUGH DUCT ON LEVEL 0, ROUGH DUCT ON SUPPLY, RETURN AND EXHAUST RISERS TO LEVEL 2, ROUGH DUCT ON LEVEL 2, SUPPLY, RETURN AND EXHAUST DUCTS OK TO FIRE WRAP. NEED TO SEE FIRE WRAP BEFORE FRAMING IS SHEET ROCKED. | LYNNS | LYNNS | | HD | P | 3090171 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 07/12/2007 | LEVEL 3 HVAC AND HWP FINALS. | LYNNS | LYNNS | | H= | P | 3090162 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 05/14/2007 | 100 LB TEST OK ON 6TH FLOOR, NORTH AND SOUTH. OK TO INSULATE. | NANCY | NANCY | | HWP | P | 3090155 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 02/05/2007 | LEVEL 6, ELEVATOR LOBBY AND CORE HALLWAY OK TO INSULATE | LYNNS | LYNNS | | HD | P | 3090147 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 01/04/2007 | LEVEL 2 HVAC AND HWP FINALS PENDING BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3090140 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 01/03/2007 | ROOF DUCT, SUPPLY AND RETURNS OK TO INSULATE. | LYNNS | LYNNS | | HD | P | 3090133 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 12/27/2006 | Temp CO: LEVEL 1, HVAC FINAL IN ALL AREAS EXCEPT FOR PHASE 2B AND NORTH ENTRANCE. | DAVEL | DAVEL | | H= | P | 3089810 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 12/07/2006 | RECEIVED BALANCE REPORT FROM PRECISION TEST AND BALANCE, INC., FOR LEVEL 0 AND 1. | LYNNS | LYNNS | | H= | P | 3090123 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 11/14/2006 | LEVEL 4 SOUTH HALF, FIRE/ SMOKE DAMPERS OK. | LYNNS | LYNNS | | HD | P | 3089800 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 11/09/2006 | 4TH LEVEL, SOUTH, 2- 100# TESTS ON CHILL AND HEATING LINES OK. | LYNNS | LYNNS | | HWP | P | 3090115 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 11/01/2006 | HVAC FINAL ON LEVEL 0 AND NORTH ENTRANCE OF LEVEL 1, HWP FINALS ON LEVELS 0 AND 1. OK FOR TCO WITH NO LIFE SAFTEY ISSUES. | LYNNS | LYNNS | | H= | P | 3090105 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 10/18/2006 | LEVEL 1, HVAC FINAL IN ALL AREAS EXCEPT FOR PHASE 2B AND NORTH ENTRANCE. | LYNNS | LYNNS | | H= | P | 3090097 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 10/17/2006 | PHASE 2B- ROUGH DUCT OK TO INSULATE. LEVEL 4- SOUTH, FIRE/ SMOKE DAMPERS OK EXCEPT AS NOTED ON PLANS. | LYNNS | LYNNS | | HD | P | 3090089 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 10/10/2006 | LEVEL 4, FRAMERS DID NOT HAVE FRAMING COMPLETED. | LYNNS | LYNNS | | HD | P | 3090081 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 10/10/2006 | LEVEL 4, AREAS 1 AND 2, 100# TEST ON HYDRONIC LINES OK. LEVEL 5, AERAS 1 AND 2, 85# TESTS ON HYDRONIC LINES OK. | LYNNS | LYNNS | | HWP | P | 3090073 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 10/03/2006 | LEVELS 5 THROUGH 8 RISER SHAFTS ON SOUTH OK TO CLOSE, LEVEL4, AREA 2, FIRE/ SMOKE AND FIRE/ DAMPERS OK EXCEPT AS NOTED ON PLANS. | LYNNS | LYNNS | | HD | P | 3090065 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 09/13/2006 | LEVEL 3, AREA 1, 100# TEST ON HEATING SUPPLY AND RETURN OK. | LYNNS | LYNNS | | HWP | P | 3090057 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 09/06/2006 | LEVEL 3, AREA 1: FIRE/SMOKE DAMPERS AS NOTED ON PLANS, LEVEL 4, AREA 1: ROUGH DUCT ON SOUTH HALF OK TO INSULATE. | LYNNS | LYNNS | | HD | P | 3090053 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 08/29/2006 | NORTH HALF OF LEVEL 4AREA 2: ROUGH DUCT OK TO INSULATE, NORTH SHAFT ON LEVELS 5 THROUGH 7 OK TO INSULATE. LEVEL3, AREA1: FIRE/ SMOKE DAMPER FRAMING EXCEPT AS NOTED ON PLANS OK. | LYNNS | LYNNS | | HD | P | 3090046 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 08/03/2006 | 100# TEST ON HEATING SUPPLY AND RETURN LINES, LEVEL 3, AREA 2. | LYNNS | LYNNS | | HWP | P | 3090036 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 07/28/2006 | LEVEL 3, AREA 2, F/S DAMPER FRAMING OK EXCEPT AS NOTED ON PLAN. | LYNNS | LYNNS | | HD | P | 3090030 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 07/19/2006 | LEVEL 3, AREA 1: ROUGH DUCT OK TO INSULATE. LEVEL 3, AREA 2: F/S DAMPER FRAMING OK EXCEPT AS NOTED ON PLANS. | LYNNS | LYNNS | | HD | P | 3090020 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 06/29/2006 | LEVEL 0, NORTH AND SOUTH MECH ROOM PIPING TESTS OK. | LYNNS | LYNNS | | HWP | P | 3090012 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 06/22/2006 | LEVEL 2 HEAT PIPING COMPLETE | JACK | JACK | | HWP | P | 3090004 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 06/20/2006 | FIRE DAMPERS 2ND LEVEL SOUTH END OK | JACK | JACK | | HD | P | 3089996 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 06/15/2006 | SHAFTS THROUGH 4TH FLOOR OK, LEVEL 2 AREA 1 FIRE DAMPERS OK, LEVEL 3 AREA 1 DUCT OK | JACK | JACK | | HD | P | 3089988 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 06/02/2006 | LEVEL 0 COMPLETE | JACK | JACK | | HD | P | 3089980 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 05/22/2006 | FIRE DAMPERS ON LEVEL 2 OK | JACK | JACK | | HD | P | 3089970 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 05/15/2006 | LEVEL 2 NORTHWEST POD FIREDAMPERS OK | JACK | JACK | | HD | P | 3089959 |
COBB MECHANICAL CONTRACTORS, INC. | HRP | P | 05/09/2006 | AHU 6 AND 7 REFRIGERATION LINES OK | JACK | JACK | | HRP | P | 3089951 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 05/08/2006 | TRENCH PIPING NORTH END OF BUILDING OK | JACK | JACK | | HWP | P | 3089942 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 05/02/2006 | AREA 2 LEVEL 2 OK | JACK | JACK | | HD | P | 3089933 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 04/18/2006 | 1ST LEVEL COMPLETE | JACK | JACK | | HWP | P | 3089925 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 04/17/2006 | F/S DAMPERS HIGH LIGHTED AND INITIALED ON PRINT | JACK | JACK | | HD | P | 3089919 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 03/31/2006 | LEVEL O AREA 1AND 2 FIRE SMOKE DAMPERS | JOEL | JOEL | | HD | P | 3089912 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 03/29/2006 | NORTH END 100# TEST O.K, HVAC # 1 SHAFT HRP 3OO# TEST O.K | JOEL | JOEL | | HWP | P | 3089905 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 03/28/2006 | F/S DAMPERS AREA 2 LEVEL 1 POD A&B OK | JIMV | JIMV | | HD | P | 3089898 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 03/17/2006 | LEVEL 1, AREA1ROUGH DUCT MAINS AND LATTERALS INCLUDING RISERS OK. NEED TO SEE ALL F/S DAMPERS. | LYNNS | LYNNS | | HD | P | 3089890 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | R | 02/27/2006 | NEED TO TEST ALL PIPING | JOEL | JOEL | | HWP | R | 3089881 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 02/21/2006 | MARK'S # 492-7451; JOE'S # 492-5274; 1ST FLR N. AREA 2 ROUGH DUCT OK, RECHECK SOME DUCT SUPPORT THIS AREA. | JIMV | JIMV | | HD | P | 3089873 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 02/10/2006 | BASEMENT LEVEL AREAS 1 & 2 TRUNKS & LATERALS OK, N. SHAFT BASEMENT THRU 3RD FLR OK. | JIMV | JIMV | | HD | P | 3089865 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 02/09/2006 | FIN TUB IN CEILING OF EXHAUST AIR CORRIDOR, OK | JIMV | JIMV | | HWP | P | 3089857 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 01/10/2006 | | JIMV | JIMV | | HD | P | 3089849 |
COBB MECHANICAL CONTRACTORS, INC. | HI | P | 12/09/2005 | CK TEMP HEATERS & FLEXIBLE GAS LINES. | JIMV | JIMV | | HI | P | 3089841 |
COBB MECHANICAL CONTRACTORS, INC. | HI | P | 11/29/2005 | TEMPORARY 5# GASLINE. OK TO UNLOCK METER. MARK 492-7451. | JIMV | JIMV | | HI | P | 3089833 |
COBB MECHANICAL CONTRACTORS, INC. | P= | C | 11/16/2007 | SEE G46039 FOR PHARMACY SINK | JEFF | JEFF | | P= | C | 3091622 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | C | 11/16/2007 | | JEFF | JEFF | | PRD | C | 3091615 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 11/13/2007 | ABULATORY ENTRANCE OK, STILL NEED PRD COMPLETED, PHARMICY SINK LEVEL 3, AND UTILITY SINK LEVEL 5 REMOVED, REST OK | JEFF | JEFF | | P= | P | 3091605 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 10/22/2007 | OK FOR TCO, ITEMS THAT REMAIN: 1. HEAT AT AMBULATORY ENTRANCE. 2. REMOVE TEMPORARY UTILITY SINK LEVEL 5. 3. PHARMACY SINK, GC LOOKING AT DELETING THIS PORTION FROM APPROVED PLANS TO GET CO AND SECURING A TENANT FINISH PERMIT FOR PHARMACY. | KYE | KYE | | P= | P | 3091598 |
COBB MECHANICAL CONTRACTORS, INC. | P16 | P | 10/15/2007 | 6) REMOVE AND PROPERLY CAP TEMPERARY WATER AT LEVEL FIVE X TWO 7) NEED TO FINAL PHARMACY SINK LEVEL 3 ROOM 3383......REST OK PENDING ANY CHANGES PERFORMED PRIOR TO NEXT INSPECTION? CALL MARK AT COBB FOR CONTACT 492-7451 | JEFF | JEFF | | P16 | P | 3091590 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 10/15/2007 | ISSUES ARE AS FOLLOWS; 1) SEE PRD NOTES DATED 10/15/07 2) FIRE SPRINKLER DRAINS AT LEVEL 0 TO BE THROUGH INDIRECT WASTE AT "FUNNEL" DRAINS AND TO HAVE FLOW CONTROL WITH REVISED AND APPROVED PLANS(ANY QUESTIONS SEE KYE) 3) REMOVE SECOND UTILITY SINK AT SOUTH MECHANICAL ROOM(HOSPITAL KEEPS TRYING TO INSTALL?) 4) NEED HEAT AT AMBLITORY ENTRANCE LEVEL ONE 5) REMOVE TEMPERARY UTILITY SINK LEVEL FIVE .....SEE P16 NOTES 10/15/07 | JEFF | JEFF | | P= | P | 3091583 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 10/15/2007 | NEED TEMPERARY STORM DRAIN AT LEVEL 0 PHASE 3 AREA 3 REMOVED AND CAPPED FOR FINAL, REST OK | JEFF | JEFF | | PRD | P | 3091576 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | C | 10/15/2007 | PHASE 3 AREA 3 LEVEL 1 COMPLETE, PTO COMPLETE | JEFF | JEFF | | PTO | C | 3091569 |
COBB MECHANICAL CONTRACTORS, INC. | P11 | C | 10/08/2007 | DISCUSSED REVISING PLANS WITH WES JONES AT CATA RUMA . PLANS NEED REVISED TO SHOW AN INDIRECT WASTE RECPTOR FOR THE DRAIN DOWN PORTION OF THE FIRE SPRINKLER SYSTEM. DRAINS ARE NOW DIRECT CONNECTED TO EJECTOR PITS. | KYE | KYE | | P11 | C | 3091562 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 09/11/2007 | LEVEL 2 AREA 3 PHASE 3 MID STORY SUPPORTS AND FREEZE PROTECTION PAST AIR LOCK COMPLETE | JEFF | JEFF | | PRD | P | 3091553 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/06/2007 | LEVEL 2 PHASE 3 AREA 3 MENS/WOMENS REST ROOM DOMESTIC AND DWV COMPLETE, PROVIDE HANGER AT WATER PIPE AT WOMENS AND FIRE CAULK VENT AT WALL PENETRATION, SEE ALL PREVIOUS NOTES | JEFF | JEFF | | PTO | P | 3091545 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/16/2007 | LEVEL 2 AREA 3 PHASE 3 DOMESTIC WATER AT WOMENS RESTROOM TO HALL OK | JEFF | JEFF | | PTO | P | 3091537 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/10/2007 | HAD MEETING WITH PLC AND ARCHITECT AND ENGINEER OVER FIRE SPRINKLER DRAINS AND OVERFLOW DRAIN AT AMBULANCE ENTRANCE..... | JEFF | JEFF | | PTO | P | 3091528 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 08/09/2007 | LEVEL 3 AREA 1 ROOM 3383, CHANGED TO PARTIAL 8/9/07, SEE PTO NOTES SAME DAY, NEED P= FOR SINK | JEFF | JEFF | | P= | P | 3091521 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/09/2007 | LEVEL 3 AREA 1 ADDED SINK AT PHARMACY 3383 OK | JEFF | JEFF | | PTO | P | 3091491 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/03/2007 | PHASE 3 AREA 3 LEVEL 2 FLOOR DRAIN VENTS OK, LEVEL 2 DOMESTIC WATER AT MENS RESTROOM OK | JEFF | JEFF | | PTO | P | 3091483 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 08/02/2007 | PHASE 3 AREA 3 LEVEL 0 TO 1 STORM AND ELEVEVATOR SHAFT DRAINS, NEED TO EXPOSE DRAINS X 2 ON LEVEL 1 FOR FINAL, SEE ALL PREVIOUS NOTES, ALSO NEED TO REMOVE TEMP STORM LEVEL 0 PRIOR TO FINAL | JEFF | JEFF | | PRD | P | 3091475 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/02/2007 | PHASE 3 AREA 3 LEVEL 2 DWV TO HALL FROM BOTH SIDES, PROVIDE PROPER GRADE AT WASTE ARMS WHEN WALLS BUILT, SEE PREVIOUS NOTES | JEFF | JEFF | | PTO | P | 3091467 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 08/01/2007 | NOT READY | JEFF | JEFF | | PTO | R | 3091459 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 08/01/2007 | NOT READY | JEFF | JEFF | | PRD | R | 3091453 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/31/2007 | PHASE 3 AREA 3 LEVEL 1 DWV, HORIZONTAL DRY VENTS TO BE RECONFIGURED AT FLOOR DRAINS X 2 | JEFF | JEFF | | PTO | P | 3091446 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 07/31/2007 | PHASE 3 AREA 3 LEVEL 1 STORM AND O/D | JEFF | JEFF | | PRD | P | 3091438 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 07/30/2007 | PHASE 3 LINK LEVEL 2 AND 3 STORM AND OVERFLOW TEST OK, NEED MID STORY SUPPORT AT 4" LEADERS X 2 BY FINAL, SEE ALL PREVIOUS PRD NOTES | JEFF | JEFF | | PRD | P | 3091429 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 07/17/2007 | LEVEL 2 COMPLETE LESS PHASE 3 "LINK", SCRUB SINK AND STERILIZER ROOM 2164 ROUGH ONLY, LEVEL 1, 2, 3, 4 COMPLETE LESS PHASE 3 "LINK", ON GOING ISSUES AT LEVEL 0 WITH SANITARY SEWER EJECTION PITS WITH FIRE SPRINKLER DRAINS DIRECTLY CONNECTED, HOSPITAL APPEARS TO BE REINSTALLING UTILITY SINK SOUTH MECHANICAL ROOM NORTH SIDE?, SEE PRD AND PTO NOTES FOR AMBLITORY ENTRANCE PHASE 3, PLUMBING IN UNCONDITIONED SPACE?, ROOF LEADER TERMINATION ON WALK WAY? | JEFF | JEFF | | P= | P | 3091422 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 07/16/2007 | LEVEL 3 COMPLETE......LEVEL 1, 3 AND 4 COMPLETE...... | JEFF | JEFF | | P= | P | 3091414 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 07/13/2007 | LEVEL 4 AREA 1 AND AREA 2 COMPLETE....... | JEFF | JEFF | | P= | P | 3091408 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 07/11/2007 | MET WITH GENERAL CONTRACTOR SUPERINTENDANT AND ENGINEERS REPRESENTITIVE AND WENT OVER INSPECTION ISSUES THROUGHOUT HOSPITAL, TO HAVE FEILD OBSERVATION REPORT SENT TO RBD AND ISSUES RESOLVED PER REPRESENTITIVE AND CONTRACTOR | JEFF | JEFF | | P= | P | 3091400 |
COBB MECHANICAL CONTRACTORS, INC. | P= | R | 07/09/2007 | NOT READY, INDIRECT WASTES STILL NOT ADDRESSED | JEFF | JEFF | | P= | R | 3091394 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 07/09/2007 | WASTE FROM LEVEL 0 COLUMN X8/R2 TO 8" TEST OK, ISSUES WITH DESIGN | JEFF | JEFF | | PTO | R | 3091387 |
COBB MECHANICAL CONTRACTORS, INC. | P= | R | 07/06/2007 | LEVEL 4 AREA 1 AND 2, REQUEST SPECIFICATIONS ON ICE MACHINES FOR VERIFICATION ON DRAIN ASSEMBLIES AND INDIRECT WASTES, REST OK, LEVEL 4 ONLY, SEE ALL PREVIOUS NOTES | JEFF | JEFF | | P= | R | 3091381 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/29/2007 | CLINICAL SINKS AND BED PAN WAHSERS UPC LISTED PER KOHLER, SEE PREVIOUS NOTES | JEFF | JEFF | | P= | P | 3091375 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 06/29/2007 | NEED APPROVED PLANS FOR LEVEL 0 ABULANCE ENTRANCE, TEST OK AT O/D, DESIGN PENDING PLANS | JEFF | JEFF | | PRD | P | 3091369 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/29/2007 | REVISED PLANS OK FOR 3407, SEE P= 6/13/07 | JEFF | JEFF | | PTO | P | 3091364 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/27/2007 | CHANGED TOILET ROUGH TO "SITZ BATH" AT 3204 OK, VERIFY CROSS CONNECTION PROTECTION WHEN CALLED FOR FINAL | JEFF | JEFF | | PTO | P | 3091357 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/26/2007 | LEVEL 4 AREA 1 COMPLETE INDIRECT WASTE AT ROOM 4126....CONTRACTOR STILL RECIEVING INFORMATION ABOUT CLINICAL SINK ISSUE OF ATMOSPHERIC VACUUM BREAKER AHEAD OF CHECK VALVE????......REST OK, SEE ALL PREVIOUS NOTES | JEFF | JEFF | | P= | P | 3091350 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/21/2007 | LEVEL 4 AREA 2, QUESTION ON INCOMPLETE INDIRECT WASTE AT ROOM 4263 AND CONTRACTOR GETTING INFORMATION ON OPERATION OF CLINICAL SINKS WITH INDIVIDUALY LISTED COMPONENETS AT ROOM 4262, REST OK IN AREA 2 | JEFF | JEFF | | P= | P | 3091340 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/13/2007 | LEVEL 3 AREA 1 AND 2, NO HOT WATER?, COMPLETE DISH WASHER DRAIN AT 3407, NEED REVISED PLANS FOR 3407(SEE PREVIOUS NOTES), TRAP LAV AT 3392, EXCESSIVE WATER HAMMER AT 3385, CLINICAL SINK C/O AND STRAINER AT 3374, NEED C/O AT URINAL 3307, COMPLETE INDIRECT WASTES AT 3301/3106/3323/3212, COMPLETE SINK AT 3216, SEE PREVIOUS NOTES | JEFF | JEFF | | P= | P | 3091322 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/12/2007 | LEVEL 3 AREA 2, NEED PTO FOR SITZ BATH ROUGH, NEED "BABY SINK" AT NICU, C/O'S AND AREATORS, NEED TO REINSPECT MOST OF LEVEL 3, SEE ALL PREVIOUS NOTES, NOTES FROM PREVIOUS INSPECTION NOT SAVED, NEED CROSS CONNECTION PROTECTION AT OWNER FURNISHED STERILIZER AT LEVEL 2 C SECTION ROOM, CONTRACTOR STILL GAINING INFORMATION ON CLINICAL SINKS | JEFF | JEFF | | P= | P | 3091314 |
COBB MECHANICAL CONTRACTORS, INC. | P= | R | 05/25/2007 | NOT READY, SEE PREVIOUS INSPECTION NOTES LEVEL 2 AREA 1 AND 2 | JEFF | JEFF | | P= | R | 3091306 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 05/17/2007 | NO APPROVED PLANS FOR LEVEL 0 AREA 1 AMBULANCE ENTRANCE, TEST ON STORM DRAIN OK WHEN VERIFIED WITH APPROVED PLANS, NO TEST AT OVERFLOW AT THIS TIME | JEFF | JEFF | | PRD | R | 3091298 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 05/16/2007 | LEVEL 2 MAIN ENTRANCE CANOPY....SECOND STORM DRAIN PAST AIR LOCK TO HAVE FREEZE PROTECTION FOR FINAL | JEFF | JEFF | | PRD | P | 3091290 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 05/16/2007 | LEVEL 2 AREA 1 AND 2 MISSING SEVERAL C/O'S AT SINKS AND URINALS, MISSING AERATORS AT SINK FAUCETS, ATMOSPHERIC VACUUM BREAKERS NOT WORKING PER LISTING AT CLINICAL SINKS X 4 | JEFF | JEFF | | P= | P | 3091282 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 05/15/2007 | LEVEL 0...OWNER ADDED UTILITY SINK NOT ON PLANS WITH UNPROTECTED HOSE THREADS AT SOUTH MECH ROOM NORTH WALL, NO WATER TURNED INTO ANY FIXTURES, HAVE FIRE PROTECTION DRAINS DIRECTLY TIED TO SANITARY EJECTION PITS, STILL HAVE ISSUES WITH OVERSIZED SEWER EJECTION PIT....SEE INSPECTION LOG 5/6/05???? | JEFF | JEFF | | P= | P | 3091274 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/27/2007 | SEE G19358 | JEFF | JEFF | | PTO | P | 3091266 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 04/26/2007 | LEVEL 6 AND 7 AREA 1 STORM DRAINS OK, MISSING OVERFLOW NIPPLES X 2 AND BASKETS X 2, WILL REQUIRE FOR A FINAL | JEFF | JEFF | | PRD | P | 3091259 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/26/2007 | LEVEL 6 AND 7 AREA 1 SHELL VENTS OK | JEFF | JEFF | | PTO | P | 3091251 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 04/25/2007 | NO APPROVED PLANS, NO INSPECTION, SEE PREVIOUS NOTES | JEFF | JEFF | | PTO | R | 3091243 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/19/2007 | LEVEL 6 AND 7 AREA 2 SHELL SANITARY DRAIN VENTS OK, VENTS ONLY | JEFF | JEFF | | PTO | P | 3091234 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 04/19/2007 | LEVEL 6 AND 7 AREA 2 STORM AND O/D AS PER APPROVED PLANS | JEFF | JEFF | | PRD | P | 3091227 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 04/18/2007 | WAIVE TRIP FEE, NOT READY, WORK PERFORMED DOES NOT MATCH APPROVED PLANS ON LEVEL 6 AREA 1, 6" OD REDUCES TO 4", TO BE 6" TO ROOF PER PLANS, REVISE PLANS OR CHANGE, ADVISED MARK WITH COBB THAT NOT APPROVED TO COVER ON 6TH LEVEL!!!! | JEFF | JEFF | | PRD | R | 3091218 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/18/2007 | SHELL VENTS OK | JEFF | JEFF | | PTO | P | 3091210 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/16/2007 | SEE G19358 INSPECTION 4/16/07 | JEFF | JEFF | | PTO | P | 3091202 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | T | 04/12/2007 | PAID (REC#746283): TRIP FEE, SEE PREVIOUS NOTES, NEED APPROVED PLANS FOR ANY FUTHER INSPECTIONS ON THIS PERMIT, CONTRACTOR CONTINUING AT OWN RISK, SEE ALL PREVIOUS PLUMBING ENTRIES........... | JEFF | JEFF | | PTO | T | 3091194 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 12/05/2006 | SHOWER VENT AT 2161 OK | JEFF | JEFF | | PTO | P | 3091185 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 12/01/2006 | CONTRACTOR PROCEEDING AT OWN RISK, NEED TO REVISE PLANS FOR LEVEL 3 AREA 1, TEST OK, DESIGN OK PENDING APPROVED PLANS | JEFF | JEFF | | PTO | P | 3091177 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 11/28/2006 | NO APPROVED PLANS FOR CHANGED FAMILY WAITING AREA, LOW TEST, VERTICAL WET VENT AT WASHER BOX TO BE 1 PIPE SIZE LARGER, TEST THROUGH SHOWER VALVE | JEFF | JEFF | | PTO | R | 3091169 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 11/17/2006 | LEVEL 4 AREA 1 WATER PIPE COMPLETE | JEFF | JEFF | | PTO | P | 3091161 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 11/16/2006 | CONTRACTOR TO RECALL | JEFF | JEFF | | PTO | R | 3091154 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 11/09/2006 | LEVEL 4 AREA 1 WATER TRNK LINES AND SE POD OK | JEFF | JEFF | | PTO | P | 3091146 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 11/01/2006 | ROOM 1462 OK, LEVEL 1 COMPLETE | JEFF | JEFF | | P= | P | 3091139 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/19/2006 | ER----ROOM 1104--DWV AND DOMESTIC WATER LINES BRANCHES--ONE SINK NEXT TO ROOM 1104 TOO | LYNNIE | LYNNIE | | PTO | P | 3091131 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/17/2006 | LEVEL 2 B--ER ENTRY CORRIDOR--DOMESTIC WATER LINES IN ER NEAR RM 1104 | LYNNIE | LYNNIE | | PTO | P | 3091124 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 10/16/2006 | LEVEL 1=====9 - 1/2'' SVB VACUUM BREAKERS====RM 1428 HAS NO FIXTURES====RM 1462 WATER CLOSET IS NOW 22'' OFF WALL-NOT TO ADA SPECS----REST OK===== | LYNNIE | LYNNIE | | P= | P | 3091117 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/13/2006 | PIPING IS COMPLETE FOR AREAS 1 AND 2---PLANS REVISED TO COME | LYNNIE | LYNNIE | | PTO | P | 3091108 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 10/12/2006 | COMPLETE EXCEPT FOR APPROVED PLANS | LYNNIE | LYNNIE | | PRD | P | 3091100 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 10/11/2006 | CONTRACTOR CONTINUING AT OWN RISK, LEVEL 7 AREA 2 TO ROOF TEST OK, NEED AN APPROVED PLAN TO VERIFY DESIGN | JEFF | JEFF | | PRD | R | 3091093 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 10/10/2006 | CONTRACTOR CONTINUING AT OWN RISK, LEVEL 6 AREA 1 TO LEVEL 7 TESTS OK, 4" SE POD THROUGH TO ROOF TEST OK, NEED TO VERIFY DESIGN WITH APPROVED PLANS | JEFF | JEFF | | PRD | P | 3091086 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/10/2006 | CONTRACTOR CONTINUING AT OWN RISK, LEVEL 6 AREA 1 TO LEVEL 7 TESTS ON 6" VENTS X 2 OK, NEED TO VERIFY DESIGN PER APPROVED PLANS | JEFF | JEFF | | PTO | P | 3091079 |
COBB MECHANICAL CONTRACTORS, INC. | P16 | C | 10/10/2006 | WALKED JOB WITH JEFF TO STEP IN WHEN HE'S OFF | LYNNIE | LYNNIE | | P16 | C | 3091071 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 10/06/2006 | CONTRACTOR CONTINUING AT OWN RISK, LEVEL 7 AREA 1 TEST OK, NEED APPROVED PLANS TO VERIFY DESIGN | JEFF | JEFF | | PRD | R | 3091064 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 10/06/2006 | CONTRACTOR CONTINUING AT OWN RISK, LEVEL 7 AREA 1 TEST OK, NEED TO VERIFY DESIGN WITH APPROVED PLANS | JEFF | JEFF | | PTO | R | 3091058 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 10/05/2006 | LEVEL 4 AREA 2 THROUGH TO LEVEL 6 TEST OK PENDING VERIFICATION OF APPROVED PLANS | JEFF | JEFF | | PRD | P | 3091050 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/04/2006 | LEVEL 4 AREA 2 WATER PIPE OK | JEFF | JEFF | | PTO | P | 3091042 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 10/03/2006 | NO MORE INSPECTIONS ABOVE FOURTH FLOOR UNTIL APPROVED PLANS VERIFIED AND WORK MATCHES APPROVED PLANS, LEVEL 7 AREA 1 LESS 6" X 2 SOUTH POD TEST OK, SEE PREVIOUS NOTES | JEFF | JEFF | | PRD | R | 3091034 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 10/03/2006 | LEVEL 4 AREA 2 WATER PIPE, NEED TO REINSPECT HANGERS/SUPPORT FOR MAIN TRUNK LINE | JEFF | JEFF | | PTO | P | 3091027 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | R | 09/29/2006 | NEED APPROVED PLANS, LEVEL 6 TO LEVEL 7 STORM DRAIN TESTS OK LESS SOUTH POD | JEFF | JEFF | | PRD | R | 3091020 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 09/29/2006 | NEED VERIFICATION WORK PERFORMED MEETS APPROVED PLANS AS NOTED BEFORE, LEVEL 6 AREA 1 TO LEVEL 7 VENT TESTS OK | JEFF | JEFF | | PTO | R | 3091012 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/28/2006 | LEVEL 5 AREA 1 THROUGH 6 VENTS OK PENDING APPROVED PLANS | JEFF | JEFF | | PTO | P | 3091004 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 09/28/2006 | LEVEL 4 AREA 1 THROUGH TO LEVEL 6 OK PENDING APPROVED PLANS | JEFF | JEFF | | PRD | P | 3090996 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/27/2006 | LEVEL 4 AREA 1 TO LEVEL 5 DWV COMPLETE | JEFF | JEFF | | PTO | P | 3090988 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 09/25/2006 | LEVEL 1 AREA 2 NORTH CANOPY | JEFF | JEFF | | PRD | P | 3090982 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 09/21/2006 | FIELD CANCELLED | JEFF | JEFF | | PTO | R | 3090973 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 09/20/2006 | LEVEL 3 AREA 0 PHASE 2B 4" SD AT AMBULANCE ENTRANCE | JEFF | JEFF | | PRD | P | 3090966 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 09/20/2006 | LEVEL 3 AREA 0 PHASE 2B AMBULANCE ENTRANCE | JEFF | JEFF | | PB | P | 3090957 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 09/19/2006 | NEW AMBULANCE ENTRANCE BASE LOST TEST | JEFF | JEFF | | PB | P | 3090949 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/15/2006 | LEVEL 4 AREA 1 SOUTH POD DWV TO LEVEL 5 OK | JEFF | JEFF | | PTO | P | 3090942 |
PCL CONSTRUCTION SERVICES, INC | PRD | P | 09/14/2006 | LEVEL 4 THROUGH 6 AREA 1 6" RISERS AT SW PODS | JEFF | JEFF | | PRD | P | 3092517 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/14/2006 | LEVEL 4 AREA 1 TO LEVEL 5 SW POD DWV COMPLETE | JEFF | JEFF | | PTO | P | 3090934 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/13/2006 | LEVEL 4 AREA 1 SW POD DWV TO LEVEL 5 | JEFF | JEFF | | PTO | P | 3090926 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/12/2006 | LEVEL 4 AREA 2 DWV COMPLETE | JEFF | JEFF | | PTO | P | 3090918 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/08/2006 | LEVEL 3 AREA 1 WATER PIPE OK | JEFF | JEFF | | PTO | P | 3090909 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/07/2006 | LEVEL 3 AREA 1 WATER PIPE OK LESS RESTROOMS 3375-3376 | JEFF | JEFF | | PTO | P | 3090901 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/06/2006 | LEVEL 3 AREA 1 WATER TRUNK LINES OK | JEFF | JEFF | | PTO | P | 3090895 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 09/01/2006 | LEVEL 3-4 AREA 2 WATER RISERS OK | JEFF | JEFF | | PTO | P | 3090886 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/08/2006 | LEVEL 4 AREA 2 HVAC SHAFT 03 TO PICU 12 DWV TO LEVEL 5 OK | JEFF | JEFF | | PTO | P | 3090878 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/07/2006 | LEVEL 4 AREA 2 PICU 12- STEP DOWN 4324 DWV TO LEVEL 5 OK | JEFF | JEFF | | PTO | P | 3090870 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/04/2006 | LEVEL 3 AREA 2 WATER PIPE COMPLETE | JEFF | JEFF | | PTO | P | 3090863 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/03/2006 | LEVEL 3 AREA 1 DWV TO LEVEL 4 COMPLETE | JEFF | JEFF | | PTO | P | 3090856 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 08/02/2006 | FIELD CANCELLED | JEFF | JEFF | | PTO | R | 3090847 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 08/01/2006 | LEVEL 3 AREA 1 NICU PAT TO IT 3004 DWV LEVEL 4 | JEFF | JEFF | | PTO | P | 3090840 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 07/31/2006 | LEVEL 3 AREA 1 STORM/OD TO LEVEL 4 OK | JEFF | JEFF | | PRD | P | 3090834 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/28/2006 | LEVEL 3 AREA 1 CLEAN UP 3322 TO LEVEL 4 DWV, LEVEL 3 AREA 2 N/S 3217-M/B PAT 3173 WATER PIPE | JEFF | JEFF | | PTO | P | 3090825 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/27/2006 | LEVEL 3 AREA 1 NICU 3348-FEMALE LOCKER 3304 TO LEVEL 4 DWV OK | JEFF | JEFF | | PTO | P | 3090818 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 07/26/2006 | LOST TESTS DWV LEVEL 3 AREA 1 | JEFF | JEFF | | PTO | R | 3090811 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 07/25/2006 | LEVEL 3 AREA 1 MATCHLINE NORTH SHAFT TO LEVEL 4 ROOF | JEFF | JEFF | | PRD | P | 3090803 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/25/2006 | LEVEL 3 AREA 1&2 AT MATCHLINE NORTH STAIR CASE TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090795 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/24/2006 | LEVEL 3 AREA 2 WATER PIPE TUNK LINES AND ROOMS FROM PUBLIC RESTROOM 3205 TO M/B PAT 3175 OK | JEFF | JEFF | | PTO | P | 3090787 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/21/2006 | LEVEL 3 AREA 2 M/B PAT 3121-3128 DWV TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090779 |
PCL CONSTRUCTION SERVICES, INC | PRD | P | 07/20/2006 | LEVEL 3 AREA 2 M/B PAT 3138 4 STORM TO LEVEL 4 OK | JEFF | JEFF | | PRD | P | 3092510 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/20/2006 | LEVEL 3 AREA 2 M/B PAT 3131-3146 DWV TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090772 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 07/19/2006 | LEVEL 3 AREA 2 STORM/OD AT MEDS TO LEVEL 4 OK | JEFF | JEFF | | PRD | P | 3090763 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/19/2006 | LEVEL 3 AREA 2 DWV AT MEDS TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090756 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/18/2006 | LEVEL 3 AREA 2 M/B PAT 3156-3168 TO LEVEL 4 DWV OK | JEFF | JEFF | | PTO | P | 3090747 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/14/2006 | LEVEL 3 AREA 2 POD A TO LEVEL 4 DWV OK | JEFF | JEFF | | PTO | P | 3090738 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/13/2006 | LEVEL 3 AREA 2 6" FROM NORTH SHAFT TO PRIMARY N/S TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090731 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/12/2006 | LEVEL 3 AREA 2 MB PATIENT ROOM TO LEVEL 4 DWV OK | JEFF | JEFF | | PTO | P | 3090724 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/11/2006 | LEVEL 3 AREA 2 4" SUMP VENT TO LEVEL 4 OK | JEFF | JEFF | | PTO | P | 3090715 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 07/05/2006 | LEVEL 3 AREA 1 NW BATHROOM WASTE 2 UNITS | DARYL | DARYL | | PTO | P | 3090707 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/30/2006 | | MICK | MICK | | PTO | P | 3090699 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/29/2006 | FLOOR 3 AREA 1 ROOF DRAINS AND OVERFLOWS SWEST | MICK | MICK | | PTO | P | 3090692 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/28/2006 | FINISH ON 12" MAIN. LEVEL 3 AREA I VENTS FOR NEWBORN ICU. | MICK | MICK | | PTO | P | 3090684 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/27/2006 | 3 LEVEL AREA 1 DWV VENT | MICK | MICK | | PTO | P | 3090676 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | R | 06/26/2006 | FIELD CANCEL | MICK | MICK | | PTO | R | 3090668 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/22/2006 | LEVEL 2 AREA 1 WATER PIPE LESS LDR 1 AND 2, DIVERTER AT LDR 9 AND C SECTION CRUB ROOM, REST OK | JEFF | JEFF | | PTO | P | 3090659 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/21/2006 | LEVEL 1 AND 2 AREA 1 4" SUMP VENT TO LEVEL 3 OK | JEFF | JEFF | | PTO | P | 3090651 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/20/2006 | LEVEL 0 AREA 1 SOUTH MECHANICAL ROOM/SUMP VENTS OK | JEFF | JEFF | | PTO | P | 3090644 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/19/2006 | LEVEL 2 AREA 1 AND 2 DWV COMPLETE TO LEVEL 3 DWV COMPLETE LESS 4" MECHANICAL ROOM VENT | JEFF | JEFF | | PTO | P | 3090635 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 06/16/2006 | LEVEL 3 AREA 1 AND 2 STORM DRAIN OVER ENTRY TO ROOF OK | JEFF | JEFF | | PRD | P | 3090627 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/15/2006 | LEVEL 2 AREA 1 6" OVER WOMENS ENTRY TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090618 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/14/2006 | FIELD CANCELLED | JEFF | JEFF | | PTO | P | 3090610 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/13/2006 | LEVEL 2 AREA 1 LDR 2138-TRIAGE 2317 TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090596 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/12/2006 | LDR 2131-2137 LEVEL 2 AREA 1 TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090589 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/07/2006 | LEVEL 2 AREA 1 LDR 2406 TO ANTE-PARTUM 2213 TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090580 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/06/2006 | LEVEL 2 AREA 1 OB RECOVERY 2214/2216 TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090571 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/02/2006 | LEVEL 2 AREA 2 PEDS PREP/RECOVERY TO LEVEL 3 DWV OK | JEFF | JEFF | | PTO | P | 3090563 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/01/2006 | LEVEL 2 AREA 1 OVER WOMENS LOCKER TO LEVEL 3 OK | JEFF | JEFF | | PTO | P | 3090555 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/31/2006 | LEVEL 2 MATCHLINE 1/2 TO LEVEL 3 PEDS SCRUB/OR | JEFF | JEFF | | PTO | P | 3090548 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/30/2006 | LEVEL 2 AREA 2 STAFF LOUNGE WASTE AND VENT TO LEVEL 3 OK | JEFF | JEFF | | PTO | P | 3090538 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/26/2006 | LEVEL 2 AREA 2 PODS AND STACK | MICK | MICK | | PTO | P | 3090530 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/24/2006 | AREA 2 LEVEL 2 POD A | MICK | MICK | | PTO | P | 3090523 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/23/2006 | DWV AND DOMESTIC WATER LEVEL 2 AREA 2 | MICK | MICK | | PTO | P | 3090514 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/22/2006 | LEVEL 2 AREA 2 TO LEVEL 3 M/B ROOM 3173 TO 3162 WASTE OK | JEFF | JEFF | | PTO | P | 3090507 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/19/2006 | LEVEL 2 AREA 2 FETAL MED POD TO LEVEL 3 OK | JEFF | JEFF | | PTO | P | 3090499 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/18/2006 | LEVEL 1 AREA 1 TO LEVEL 2 PED OPERATING ROOM TO WOMENS LOCKER GANG BATH | JEFF | JEFF | | PTO | P | 3090491 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/17/2006 | LEVEL 2 AREA 2 WASTE AND VENT OVER FETAL MED LESS LINE FC TO LEVEL 3 | JEFF | JEFF | | PTO | P | 3090485 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 05/16/2006 | LEVEL 0 AREA 1 TO LEVEL 3 AREA 1 OK LESS 4" | JEFF | JEFF | | PRD | P | 3090478 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/16/2006 | LEVEL 2 AREA 2 VENTS AT FETAL MED 1 TO ULTRASOUND 1 OK | JEFF | JEFF | | PTO | P | 3090470 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/15/2006 | FIELD CANCELLED | JEFF | JEFF | | PTO | P | 3090462 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 05/12/2006 | LOST TEST, ADD HANGERS ON 4" LEADERS IN BASEMENT, BASEMENT TO LEVEL 3 | JEFF | JEFF | | PRD | P | 3090453 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/11/2006 | LEVEL 1 AREA 1 WASTE TO LDR 2161, VENTS LEVEL 1 AREA 1 THROUGH RESUSCITATION TO LEVEL 2 COMPLETE | JEFF | JEFF | | PTO | P | 3090445 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/09/2006 | LEVEL 1 AREA 1 TO LEVEL 2 LABOR DELIVERY CORRIDOR 2115-2116 STAIRWELL 1 | JEFF | JEFF | | PTO | P | 3090438 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/08/2006 | LEVEL 1 AREA 1 TO LEVEL 2 LABOR/DELIVERY AND PUBLIC RESTROOMS AT WOMENS ENTRANCE, VENT STACK LEVEL 1 AREA 1 CONFERENCE AND CORRRIDOR TO LEVEL 2 | JEFF | JEFF | | PTO | P | 3090429 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/04/2006 | INSPECTED HDPW PIPE TO BE BURIED. OK TO COVER. PRESSURE TEST AT LATER DATE. | MICK | MICK | | PTO | P | 3090421 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/03/2006 | DWV LEVEL 1 AREA 1 SHELL VENTS TO LEVEL 2 SOUTH SHAFT, WATER PIPE LEVEL 2 AREA 2 TRUNK LINES AND ROOMS CLOUD A | JEFF | JEFF | | PTO | P | 3090413 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/02/2006 | LEVEL 1 AREA 1 UNFINISHED TO LEVEL 2 COLUMN LINES U-Z | JEFF | JEFF | | PTO | P | 3090405 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/01/2006 | LEVEL 1 AREA 1 6" WASTE AT SOUTH HVAC SHAFT TO LEVEL 2 OK | JEFF | JEFF | | PTO | P | 3090399 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/28/2006 | CORIIDOR 1261 TO INCLUDE REST OF NURSES POD E LEVEL 1 TO SECOND FLOOR, ROLL SHOWER VENT AT SHOWER 2161 MENS SHOWER | JEFF | JEFF | | PTO | P | 3090391 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/27/2006 | NURSES POD E LEVEL 1 TO 4" VENT STACK LESS 3" BRANCH TOWARD JANITORS CLOSET | JEFF | JEFF | | PTO | P | 3090384 |
COMMERCIAL DESIGN ENGEERING LTD | P= | C | 04/27/2006 | SANITARY FLOOR DRAINS IN ELEVATOR PITS OK PER DAVE LONDON, TO COMPLETE CDE | JEFF | JEFF | | P= | C | 3091807 |
COMMERCIAL DESIGN ENGEERING LTD | PB | C | 04/27/2006 | CONTRACTOR COMPLETE WITH UNDER GROUND | JEFF | JEFF | | PB | C | 3091800 |
COMMERCIAL DESIGN ENGEERING LTD | PTO | P | 04/21/2006 | REPIPE ROOM 1281. | MICK | MICK | | PTO | P | 3091794 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/17/2006 | PUBLIC RESTROOM 1278 DWV LEVEL ONE OK | JEFF | JEFF | | PTO | P | 3090377 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/07/2006 | AREA 1 LEVEL 0 DWV THRU 1ST FLOOR, O.K, NEEDS TO FILL 12'' DWV MAIN FULL | JOEL | JOEL | | PTO | P | 3090370 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/03/2006 | AREA 1&2 LEVEL 0&1 H2O MAINS, AREA 1 LEVEL 2 DWV NORTH END | JOEL | JOEL | | PTO | P | 3090361 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 03/30/2006 | LEVEL O 4'' DWV O.K | JOEL | JOEL | | PTO | P | 3090352 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 03/29/2006 | 4'' NORTH MECH. ROOM VENT THRU 2ND FLOOR | JOEL | JOEL | | PTO | P | 3090344 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 03/27/2006 | 8'' DWV MAIN IN LOWER LEVEL, 3 BATHS IN CENTRAL AREA ON FIRST FLOOR DOWN TO LOWER LEVEL | JOEL | JOEL | | PTO | P | 3090336 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 03/17/2006 | | JOEL | JOEL | | PRD | P | 3090329 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 03/15/2006 | LEVEL ONE AREA 2 H2O LOOP AND WALLSO.K, DWV N.W CORNER AND 4'' BELOW O.K | JOEL | JOEL | | PTO | P | 3090322 |
COMMERCIAL DESIGN ENGEERING LTD | PTO | P | 03/08/2006 | LEVEL ONE AREA 2 NORTH EAST POD DWV WALLS O.K | JOEL | JOEL | | PTO | P | 3091785 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 02/13/2006 | AREA 1 LEVEL 1 WEST END O.K | JOEL | JOEL | | PB | P | 3090314 |
COBB MECHANICAL CONTRACTORS, INC. | PRD | P | 01/10/2006 | SUTH END TRUNK LINES O.K | JOEL | JOEL | | PRD | P | 3090306 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 01/10/2006 | DECONTAMINATION LINE O.K | JOEL | JOEL | | PTO | P | 3090292 |
COMMERCIAL DESIGN ENGEERING LTD | PTO | P | 12/05/2005 | NEED TO VERIFY W/ ENGINEER WHETHER CHEMICAL WASTE PIPING IS REQUIRED | JOEL | JOEL | | PTO | P | 3091779 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 11/30/2005 | SOUTH END AREA 1 O.K | JOEL | JOEL | | PB | P | 3090285 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 11/28/2005 | S.E CORNER O.K | JOEL | JOEL | | PB | P | 3090277 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 11/21/2005 | AREA 1 N.E CORNER O.K | JOEL | JOEL | | PB | P | 3090268 |
COBB MECHANICAL CONTRACTORS, INC. | PB | P | 11/07/2005 | AREA 2 N.E UNDERGROUND O.K | JOEL | JOEL | | PB | P | 3090261 |
COBB MECHANICAL CONTRACTORS, INC. | PB | R | 11/03/2005 | CONTRACTOR CANCELLED | JOEL | JOEL | | PB | R | 3090253 |
COMMERCIAL DESIGN ENGEERING LTD | PB | C | 08/23/2005 | | JEFF | JEFF | | PB | C | 3091772 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/15/2005 | POSSIBLE SEWER STUB INSPECTION, REST OK | JEFF | JEFF | | PB | P | 3091766 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/10/2005 | AREA DRAINS AT COLUMN C13/C20/C21 OK | JEFF | JEFF | | PB | P | 3091759 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/09/2005 | AREA DRAINS AT COLUMN 28/29 OK | JEFF | JEFF | | PB | P | 3091750 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/08/2005 | MED GAS COMP AND CRACK UNIT DRAINS OK | JEFF | JEFF | | PB | P | 3091742 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/06/2005 | EREAS 0022/0029 OK | JEFF | JEFF | | PB | P | 3091734 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 06/01/2005 | SANITARY DRAIN TRUNK LINE TO LARGE SUMP PIT COMPLETE | JEFF | JEFF | | PB | P | 3091729 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/31/2005 | SOUTH ELEVATOR PIT OK | JEFF | JEFF | | PB | P | 3091719 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/19/2005 | SANITARY NORTH OD SD SUMP PIT OK | JEFF | JEFF | | PB | P | 3091711 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/18/2005 | 4" NORTH OF SD SUMP PIT OK | JEFF | JEFF | | PB | P | 3091699 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/13/2005 | COLUMN 28-29-20 TRUNK LINE OK | JEFF | JEFF | | PB | P | 3091691 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/10/2005 | 6'' FLOOR DRAINS, MARKED ON SHOP PLAN WITH MIKE, ALSO DRAWN ON BACK OF ORANGE LOG CARD LEFT WITH MIKE, 10 FLOOR DRAINS AND 2 VENTS UNDER TEST | JACK | JACK | | PB | P | 3091684 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/09/2005 | SD TO SE EREA WAY OK | JEFF | JEFF | | PB | P | 3091676 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 05/06/2005 | SANITARY? AT 0031/0032 TO PIT(QUESTIONING SIZE OF PIT FOR PRIVATE SINGLE RESTROOM), STORM TO COLUMN 13 | JEFF | JEFF | | PB | P | 3091668 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 04/28/2005 | RESTROOMS 0031/0032 LESS PIT/FD/MOP SINK | JEFF | JEFF | | PB | P | 3091662 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 04/27/2005 | TRUNK LINE TO RESTROOMS OO31/0032 LESS PIT | JEFF | JEFF | | PB | P | 3091654 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 04/22/2005 | SANITARY AND STORM TRUNK LINES ONLY EVEN TO C28, NO DRAIN IN ELEVATOR PITS ALLOWED TO SANITARY, REVISE PLANS | JEFF | JEFF | | PB | P | 3091645 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 04/13/2005 | FROM AND TO UNDER DRAIN SUMP PIT TO COLUMN C61/C62, REMOVE SANITARY OVERFLOW FROM STORM DRAIN SUMP PIT BY NEXT INSPECTION | JEFF | JEFF | | PB | P | 3091638 |
COMMERCIAL DESIGN ENGEERING LTD | PB | P | 04/07/2005 | COLUMN C105-C84 COMBINATION WASTE AND VENT TRUNK LINE ONLY | JEFF | JEFF | | PB | P | 3091631 |
OTIS ELEVATOR COMPANY | V= | C | 11/28/2007 | | TOM | TOM | | V= | C | 3091815 |
PCL CONSTRUCTION SERVICES, INC | V= | C | 11/26/2007 | OTIS--CARS 33/38/39/40/41/42 ALL ITEMS CORRECTED--OK TO ISSUE PERMIT | TOM | TOM | | V= | C | 3092582 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 10/23/2007 | OTIS--NUMBER CAR LIGHT LOCKOUTS IN MACH RM TO MATCH MACHINE NUMBERS--SPRINKLER IN PIT COVERED W/ DIRT ETC--ERU UNIT NOT CHECKED--CHECK TO SEE IF RELAY FOR ERU DISCONNECT IS INSTALLED IN MAINLINE DISCONNECT--FIRE FINAL--110V LIGHTING & GFI AT TOP OF H/W--CAR # 42 | TOM | TOM | | V= | P | 3092566 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 10/23/2007 | OTIS--FIRE SEAL MACH. RM. & HOISTWAY PENETRATIONS--MACH RM DOOR TO SELF CLOSE SELF LOCK--"ELEVATOR EQUIPMENT SIGN ON MACH RM DOOR--PHONE IN CAR--OPEN CAVITY @ TOP OF HOISTWAY--HEAT PROBE EXTENDING INTO HOISTWAY AT LEVEL 4--NUMBER MAIN LANDING WITH ELEVATOR NUMBER--DATE CROSSHEAD--SECURE TOP OF CAR HATCH & SWITCH--TAG ALL APPROPIATE EQUIPMENT--FIRE FINAL--VARIOUS ITEMS FOR OTIS TO FINISH--110V LIGHTING & GFI TOP OF H/W--CAR # 41 | TOM | TOM | | V= | P | 3092574 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 09/10/2007 | OTIS HYDRO--CAR # 40--HATCH SWITCH--TOP OF H/W PENE--GROUT SILLS--NUMBER CAR TOP ETC--PIT LADDER TO EXTEND 48" ABOVE LANDING SILL | TOM | TOM | | V= | P | 3092558 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 09/10/2007 | OTIS CAR # 39--SEE CAR # 33 | TOM | TOM | | V= | P | 3092550 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 09/10/2007 | OTIS CAR # 38--SEE COMMENTS CAR # 33 | TOM | TOM | | V= | P | 3092542 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 09/10/2007 | OTIS CAR # 33--PHONE--BEVEL LEDGES--M/R DOOR SIGN--OVERHEAD 110V--OPEN DUCTING @ TOP OF H/W--UNCOVER DRAINS IN PITS--GUARDING ON PIT LIGHTS--COMMUNICATION BETWEEN CAR & M/R | TOM | TOM | | V= | P | 3092534 |
PCL CONSTRUCTION SERVICES, INC | V= | P | 09/28/2006 | NEED SEAL HOLES IN MECH ROOM--SIGNAGE ON MECH ROOM DOOR--LIGHT TOP OF HOISTWAY--MOVE CABLE 2ND LEVEL--PROVIDE LIGHT AT ALL CALL STATIONS--OPERATOR AND 2 WAY COMMUNICATIONS--CONSTRUCTION USE ONLY | JOHNW | JOHNW | | V= | P | 3092525 |