GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 10/25/2006 | | TERRYB | TERRYB | | B= | C | 3215133 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | C | 09/13/2006 | WEST ENTRY | TERRYB | TERRYB | | BFT | C | 3215125 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 07/25/2006 | TUNNEL LID APPROX 10' FOR EXISTING BUILDING OK | DANF | DANF | | BFT | P | 3215117 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 07/10/2006 | EXTERIOR WALLS | TERRYB | TERRYB | | BFR | C | 3214930 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 06/21/2006 | UTILITY TUNNEL | TERRYB | TERRYB | | BFN | P | 3215108 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 06/08/2006 | FOOTER FOR UTILITY CONNECTING TUNNEL | TERRYB | TERRYB | | BSP | P | 3215095 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 05/18/2006 | TOP OF ESCAPE TUNNEL | TERRYB | TERRYB | | BFN | P | 3215088 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 05/15/2006 | WEST ENTRY | TERRYB | TERRYB | | BFN | P | 3214922 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 05/04/2006 | EAST WALL STAIRS | TERRYB | TERRYB | | BFN | P | 3215080 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 05/04/2006 | WEST STAIRS | TERRYB | TERRYB | | BFT | P | 3215072 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 04/20/2006 | WALLS FOR TUNNEL AND FOOTER FOR STAIRS | TERRYB | TERRYB | | BFT | P | 3215064 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | R | 04/18/2006 | STEEL NOT READY; RECALL | DANF | DANF | | BFN | R | 3215056 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 04/13/2006 | FOOTER AT ESCAPE TUNNEL | TERRYB | TERRYB | | BFT | P | 3215048 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 04/10/2006 | WALL FOR STAIRWAY CONNECTION TO NEW BUILDING; WALL FOR NEW CHIMMINEY | DANF | DANF | | BFN | P | 3215040 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 04/05/2006 | ELECTRIC ROOM, OFFICE AND BATHROOM | TERRYB | TERRYB | | BFR | P | 3215031 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 04/04/2006 | STAIRWELL | TERRYB | TERRYB | | BFT | P | 3215024 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 03/28/2006 | STRUCTURAL FLOOR | TERRYB | TERRYB | | BFN | P | 3215015 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFD | C | 02/03/2006 | NORTH AND WEST WALLS ONLY | TERRYB | TERRYB | | BFD | C | 3215007 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 02/03/2006 | BALANCE OF INTERIOR PADS | TERRYB | TERRYB | | BFT | P | 3214999 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 02/01/2006 | SOUTH WALL | TERRYB | TERRYB | | BFN | P | 3214991 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 01/25/2006 | BALANCE OF WEST WALL AND 10' AT SOUTH WALL TOWARD EAST | TERRYB | TERRYB | | BFN | P | 3214986 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 01/24/2006 | 2 INTERIOR PADS | TERRYB | TERRYB | | BFT | P | 3214978 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 01/17/2006 | NORTH WALL AND 14' SOUTH OF NORTH WALL ON WEST WALL | TERRYB | TERRYB | | BFN | P | 3214970 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 01/12/2006 | BALANCE OF FOOTER AND 1 INTERIOR PAD | TERRYB | TERRYB | | BFT | P | 3214962 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFN | P | 01/09/2006 | FOOTER STEEL WEST SIDE OK - MARKED ON PLAN / WALL STEEL EAST SIDE OK - MARKED ON PLAN | MICHAELA | MICHAELA | | BFN | P | 3214954 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 01/05/2006 | PORTION OF SOUTH WALL SEE PLANS FOR AREA INSPECTED | TERRYB | TERRYB | | BFT | P | 3214946 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 12/30/2005 | SEE PLANS FOR AREA INSPECTED | TERRYB | TERRYB | | BFT | P | 3214937 |
GREEN ELECTRIC INC | E= | C | 09/28/2006 | | MIKEC | MIKEC | | E= | C | 3215299 |
GREEN ELECTRIC INC | ER | P | 08/07/2006 | | MIKEC | MIKEC | | ER | P | 3215288 |
GREEN ELECTRIC INC | EUG | C | 06/29/2006 | | MIKEC | MIKEC | | EUG | C | 3215280 |
GREEN ELECTRIC INC | ESL | C | 02/09/2006 | | MIKEC | MIKEC | | ESL | C | 3215272 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 09/29/2006 | HWP FINAL. | LYNNS | LYNNS | | H= | C | 3215193 |
COLORADO SHEET METAL CO., INC. | H= | C | 09/29/2006 | RECEIVED BALANCE REPORT FROM TAB SERVICES, INC, DENVER CO. | LYNNS | LYNNS | | H= | C | 3215265 |
COLORADO SHEET METAL CO., INC. | H= | P | 08/31/2006 | FINAL PENDING BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3215257 |
COLORADO SHEET METAL CO., INC. | HV | C | 08/18/2006 | BOILER VENT COMPLETE. | LYNNS | LYNNS | | HV | C | 3215249 |
COLORADO SHEET METAL CO., INC. | HD | C | 08/18/2006 | ROUGH DUCT IN BOILER ROOM AREA. | LYNNS | LYNNS | | HD | C | 3215241 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 08/17/2006 | 4- 200# TESTS ON HYDRO LINES OK. | LYNNS | LYNNS | | HWP | P | 3215186 |
COLORADO SHEET METAL CO., INC. | HV | P | 08/03/2006 | PARTIAL BOILER VENT STACK OK TO ENCLOSE. | LYNNS | LYNNS | | HV | P | 3215233 |
OLSON PLUMBING & HEATING COMPANY | HC | C | 08/03/2006 | OK FOR METER. | LYNNS | LYNNS | | HC | C | 3215178 |
OLSON PLUMBING & HEATING COMPANY | HI | P | 07/26/2006 | 60# TEST ON A 10# GAS DELIVERY LINE TO BOILERS. | LYNNS | LYNNS | | HI | P | 3215173 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 10/02/2006 | | MARTY | MARTY | | P= | C | 3215225 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 08/15/2006 | BOILER ROOM. | MARTY | MARTY | | PTO | C | 3215216 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 01/03/2006 | | JOEL | JOEL | | PB | C | 3215208 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 12/30/2005 | LOWER LEVEL W/C WET VENTED WITH 3" STACK FOR UPPER LEVEL, OTHER AREAS OK TO COVER | LEE | LEE | | PB | P | 3215200 |