THE COPESTONE COMPANY | B= | C | 07/20/2007 | THIS IS OKAY TO CLOSE AS FIRE SIGNED OFF ON HIS CARD APPROVED, DAC | ANGELA | ANGELA | | B= | C | 3425963 |
THE COPESTONE COMPANY | B= | P | 07/13/2007 | NEED FIRE FINAL | JOHNP | JOHNP | | B= | P | 3425955 |
PROFESSIONAL PIPING, LLC | BSP | T | 07/03/2007 | PAID (REC#759074)ADDITIONAL PLAN REVIEW TIME: $50.000 From: DARYL Relocated gas lines | DARYL | DARYL | | BSP | T | 3426134 |
THE COPESTONE COMPANY | BBB | C | 06/29/2007 | LETTER PICKED UP | JOHNP | JOHNP | | BBB | C | 3425948 |
THE COPESTONE COMPANY | BIN | C | 06/21/2007 | | JOHNP | JOHNP | | BIN | C | 3425940 |
THE COPESTONE COMPANY | BLA | C | 06/08/2007 | | JOHNP | JOHNP | | BLA | C | 3425933 |
THE COPESTONE COMPANY | BLA | P | 06/04/2007 | PARAPHETS; TOWERS AT 1-A, 15-F; 23-D OK | JOHNP | JOHNP | | BLA | P | 3425925 |
THE COPESTONE COMPANY | BIN | P | 05/16/2007 | PERIMETER UP TO CEILING LINE | JOHNP | JOHNP | | BIN | P | 3425917 |
THE COPESTONE COMPANY | BSP | T | 05/16/2007 | PAID (REC#753758)ADDITIONAL PLAN REVIEW TIME: $50.000 From: DARYL Rerouted drains and installed two interceptors rather than one. | DARYL | DARYL | | BSP | T | 3425909 |
THE COPESTONE COMPANY | BFR | C | 05/09/2007 | | JOHNP | JOHNP | | BFR | C | 3425900 |
THE COPESTONE COMPANY | BFR | P | 04/05/2007 | TOWER STUDS & JOISTS OK, 5 LINE SHEAR WALLS OK; INTERIOR PERIMETER STEEL STUDS, EXCEPT TOWERS OK | JOHNP | JOHNP | | BFR | P | 3425891 |
THE COPESTONE COMPANY | BLA | P | 04/04/2007 | UP TO ROOFLINE OK | JOHNP | JOHNP | | BLA | P | 3425883 |
THE COPESTONE COMPANY | BFR | P | 03/09/2007 | REST OF SOFFIT & FASCIA OK | JOHNP | JOHNP | | BFR | P | 3425876 |
THE COPESTONE COMPANY | BFR | P | 03/06/2007 | SOFFIT & FASCIA AS MARKED ON PLANS | JOHNP | JOHNP | | BFR | P | 3425863 |
THE COPESTONE COMPANY | BFR | P | 03/02/2007 | FASCIA & SOFFITS AS MARKED ON PLANS | JOHNP | JOHNP | | BFR | P | 3425857 |
THE COPESTONE COMPANY | BFR | P | 02/27/2007 | EXTERIOR STEEL STUDS AT PARAPHET & SOFFIT OK AT 19 - 23 LINES | JOHNP | JOHNP | | BFR | P | 3425848 |
THE COPESTONE COMPANY | BFN | C | 02/27/2007 | LETTER ON FILE | JOHNP | JOHNP | | BFN | C | 3425841 |
THE COPESTONE COMPANY | BBB | P | 12/13/2006 | NE WALL AT 12' ELEVATION OK | JOHNP | JOHNP | | BBB | P | 3425833 |
THE COPESTONE COMPANY | BFN | R | 12/13/2006 | CANCELED | JOHNP | JOHNP | | BFN | R | 3425825 |
THE COPESTONE COMPANY | BBB | P | 12/12/2006 | OK EARTH ENGINEERING TO DO BOND BEAMS | JIMP | JIMP | | BBB | P | 3425818 |
THE COPESTONE COMPANY | BFN | P | 12/06/2006 | ALL WALLS COMPLETE, JUST NEED FULL SOILS OPEN HOLE REPORT | JOHNP | JOHNP | | BFN | P | 3425811 |
THE COPESTONE COMPANY | BFT | C | 12/05/2006 | REST OF PADS OK | JOHNP | JOHNP | | BFT | C | 3425805 |
THE COPESTONE COMPANY | BFT | P | 11/27/2006 | 3 NORTH INTERIOR PADS, MARKED ON PLANS | JOHNP | JOHNP | | BFT | P | 3425800 |
THE COPESTONE COMPANY | BFI | C | 11/27/2006 | | JOHNP | JOHNP | | BFI | C | 3425793 |
THE COPESTONE COMPANY | BFI | P | 11/21/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFI | P | 3425784 |
THE COPESTONE COMPANY | BFN | P | 11/21/2006 | PERIMETER WALLS OK | JOHNP | JOHNP | | BFN | P | 3425778 |
THE COPESTONE COMPANY | BFI | P | 11/17/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFI | P | 3425772 |
THE COPESTONE COMPANY | BFN | P | 11/17/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFN | P | 3425766 |
THE COPESTONE COMPANY | BFT | P | 11/17/2006 | PERIMETER COMPLETE | JOHNP | JOHNP | | BFT | P | 3425755 |
THE COPESTONE COMPANY | BFN | P | 11/14/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFN | P | 3425747 |
THE COPESTONE COMPANY | BFT | P | 11/14/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFT | P | 3425734 |
THE COPESTONE COMPANY | BIN | P | 11/14/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BIN | P | 3425726 |
THE COPESTONE COMPANY | BFN | P | 11/09/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFN | P | 3425717 |
THE COPESTONE COMPANY | BFT | P | 11/07/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFT | P | 3425710 |
THE COPESTONE COMPANY | BFT | P | 11/02/2006 | AS MARKED ON APPROVED PLANS | JOHNP | JOHNP | | BFT | P | 3425700 |
FOSTER ELECTRIC CORPORATION | E= | C | 06/28/2007 | | JOSEPH | JOSEPH | | E= | C | 3426118 |
FOSTER ELECTRIC CORPORATION | E= | R | 06/25/2007 | EXTERIOR LIGHT NOT WORKING; ROOF TOP UNIT ABOVE UNIE 4359 NOT INSTALLED; USE PLASTIC BUSHINGS ON ROOF TOP DISCONNECTS WHERE YOU ARE USING A CLOSE NIPPLE; PANEL O AND P ARE INCOMPLETE | JOSEPH | JOSEPH | | E= | R | 3426110 |
FOSTER ELECTRIC CORPORATION | ER | C | 06/07/2007 | | JOSEPH | JOSEPH | | ER | C | 3426104 |
FOSTER ELECTRIC CORPORATION | ES | C | 06/06/2007 | COMMERCIAL SERVICE: 2 - 1200 AMP 3 PHASE 120 /208 VOLT SERVICES; ( 2 SEPERATE METER STACKS) BY FOSTER ELECTRIC; NEED 18 METERS SET; METER TAGS READ 4307A; 4307B; 4311; 4315; 4319A; 4319B; 4323; 4331A; 4331B; 4335A; 4335B; 4339; 4343A; 4343B; 4355; 4359A; 4359B; 4327 | JOSEPH | JOSEPH | | ES | C | 3426092 |
FOSTER ELECTRIC CORPORATION | EP | R | 06/06/2007 | SOME OF THE METER TAGS ARE IDENTICAL. THEY NEED TO BE RELABELED (ADD A LETTER TO DISTINGUISH) WHERE MORE THAN ONE SERVICE DISCONNECT SUPPLIES POWER TO A SINGLE TENNANT SPACE PHEONELIC LABELING IS REQUIRED ON ALL PANELS AND DISCONNECTS ON BOTH ENDS. ALL OTHER CORRECTIONS MADE | JOSEPH | JOSEPH | | EP | R | 3426086 |
FOSTER ELECTRIC CORPORATION | ES | R | 06/04/2007 | COLD WATER GROUNDING ELECTROUD CONDUCTOR NEEDS TO LAND DIRECTLY TO SERVICE NEUTRAL; SECURE #4 UFER GROUND TO SIDE OF METER STACK SO IT CANNOT ACCIDENTLY TOUCH UNGROUNDED BUSSES; LABEL EACH SERVICE WITH PHENOLIC LABELING. ALL OPENINGS (CAUSED BY DAMAGING CONCENTRIC KNOCKOUTS) IN BOTTOM OF METER STACK MUCT BE SEALED | JOSEPH | JOSEPH | | ES | R | 3426079 |
FOSTER ELECTRIC CORPORATION | ER | P | 05/16/2007 | WALLS SUB PANELS AND BRANCH CIRCUITS LEAVING SUB PANELS | JOSEPH | JOSEPH | | ER | P | 3426071 |
FOSTER ELECTRIC CORPORATION | EUG | P | 05/15/2007 | FOUR LIGHT POLES ON SW SIDE ONLY | JOSEPH | JOSEPH | | EUG | P | 3426062 |
FOSTER ELECTRIC CORPORATION | ER | P | 04/20/2007 | EXTERIOR WALLS (SUB PANELS ONLY) | JOSEPH | JOSEPH | | ER | P | 3426054 |
FOSTER ELECTRIC CORPORATION | EUG | P | 03/09/2007 | 3/4 INCH PVC UNDER SLAB OK TO COVER | JOSEPH | JOSEPH | | EUG | P | 3426047 |
FOSTER ELECTRIC CORPORATION | EUG | P | 11/27/2006 | PERIMETER WALL ON SOUTH SIDE ONLY | JOSEPH | JOSEPH | | EUG | P | 3426039 |
FOSTER ELECTRIC CORPORATION | EUG | P | 11/21/2006 | 2-1/2" PVC PIPES ON EAST PERIMETER WALL ONLY | JOSEPH | JOSEPH | | EUG | P | 3426030 |
FOSTER ELECTRIC CORPORATION | EUG | P | 11/17/2006 | PANEL FEEDERS ON F LINE, GRID 13 TO 23 | THOMAS | THOMAS | | EUG | P | 3426022 |
FOSTER ELECTRIC CORPORATION | ESL | P | 11/14/2006 | UFER OK | JOSEPH | JOSEPH | | ESL | P | 3426015 |
PROFESSIONAL PIPING, LLC | HC | C | 10/10/2007 | RELEASE METERS FOR UNITS 4335, 4345 AND 4355. | LYNNS | LYNNS | | HC | C | 3426170 |
PROFESSIONAL PIPING, LLC | H= | C | 07/09/2007 | GAS FINAL, PLANS REVISED AND APPROVED. | LYNNS | LYNNS | | H= | C | 3426160 |
PROFESSIONAL PIPING, LLC | H= | P | 06/22/2007 | REVISE PLANS | JOEL | JOEL | | H= | P | 3426152 |
FRONTIER MECHANICAL INC. | H= | C | 06/22/2007 | | JOEL | JOEL | | H= | C | 3426125 |
PROFESSIONAL PIPING, LLC | HI | C | 06/21/2007 | 11- 10# TESTS AND DESIGN OK. BY FINAL, COMPLETE STRAPS ON GAS LINES AND REVISE PLANS TO SHOW CHANGES, SUBMIT TO RBD FOR APPROVAL. | LYNNS | LYNNS | | HI | C | 3426144 |
PROFESSIONAL PIPING, LLC | P= | C | 07/03/2007 | INSTALLED 1 1/2" RP FOR IRRIGATION, TWO TESTABLE DEVICES | JEFF | JEFF | | P= | C | 3426273 |
PROFESSIONAL PIPING, LLC | PTO | C | 07/03/2007 | | JEFF | JEFF | | PTO | C | 3426265 |
PROFESSIONAL PIPING, LLC | P= | R | 06/26/2007 | SEE PTO NOTES | LYNNIE | LYNNIE | | P= | R | 3426257 |
PROFESSIONAL PIPING, LLC | PTO | R | 06/26/2007 | 1) NO DRAIN FOR RP DEVICE 2) NO WATER METER INSTALLED--NO RP FOR SPRINKLER AT THIS TIME--FUTURE? | LYNNIE | LYNNIE | | PTO | R | 3426250 |
PROFESSIONAL PIPING, LLC | PRD | C | 06/11/2007 | | LYNNIE | LYNNIE | | PRD | C | 3426242 |
PROFESSIONAL PIPING, LLC | PRD | P | 06/06/2007 | THREE TOWERS AND S/W SIDE COMPLETE, S/E TWO DRAINS COMPLETE, NEED N/E INCLUDING THREE TOWERS TO COMPLETE | LEE | LEE | | PRD | P | 3426235 |
PROFESSIONAL PIPING, LLC | PTO | P | 06/06/2007 | LACKS WRAP ON F/D VENT AND WATER PIPE INSULATION THRU-OUT, TESTS OK | LEE | LEE | | PTO | P | 3426227 |
PROFESSIONAL PIPING, LLC | PB | C | 05/23/2007 | | LYNNIE | LYNNIE | | PB | C | 3426217 |
PROFESSIONAL PIPING, LLC | PB | R | 05/21/2007 | NO PLANS IN SIGHT | LYNNIE | LYNNIE | | PB | R | 3426209 |
PROFESSIONAL PIPING, LLC | PB | P | 05/18/2007 | GREASE LINE NORTH END HOLDING PRESSURE AND SANITARY AT NORTH END LOST TEST, PLANS HAVE BEEN REVISED | JACK | JACK | | PB | P | 3426200 |
PROFESSIONAL PIPING, LLC | PB | P | 12/11/2006 | REVISE APPROVED PLANS AS TO THE RELOCATION OF THE S.S. AND G.W. LINES EXITING THE BUILDING IN ANOTHER END OF THE BUILDING--GREASE TRAP TOO? | LYNNIE | LYNNIE | | PB | P | 3426192 |
PROFESSIONAL PIPING, LLC | PB | P | 12/06/2006 | G. W. AND .S.S---WATER METER ROOM LACKS A 4'' FLOOR DRAIN--P1.01--CLOUDED AREAS | LYNNIE | LYNNIE | | PB | P | 3426186 |
PROFESSIONAL PIPING, LLC | PB | P | 12/01/2006 | PERMIT IS GOOD FOR A TOTAL OF 5 INSPECTIONS---G.W. AND S.S. P1.01--HIGH LIGHTED AREAS | LYNNIE | LYNNIE | | PB | P | 3426179 |