PCL CONSTRUCTION SERVICES, INC | B= | C | 11/29/2007 | FIRE FINAL SIGNED OFF ON CARD 11-27-07/ZONING SIGNED OFF ON CARD 11-29-07 | BERTW | BERTW | | B= | C | 3482653 |
CONTRACTOR NOT SPECIFIED | B= | P | 11/25/2007 | Temp CO: 6TH AND 7TH FLOORS OK, PENDING OTHER INSPECTIONS. | MINDY | MINDY | | B= | P | 3482169 |
PCL CONSTRUCTION SERVICES, INC | B= | P | 11/20/2007 | TCO EXTENDED TO 12-25-07 | JAN | JAN | | B= | P | 3482645 |
PCL CONSTRUCTION SERVICES, INC | B= | P | 10/25/2007 | 6TH AND 7TH FLOORS OK, PENDING OTHER INSPECTIONS. | ED | ED | | B= | P | 3482638 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 07/25/2007 | 7TH FLOOR NORTH POD ABOVE CEILING OK/ CORRIDOR SMOKE WALLS WITH PLENUMS IN THEM TO STORAGE AREAS - STILL NOT FIXED-CANNOT HAVE PENETRATIONS | BERTW | BERTW | | BFR | P | 3482631 |
PCL CONSTRUCTION SERVICES, INC | BFR | R | 07/24/2007 | CALLED 303-667-1703 -3 TIMES FROM 11AM TO 11-30AM/WAITED ON 7TH FLOOR BUT COULDNT FIND SUPER/PLEASE RECALL | BERTW | BERTW | | BFR | R | 3482625 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 07/20/2007 | 7TH FLOOR SOUTH POD ABOVE CEILING, NEED TO TALK TO PLAN CHECK ABOUT ANY UNPROTECTED OPENINGS IN SMOKE WALLS | TERRYB | TERRYB | | BSP | P | 3482617 |
PCL CONSTRUCTION SERVICES, INC | BSP | T | 06/26/2007 | PAID (REC#761190)ADDITIONAL PLAN REVIEW TIME: $50.000 From: RICH revised sheet LS70, 7th floor smoke control wall,G19358 | RICH | RICH | | BSP | T | 3482610 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 06/25/2007 | 6TH FLOOR ABOVE CEILING | TERRYB | TERRYB | | BSP | P | 3482602 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 06/19/2007 | AREA D-WEST WALLS AND DROP SOFFIT OK | BERTW | BERTW | | BFR | P | 3482594 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 06/06/2007 | AREA D OK | TERRYB | TERRYB | | BFR | P | 3482585 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 05/30/2007 | 7TH FLOOR AREA C | TERRYB | TERRYB | | BFR | P | 3482579 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 05/22/2007 | 7TH FLOOR AREA "B" FRAMING AND FLOOR PENETRATIONS OK | BERTW | BERTW | | BFR | P | 3482571 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 05/08/2007 | 7TH FLOOR AREA "A" WALLS OK/NEED FLOOR PENETRATIONS SEALED | BERTW | BERTW | | BFR | P | 3482563 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/30/2007 | 6TH FLOOR WALLS UNITS A AND B OK/RATED WALL @ MENS LOCKER ROOM AND DRINKING FOUNTAIN OK | BERTW | BERTW | | BFR | P | 3482555 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/23/2007 | FLOOR PENETRATION FIRESTOP | TERRYB | TERRYB | | BFR | P | 3482548 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/20/2007 | 6TH FLOOR AREA B WALLS OK/NEED FIRE CAULK INSPECTION | BERTW | BERTW | | BFR | P | 3482539 |
PCL CONSTRUCTION SERVICES, INC | BSP | P | 04/17/2007 | FIRECAULKING @ FLOOR PENETRATIONS AND CURTAIN WALLS OK AREA 6A ONLY | BERTW | BERTW | | BSP | P | 3482531 |
PCL CONSTRUCTION SERVICES, INC | BFR | P | 04/16/2007 | 6TH FLOOR WALLS OK TO ONE SIDE/NEED ALL FLOOR PENETRATIONS SEALED/ON 7TH FLOOR NEED TO REMOVE DRYWALL FROM CURTAIN WALLS IN AREAS FOR SPOT CHECK OF FIRECAULKING AND EXPOSE SHAFT LINERS FOR SPOT CHECK/NEED ALL OTHER ROUGH INSPECTIONS AND CORE SHELL SINDE OFF | BERTW | BERTW | | BFR | P | 3482524 |
RIVIERA ELECTRIC | E= | C | 11/13/2007 | | MATTHEW | MATTHEW | | E= | C | 3483028 |
RIVIERA ELECTRIC | E= | P | 11/05/2007 | NEED METALIC SEALTITE, IS NEUTRAL BONDED IN UPS ?, CONTRACTOR NEEDS TO COMPLETE INSTALLATION | MATTHEW | MATTHEW | | E= | P | 3483020 |
RIVIERA ELECTRIC | E= | P | 10/31/2007 | COMPLETE EXCLUDING: EQUIPMENT HOOK UP IN ROOM 7086 | MATTHEW | MATTHEW | | E= | P | 3483011 |
RIVIERA ELECTRIC | E= | P | 10/16/2007 | SEVENTH FLOOR MARKED ON TE3.72 OK | MATTHEW | MATTHEW | | E= | P | 3483004 |
RIVIERA ELECTRIC | E= | P | 10/15/2007 | TE 3.72 EXCLUDING NEUCLER MEDICINE | THOMAS | THOMAS | | E= | P | 3482996 |
RIVIERA ELECTRIC | E= | P | 10/15/2007 | SEVENTH FLOOR MARKED ON PLANS OK | MATTHEW | MATTHEW | | E= | P | 3482988 |
RIVIERA ELECTRIC | E= | P | 10/12/2007 | SEVENTH FLOOR SOUTHEAST SHEET TE 3.71 | THOMAS | THOMAS | | E= | P | 3482980 |
RIVIERA ELECTRIC | E= | P | 10/11/2007 | SEVENTH FLOOR SOUTH--REFER TO SHEET TE 3.71 | THOMAS | THOMAS | | E= | P | 3482972 |
RIVIERA ELECTRIC | ER | P | 09/21/2007 | nurses stations te3.72 | MATTHEW | MATTHEW | | ER | P | 3482963 |
RIVIERA ELECTRIC | ER | P | 09/20/2007 | hardlid te4.72 | MATTHEW | MATTHEW | | ER | P | 3482954 |
RIVIERA ELECTRIC | ER | P | 09/14/2007 | NURSES STATION TE 3.72, CEILING TE4.72 | MATTHEW | MATTHEW | | ER | P | 3482945 |
RIVIERA ELECTRIC | ER | P | 09/07/2007 | MILWORK 3.72 & HARDLIDS 4.62 | THOMAS | THOMAS | | ER | P | 3482937 |
RIVIERA ELECTRIC | ER | P | 09/06/2007 | WALLS 3.23 & 4.23 | THOMAS | THOMAS | | ER | P | 3482929 |
RIVIERA ELECTRIC | ER | P | 08/20/2007 | NURSES STATION ON TE 3.71 OK | MATTHEW | MATTHEW | | ER | P | 3482920 |
RIVIERA ELECTRIC | ER | P | 08/16/2007 | CEILINS ON PLANS TE 4.72 OK | MATTHEW | MATTHEW | | ER | P | 3482913 |
RIVIERA ELECTRIC | ER | P | 08/14/2007 | NURSES STATIONS MARKED ON TE 3.71 OK | MATTHEW | MATTHEW | | ER | P | 3482903 |
RIVIERA ELECTRIC | ER | R | 08/09/2007 | NOT READY | MATTHEW | MATTHEW | | ER | R | 3482897 |
RIVIERA ELECTRIC | ER | P | 08/06/2007 | CEILINGS TE4.72 | MATTHEW | MATTHEW | | ER | P | 3482889 |
RIVIERA ELECTRIC | ER | P | 08/03/2007 | CEILINGS MARKED ON PLANE TE4.71 AND 72 OK | MATTHEW | MATTHEW | | ER | P | 3482882 |
RIVIERA ELECTRIC | ER | P | 08/01/2007 | WALLS TE 3.72-----GRID CIELINGS TE 4.72 | THOMAS | THOMAS | | ER | P | 3482874 |
RIVIERA ELECTRIC | ER | P | 07/23/2007 | CIELINGS E4.71 | THOMAS | THOMAS | | ER | P | 3482866 |
RIVIERA ELECTRIC | ER | P | 07/13/2007 | GRID CIELINGS E 4.71 | THOMAS | THOMAS | | ER | P | 3482859 |
RIVIERA ELECTRIC | ER | P | 07/06/2007 | CEILING MARKED ON PLANS TE 4.71 AND TE 3.62 OK | MATTHEW | MATTHEW | | ER | P | 3482852 |
RIVIERA ELECTRIC | ER | P | 07/05/2007 | GRID CIELINGS----3.61 3.62 | THOMAS | THOMAS | | ER | P | 3482844 |
RIVIERA ELECTRIC | ER | P | 07/02/2007 | WING WALLS FOR CHECK IN/OUT IN ROOM 7016; CEILING MARKED ON PLANS TE 3.61 OK | MATTHEW | MATTHEW | | ER | P | 3482836 |
RIVIERA ELECTRIC | ER | P | 06/29/2007 | GRID CIELINGS & UNDERCOUNTER E3.61 | THOMAS | THOMAS | | ER | P | 3482828 |
RIVIERA ELECTRIC | ER | P | 06/27/2007 | GRID CIELINGS 3.61----WALLS 3.72 | THOMAS | THOMAS | | ER | P | 3482821 |
RIVIERA ELECTRIC | ER | P | 06/26/2007 | CEILINGS ON SHEET TE3.61 & TE4.72 | JOSEPH | JOSEPH | | ER | P | 3482813 |
RIVIERA ELECTRIC | ER | P | 06/14/2007 | HARDLIDS TE 3.72 | THOMAS | THOMAS | | ER | P | 3482804 |
RIVIERA ELECTRIC | ER | P | 06/05/2007 | WALLS & HARDLIDS TE3.72 | THOMAS | THOMAS | | ER | P | 3482798 |
RIVIERA ELECTRIC | ER | P | 06/01/2007 | WALLS TE 3.72 | THOMAS | THOMAS | | ER | P | 3482791 |
RIVIERA ELECTRIC | ER | P | 05/24/2007 | WALLS HARDLIDS---TE3.72 | THOMAS | THOMAS | | ER | P | 3482784 |
RIVIERA ELECTRIC | ER | P | 05/18/2007 | WALLS & HARDLIDS TE3.71 | THOMAS | THOMAS | | ER | P | 3482776 |
RIVIERA ELECTRIC | ER | P | 05/11/2007 | WALLS AND LIDS MARKED ON TE 3.71 OK | MATTHEW | MATTHEW | | ER | P | 3482767 |
RIVIERA ELECTRIC | ER | P | 05/07/2007 | WALLS & HARDLIDS TE 3.71 | THOMAS | THOMAS | | ER | P | 3482759 |
RIVIERA ELECTRIC | ER | P | 04/27/2007 | HARDLIDS ON LEVEL SIX MARKED ON APPROVED PLANS E 3.61 AND E 3.62 | MATTHEW | MATTHEW | | ER | P | 3482750 |
RIVIERA ELECTRIC | ER | P | 04/18/2007 | WALLS SIXTH FLOOR---SEE PLANS | THOMAS | THOMAS | | ER | P | 3482742 |
RIVIERA ELECTRIC | ER | P | 04/18/2007 | WALLS MARKED ON PLANS TE3.61 LEVEL 6 | MATTHEW | MATTHEW | | ER | P | 3482735 |
RIVIERA ELECTRIC | ER | P | 04/11/2007 | WALLS LEVEL 6 AREA A MARKED ON APPROVED PLANS TE3.61 | MATTHEW | MATTHEW | | ER | P | 3482727 |
COBB MECHANICAL CONTRACTORS, INC. | H= | C | 10/31/2007 | HVAC AND HWP FINALS. RECEIVED BALANCE REPORT. | LYNNS | LYNNS | | H= | C | 3482269 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 09/26/2007 | hwp final on 7th floor. | LYNNS | LYNNS | | H= | P | 3482261 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 09/26/2007 | hvac final on 7th floor pending balance report. | LYNNS | LYNNS | | HD | P | 3482253 |
COBB MECHANICAL CONTRACTORS, INC. | H= | R | 09/25/2007 | CALLED IN FOR A PLUMBING FINAL. | LYNNS | LYNNS | | H= | R | 3482246 |
COBB MECHANICAL CONTRACTORS, INC. | H= | P | 08/14/2007 | HVAC AND HWP FINALS ON 6TH FLOOR. | LYNNS | LYNNS | | H= | P | 3482239 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 06/06/2007 | FIRE/ SMOKE DAMPERS ON LEVELS 6 AND 7. MISSING 2 DAMPERS ON 6TH AND 1 DAMPER ON 7TH FLOORS. DRYER VENTS IN WALLS ON 7TH FLOOR OK TO COVER. | LYNNS | LYNNS | | HD | P | 3482231 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 05/25/2007 | 7TH FLOOR, NORTH AND SOUTH: 100 LB TEST OK OK TO INSULATE. | NANCY | NANCY | | HWP | P | 3482223 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 05/24/2007 | 7TH FLOOR. TEST ON 7TH FLOOR NORTH AND SOUTH. LOST TEST DURING INSPECTION. | NANCY | NANCY | | HWP | P | 3482216 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 05/23/2007 | TERMINAL BOXES ON LEVEL 6 AREA 1 OK. TERMINAL BOXES ON LEVEL 7 AREA 1 OK. LEVEL 7 AREA 2, TERMINAL BOXES AND LATERALS OK. OK TO INSULATE. ROUND INLET DUCT TO TERMINAL BOXES 7A14 AND 7A15 NOT INSTALLED YET. | NANCY | NANCY | | HD | P | 3482207 |
COBB MECHANICAL CONTRACTORS, INC. | HWP | P | 05/11/2007 | 6TH FLOOR: NEED TO RECHECK PRESSURE GAUGE ON MONDAY. STILL INFLATING LINES AFTER FIXING 4 LEAKS. OK TO START INSULATION. | NANCY | NANCY | | HWP | P | 3482200 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 04/24/2007 | LEVEL 7, AREA 1: ROUGH DUCT ON MAINS AND LATTERALS OK TO INSULATE. NEED TO SEE VAV'S AND F/S DAMPERS AND FRAMING. LEVEL 6, AREA1: F/S DAMPERS AS NOTED ON PLANS. | LYNNS | LYNNS | | HD | P | 3482192 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 04/17/2007 | LEVEL 6, FIRE/ SMOKE DAMPER FRAMING AS NOTED ON SHEET M3.61 AND LEVEL 7, ROUGH DUCT FOR CORE AND SHELL, OK TO INSULATE. | LYNNS | LYNNS | | HD | P | 3482184 |
COBB MECHANICAL CONTRACTORS, INC. | HD | P | 04/09/2007 | LEVEL 6, PPC WING OK TO INSULATE DOWN STREAM OF BOXES. | LYNNS | LYNNS | | HD | P | 3482176 |
COBB MECHANICAL CONTRACTORS, INC. | P= | C | 10/15/2007 | LEVEL 6 AND 7 TENANT FINISH ONLY | JEFF | JEFF | | P= | C | 3482507 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 09/26/2007 | LEVEL 7 AREA 1 COMPLETE, AREA 2 MISSING C/O'S X 3, NEED FLOOR DRAIN AT WASHING MACHINE OR VARIANCE AND COMPLETE DRINKING FOUNTAIN, REST OK | JEFF | JEFF | | P= | P | 3482501 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 08/13/2007 | LEVEL 6 COMPLETE | JEFF | JEFF | | P= | P | 3482490 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 08/09/2007 | LEVEL 6 AREA 1 AND 2, NEED 2" TRAP AT INDIRECT WASTE AT 6131 AND COMPLETE CONNECTIONS X 2, COMPLETE CONNECTION AT INDIRECT WASTE AT 6133, REST OK | JEFF | JEFF | | P= | P | 3482484 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | C | 06/19/2007 | LEVEL 6 AND 7 COMPLETE | JEFF | JEFF | | PTO | C | 3482476 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 06/18/2007 | DOMESTIC WATER PIPE COMPLETE, REPIPING DRINKING FOUNTAIN DWV LEVEL 7 AREA 1 | JEFF | JEFF | | PTO | P | 3482468 |
COBB MECHANICAL CONTRACTORS, INC. | P= | P | 06/08/2007 | LEVEL 2 COMPLETE BUT STILL HAVE ISSUES WITH CROSS CONNECTION PROTECTION AT CLINICAL SINKS WITH SEPERATELY LISTED COMPONANTS AND STERILIZERS REQUIRING CROSS CONNECTION PROTECTION BY OTHERS? | JEFF | JEFF | | P= | P | 3482460 |
COBB MECHANICAL CONTRACTORS, INC. | P= | R | 05/25/2007 | SEE F55875 | JEFF | JEFF | | P= | R | 3482453 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/18/2007 | MET WITH "RANDY", MAINTANENCE SUPERVISOR OF MEMORIAL HOSPITAL TO DISCUSS THE ADDING OF FIXTURES AND CROSS CONNECTIONS BY HOSPITALS PERSONEL.......WAS VERY CLEAR THAT THIS ISSUE NEEDS MUCH MORE ATTENTION!!! | JEFF | JEFF | | PTO | P | 3482446 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/17/2007 | LEVEL 7 AREA 2 DOMESTIC WATER COMPLETE LESS DRINKING AND ROOF HOSE BIBB, VERIFY CONDITIONED SPACE AT ROOF FOR FINAL | JEFF | JEFF | | PTO | P | 3482438 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/16/2007 | LEVEL 7 AREA 2 DWV COMPLETE | JEFF | JEFF | | PTO | P | 3482431 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/15/2007 | LEVEL 6 AREA 2 DRINKING FOUNTAIN WASTE AND VENT TO LEVEL 7 COMPLETE, LEVEL 6 DWV AREA 2 COMPLETE, LEVEL 7 AREA 2 WEST AND NORTH PODS WASTE AND VENT COMPLETE | JEFF | JEFF | | PTO | P | 3482423 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/14/2007 | LEVEL 6 AREA DWV COMPLETE LESS DRINKING FOUNTAINS | JEFF | JEFF | | PTO | P | 3482415 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/11/2007 | LEVEL 6 AREA 2 NE POD DWV OK | JEFF | JEFF | | PTO | P | 3482406 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/10/2007 | LEVEL 5 "D" NORTH DWV OK. | SCOTT | SCOTT | | PTO | P | 3482399 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/09/2007 | LEVEL 5 AREA "C" DWV ROUGH-IN ONLY. LEVEL 7 A&B DOMESTIC WATER, EXCLUDING MOPSINK AREA. | SCOTT | SCOTT | | PTO | P | 3482391 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/08/2007 | LEVEL 4 UNIT C CENTER DRAIN AND WASTE. | SCOTT | SCOTT | | PTO | P | 3482383 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/07/2007 | S.S.---LEVEL 4 AREA "D" 6" TRUNK AND BRANCHS | LYNNIE | LYNNIE | | PTO | P | 3482375 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/04/2007 | LEVEL 7 AREA 1 DWV COMPLETE | JEFF | JEFF | | PTO | P | 3482370 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/03/2007 | LEVEL 7 AREA 1 POD A DWV COMPLETE | JEFF | JEFF | | PTO | P | 3482362 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/02/2007 | LEVEL 6 AREA 1 DWV TO LEVEL 7 COMPLETE | JEFF | JEFF | | PTO | P | 3482354 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 05/01/2007 | LEVEL 6 DWV TO LEVEL 7 AREA 1 COMPLETE | JEFF | JEFF | | PTO | P | 3482346 |
COBB MECHANICAL CONTRACTORS, INC. | P16 | C | 04/30/2007 | DISCUSSED PROBLEMS WITH MARK ABOUT NOT BEING READY FOR INSPECTIONS BEING CALLED IN...............ONE TRIP USED...WAIVED TRIP FEE..NOT READY | JEFF | JEFF | | P16 | C | 3482338 |
PCL CONSTRUCTION SERVICES, INC | PTO | P | 04/27/2007 | LEVEL 5 TO 6 POD B 4" STACK AT COLUMN C2, LEVEL 6 TO 7 4" WASTE ABOVE MENS RESTROOM 6138 | JEFF | JEFF | | PTO | P | 3482704 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/26/2007 | LEVEL 4 TO 5 AREA 1 POD C WASTE OK | JEFF | JEFF | | PTO | P | 3482330 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/20/2007 | NO MORE INSPECTIONS FOR INTERIOR FINISH UNTIL ISSUES RESOLVED FOR CORE AND SHELL RESOLVED PER JIM VERNON, LEVEL 4 TO LEVEL 5 AREA 1 POD B(CENTER AREA) WASTE OK, WILL NEED TO REINSPECT FOR SUPPORT ISSUES THROUGHOUT | JEFF | JEFF | | PTO | P | 3482323 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/19/2007 | LEVEL 6 TO LEVEL 7 SANITARY VENTS POD A OK | JEFF | JEFF | | PTO | P | 3482314 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/18/2007 | LEVEL 6 WASTE TO LEVEL 7 AREA 1 SOUTH AND WEST PODS ONLY, WASTE ONLY, SEE PRD NOTES AT F55875 4/18/07 | JEFF | JEFF | | PTO | P | 3482305 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/17/2007 | LEVEL 5 TO 6 AREA 1 POD A WASTE OK | JEFF | JEFF | | PTO | P | 3482295 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/16/2007 | LEVEL 4 TO LEVEL 5 AREA 1 POD A WASTE OK | JEFF | JEFF | | PTO | P | 3482285 |
COBB MECHANICAL CONTRACTORS, INC. | PTO | P | 04/12/2007 | CONTRACTOR TO PROVIDE COPY OF APPROVED PLANS ON SITE(MEANING INSIDE BUILDING) PRIOR TO NEXT INSPECTION, CONTRACTOR WILL NOT BE APPROVED TO CONTINUE OR COVER UNTIL ISSUES AT F55875 HAVE BEEN RESOLVED, CONTRACTOR CONTINUING AT OWN RISK, WATER PIPE FROM 5TH FLOOR ISOLATION VALVES AND 6TH FLOOR AREA 1 COMPLETE TO 7TH FLOOR ISOLATION VALVES AS PER APPROVED PLANS FOR TI FINISH...... | JEFF | JEFF | | PTO | P | 3482277 |
OTIS ELEVATOR COMPANY | V= | C | 11/28/2007 | | TOM | TOM | | V= | C | 3482515 |