COLARELLI CONSTRUCTION, INC. | B= | C | 10/30/2008 | | CHRISM | CHRISM | | B= | C | 3762920 |
COLARELLI CONSTRUCTION, INC. | B= | P | 08/30/2008 | Temp CO: NEED TO SWITCH OUT RTU MOTORS | KIM | KIM | | B= | P | 3717255 |
COLARELLI CONSTRUCTION, INC. | B= | P | 07/30/2008 | FIRE COMPLETE, ELECTRIC FINAL PARTIAL STATUS | CHRISM | CHRISM | | B= | P | 3717135 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 07/18/2008 | FIREPROTECTION OF COLUMNS COMPLETE | CHRISM | CHRISM | | BSP | P | 3710722 |
OLSON PLUMBING & HEATING COMPANY | BSP | T | 07/16/2008 | PAID (REC#816584) ADDITIONAL PLAN REVIEW TIME: $50 From: TCRIPPEN new splice page added drain and roof drain | TCRIPPEN | TCRIPPEN | | BSP | T | 3708864 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 07/14/2008 | COLUMN FIREPROTECTION FOR SURGERY SUITE AND SHAFT SUPPORT OK ALL BUT AT TWO COLUMNS ON SECOND FLOOR IN UNFINISHED SPACE AND ONE COLUMN IN WALLGREENS SUITE, WELD AND STRUCTURAL STEEL CERTIFICATIONS ON FILE, SPRAY APPLIED FIRECOATING INSPECTION REPORTS ON FILE FOR MECH SHAFT AND WOMANS SURGERY CENTER | CHRISM | CHRISM | | BSP | P | 3707368 |
OLSON PLUMBING & HEATING COMPANY | BSP | T | 07/02/2008 | PAID (REC#814683) ADDITIONAL PLAN REVIEW TIME: $100 From: TCRIPPEN under ground only | TCRIPPEN | TCRIPPEN | | BSP | T | 3702312 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 06/16/2008 | | ANDY | ANDY | | BFR | P | 3692997 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 06/16/2008 | ABOVE GRID 4TH FLOOR AND MECH. SHAFT OK | ANDY | ANDY | | BSP | P | 3692987 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 06/13/2008 | FRAMING IN LINK BRIDGE OK WILL NEED WELD CERT, TWO HR WALL AT LINK END OK TO ROCK SECOND LAYER, ABOVE GRID OK CORRIDORS SECOND AND THIRD FLOORS,FOUTH FLOOR CORRIDOR ONE HOUR WALL PENETRATIONS NEED TO BE FIRECHAULKED, BACK ROCK FIRE EXT BOXES,ceiling framing at entry vestibule and porticoture ok to rock after elect insp. | CHRISM | CHRISM | | BFR | P | 3691681 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 05/07/2008 | FRAMING FOR FIREPROTECTION OF COLUMNS AT SHAFT SUPPORT | CHRISM | CHRISM | | BFR | P | 3672123 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 05/06/2008 | ELEVATOR SHAFT FRONTS COMPLETE, MECH SHAFT ON SECOND FLOOR CORE BOARD COMPLETE, MECH SHAFT SUPPORT COMUMN PROTECTION ON SECOND FLOOR FRAMING OK | CHRISM | CHRISM | | BSP | P | 3671398 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 05/01/2008 | ELEVATOR SHAFT FRONT CORE BOARD OK | CHRISM | CHRISM | | BSP | P | 3669264 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 04/30/2008 | elevator shaft front core board ok 1st, 2nd,3rd floors ok,ok 2hr column protection in bathrooms 1st,2nd,3rd, 2hr columns on third floor for shaft support require putty packs in electrical boxes and check firespray at above grid insp. | CHRISM | CHRISM | | BSP | P | 3668420 |
COLARELLI CONSTRUCTION, INC. | BBB | C | 04/30/2008 | trash encloser walls | CHRISM | CHRISM | | BBB | C | 3668411 |
COLARELLI CONSTRUCTION, INC. | BSP | T | 04/22/2008 | PAID (REC#803780) ADDITIONAL PLAN REVIEW TIME: $50.000 From: RICH spliced revised G101, G102, SHOWING STRUCTURAL SUPPORT COMPONETS FOR SHAFT SUPPORT 2HR | RICH | RICH | | BSP | T | 3586095 |
COLARELLI CONSTRUCTION, INC. | BLA | C | 04/21/2008 | | CHRISM | CHRISM | | BLA | C | 3586104 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 04/17/2008 | FRAMING AT FRONT PORTACOTURE OK, WENT OVER FIRE PROTECTION OF COLUMNS AND BEAMS FOR SHAFT SUPPORT FIRST FLOOR ALSO COLUMN PROTECTION FOR SURGICAL CENTER. FIRE PROTECTIVE PLANS TO BE SUBMITTED TO PLAN CHECK. | CHRISM | CHRISM | | BFR | P | 3586367 |
COLARELLI CONSTRUCTION, INC. | BIN | P | 04/17/2008 | FIRST FLOOR NORTH HALF EXTERIOR WALL INSULATION AND VAPOR BARRIER OK | CHRISM | CHRISM | | BIN | P | 3586360 |
COLARELLI CONSTRUCTION, INC. | BIN | P | 03/25/2008 | SHELL INSULATION ON LEVEL 2 OK | ANDY | ANDY | | BIN | P | 3586354 |
COLARELLI CONSTRUCTION, INC. | BSP | T | 03/25/2008 | PAID (REC#798103)ADDITIONAL PLAN REVIEW TIME: $50.000 From: MICHAEL Splice two hour floor detail | MICHAELA | MICHAELA | | BSP | T | 3586346 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 03/14/2008 | FIRESAFE AT SECOND FLOOR EXTERIOR SLAB EDGE OK | CHRISM | CHRISM | | BSP | P | 3586340 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 03/13/2008 | FIRESAFE OK AT SLAB EDGE SECOND FLOOR | CHRISM | CHRISM | | BSP | P | 3586331 |
COLARELLI CONSTRUCTION, INC. | BLA | P | 03/11/2008 | OK SOUTH AND EAST SIDE TO FRONT ENTRY | CHRISM | CHRISM | | BLA | P | 3586324 |
COLARELLI CONSTRUCTION, INC. | BFI | C | 03/10/2008 | FOUNDATION INSULATION COMPLETE, UNDERSLAB | CHRISM | CHRISM | | BFI | C | 3586317 |
COLARELLI CONSTRUCTION, INC. | BIN | P | 03/07/2008 | VAPOR BARRIER AND INSULATION COMPLETE AT THIRD FLOOR EXTERIOR | CHRISM | CHRISM | | BIN | P | 3586311 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 03/03/2008 | 3rd floor - east half firesafe at floor okay | TODDS | TODDS | | BSP | P | 3586303 |
COLARELLI CONSTRUCTION, INC. | BLA | P | 02/28/2008 | WEST ELEVATION OK | CHRISM | CHRISM | | BLA | P | 3586295 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 02/26/2008 | FIRESAFE AT FLOOR EDGE THIRD FLOOR WEST HALF OK | CHRISM | CHRISM | | BSP | P | 3586289 |
COLARELLI CONSTRUCTION, INC. | BIN | P | 02/26/2008 | INSULATION AND VAPOR BARRIER FOURTH FLOOR EAST HALF | CHRISM | CHRISM | | BIN | P | 3586283 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 02/21/2008 | FIRESAFE AT SLAB EDGE OK FROM EAST STAIR TOWER TO "D" WEST WALL | CHRISM | CHRISM | | BSP | P | 3586278 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 02/15/2008 | FIRESAFING STARTED AT FOURTH FLOOR NORTH WALL OK, INSIDE LAYER OF SHAFT LINER OK AT CENTERAL SHAFT THIRD AND FOURTH FLOORS THREE SIDES ONLY | CHRISM | CHRISM | | BSP | P | 3586270 |
COLARELLI CONSTRUCTION, INC. | BLA | P | 02/12/2008 | LATH ON NORTH AND EAST WALLS FROM GRID LINE E-1 TO G-5 OK | CHRISM | CHRISM | | BLA | P | 3586262 |
COLARELLI CONSTRUCTION, INC. | BFI | P | 02/07/2008 | UNDERSLAB INSULATION AT SOUTH SIDE ELECTRICAL ROOM, AND NORTH HALF OF BUILDING OK | CHRISM | CHRISM | | BFI | P | 3586257 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 01/29/2008 | EXTERIOR WALL FRAMING OK TO COVER OUTSIDE, WELD CERT REQUIRED BY FINAL, NO FIRESAFE DONE AT THIS TIME | CHRISM | CHRISM | | BFR | P | 3586247 |
COLARELLI CONSTRUCTION, INC. | BSP | T | 01/22/2008 | PAID (REC#789759)ADDITIONAL PLAN REVIEW TIME: $50.000 From: MICHAEL Splice in g101-102 for sprinklers in electrical room | MICHAELA | MICHAELA | | BSP | T | 3586239 |
OLSON PLUMBING & HEATING COMPANY | BSP | T | 01/16/2008 | PAID (REC#790216): ADDITIONAL PLAN REVIEW TIME: $50.000 From: TCRIPPEN moved gas line | TCRIPPEN | TCRIPPEN | | BSP | T | 3585822 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 01/09/2008 | EXTERIOR WALL FRAMING OK, WELD INSPECTION REPORT REQUIRED, OK TO COVER | CHRISM | CHRISM | | BSP | P | 3586228 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 12/03/2007 | EXTERIOR WALL FRAMMING FROM GRID LINE D-1 TO G-5 OK TO COVER OUTSIDE, WELD INSPECTION RESULTS BY FINAL | CHRISM | CHRISM | | BFR | P | 3586220 |
OLSON PLUMBING & HEATING COMPANY | BSP | T | 11/29/2007 | PAID (REC#782744): ADDITIONAL PLAN REVIEW TIME: $50.000 From: TCRIPPEN rerouted roof drain see clouds | TCRIPPEN | TCRIPPEN | | BSP | T | 3585814 |
OLSON PLUMBING & HEATING COMPANY | BSP | T | 11/15/2007 | PAID (REC#781035): ADDITIONAL PLAN REVIEW TIME: $50.000 FROM: TCRIPPEN NEW PAGE WITH ADDED PSI AND GAS PIPE LENGTH | TCRIPPEN | TCRIPPEN | | BSP | T | 3585806 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 09/11/2007 | THIRD PILASTER FOR LINK BRIDGE | CHRISM | CHRISM | | BFN | P | 3586207 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 09/10/2007 | SECOND PILLASTER FOR LINK BRIDGE | CHRISM | CHRISM | | BFN | P | 3586200 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 09/06/2007 | FIRST PILASTER FOR BRIDGE TO HOSPITAL | CHRISM | CHRISM | | BFN | P | 3586193 |
COLARELLI CONSTRUCTION, INC. | BFI | P | 08/30/2007 | VERTICLE INSULATION AT SOUTH AND EAST WALLS | CHRISM | CHRISM | | BFI | P | 3586185 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 08/30/2007 | SMALL AREA AT STAIR TOWER OK TO POUR, | CHRISM | CHRISM | | BFN | P | 3586178 |
COLARELLI CONSTRUCTION, INC. | BFI | P | 08/27/2007 | WEST WALL VERTICLE INSULATION OK | CHRISM | CHRISM | | BFI | P | 3586165 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 08/27/2007 | SOUTH AND EAST WALLS OK, EUFRE GROUND IN SOUTH WALL TOM F. TO CHECK | CHRISM | CHRISM | | BFN | P | 3586159 |
COLARELLI CONSTRUCTION, INC. | BFT | P | 08/21/2007 | CAISSON DRILL LOG ON FILE, FOUNDATION INSULATION AT NORTH AND EAST WALLS SEE PAGE S101 IN BLUE | CHRISM | CHRISM | | BFT | P | 3586151 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 08/21/2007 | WEST AND SOUTH WALLS, SEE PAGE S101 MARKED IN GREEN | CHRISM | CHRISM | | BFN | P | 3586143 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 08/16/2007 | WALL STEEL OK - SEE RBD PAGE S101 FOR LOCATION | MICHAELA | MICHAELA | | BFN | P | 3586136 |
COLARELLI CONSTRUCTION, INC. | BFT | P | 08/09/2007 | PAD FOR CENTER ELEVATOR AND STAIR TOWER OK | CHRISM | CHRISM | | BFT | P | 3586128 |
COLARELLI CONSTRUCTION, INC. | BFN | P | 08/02/2007 | GRADE BEAM AT SOUTH STAIR TOWER OK | CHRISM | CHRISM | | BFN | P | 3586119 |
COLARELLI CONSTRUCTION, INC. | BFT | P | 08/02/2007 | NEED STAMPED CAISSON LOG | CHRISM | CHRISM | | BFT | P | 3586111 |
KENNY ELECTRIC SERVICE, INC. | E= | C | 10/29/2008 | | GARYL | GARYL | | E= | C | 3762662 |
KENNY ELECTRIC SERVICE, INC. | E= | P | 07/18/2008 | NEED TO CONFRIM AMPS ON RTU'S AND IDENTIFY DISCONNECTS | GARYL | GARYL | | E= | P | 3710590 |
KENNY ELECTRIC SERVICE, INC. | ER | C | 07/18/2008 | | GARYL | GARYL | | ER | C | 3710588 |
KENNY ELECTRIC SERVICE, INC. | EP | P | 07/03/2008 | TRANSFORMERS 4 FLOORS CORE AND SHELL GROUNDING AND TERMINATION | GARYL | GARYL | | EP | P | 3703078 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 07/03/2008 | CEILINGS COMPLETE | GARYL | GARYL | | ER | P | 3703071 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 06/12/2008 | 2ND, 3RD AND 4TH FLOOR COMMON CORRIDOR CEILINGS-----------------ALL OK EXCEPT GRID WIRE IN FRONT OF DOOR ON VAV ON 2ND AND 3RD FLOORS--------------ALL THE CORRIDOR VAV'S ARE 3PH 480-VOLT 15-AMP.NEED TO CHECK BREAKERS ON LATER INSPECTION------------------ | DEAN | DEAN | | ER | P | 3691421 |
KENNY ELECTRIC SERVICE, INC. | EUG | P | 05/29/2008 | pipe to the west two pole lights | ARNOLD | ARNOLD | | EUG | P | 3683237 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 04/17/2008 | | MIKEC | MIKEC | | ER | P | 3586088 |
KENNY ELECTRIC SERVICE, INC. | ES | C | 04/02/2008 | COMMERCIAL SERVICE: 2500 AMP 4/W 277/480V KENNY ELECTRIC | TIMA | TIMA | | ES | C | 3586080 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 02/13/2008 | 2ND, 3RD, 4TH FLOORS, CORRIS, CORE AND SHELL BATHROOMS WALLS ONLY | GARYL | GARYL | | ER | P | 3586071 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 01/10/2008 | ROOF OF 4TH FLOOR | GARYL | GARYL | | ER | P | 3586064 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 01/04/2008 | CEILING OF 4TH FLOOR FROM THE ROOF | GARYL | GARYL | | ER | P | 3586056 |
KENNY ELECTRIC SERVICE, INC. | EST | R | 11/29/2007 | install brass tag---bond gutter to neutral---install bond screws in disconnect---bond nipples & use correct size wire | THOMAS | THOMAS | | EST | R | 3586048 |
KENNY ELECTRIC SERVICE, INC. | ESL | P | 11/08/2007 | 2ND FLOOR PVC, CORE/SHELL BRANCH CIRCUITS ONLY | GARYL | GARYL | | ESL | P | 3586039 |
KENNY ELECTRIC SERVICE, INC. | EUG | P | 11/08/2007 | PVC FOR CORE/SHELL BRANCH CIRCUITS ONLY | GARYL | GARYL | | EUG | P | 3586032 |
KENNY ELECTRIC SERVICE, INC. | ER | R | 11/05/2007 | PVC BEING RAN IN SLAB FOR MEDICAL CARE FACILITY | GARYL | GARYL | | ER | R | 3586024 |
KENNY ELECTRIC SERVICE, INC. | ESL | P | 10/17/2007 | THIRD FLOOR DECK | THOMAS | THOMAS | | ESL | P | 3586016 |
KENNY ELECTRIC SERVICE, INC. | ESL | P | 10/11/2007 | FOURTH FLOOR DECK | THOMAS | THOMAS | | ESL | P | 3586007 |
KENNY ELECTRIC SERVICE, INC. | EUG | P | 09/24/2007 | SEE PLANS | MIKEC | MIKEC | | EUG | P | 3586000 |
KENNY ELECTRIC SERVICE, INC. | EUG | P | 09/20/2007 | 8 POLE LIGHT BASES, PVC STUBBED OUT AT EACH OF 6 BASES AND PVC TIEING 2 FAR EAST BASES TOGETHER--------------MARKED ON PLANS--------------- | DEAN | DEAN | | EUG | P | 3585993 |
OTIS ELEVATOR COMPANY | HE= | C | 07/29/2008 | both cars complete by tom e | JOHNW | JOHNW | | HE= | C | 3715587 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | C | 07/22/2008 | RECEIVED BALANCE REPORT. TURNED IN TO SCANNING. | LYNNS | LYNNS | | H= | C | 3711768 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 07/14/2008 | GAS FINAL. | LYNNS | LYNNS | | H= | C | 3707699 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 07/01/2008 | INSPECTION OF REGISTERS IN BRIDGE LINK ALL OK. SEE SHEET M104. FINAL HVAC ON SHELL AND CORE OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 3701318 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 06/27/2008 | INSPECTION OF LOBBY CORRIDORS, BATHROOMS AND JANITOR'S CLOSET, LEVEL 1, CORE AND SHELL, ALL OK. SEE SHEET M101. | NANCY | NANCY | | HD | P | 3699657 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 06/24/2008 | ROUGH DUCT FOR BRIDGE LINK. | LYNNS | LYNNS | | HD | P | 3697756 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 06/13/2008 | HVAC FINAL FOR 2ND FLOOR ELEVATOR LOBBY, BATH ROOMS AND CORRIDOR. OOK FOR TILE. | LYNNS | LYNNS | | H= | P | 3692188 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HRP | P | 06/13/2008 | 2- 300# TESTS ON REFRIGERATION LINES FOR TWO SPLIT SYSTEMS, 4TH AND 2ND FLOORS OK. | LYNNS | LYNNS | | HRP | P | 3692185 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 06/06/2008 | PARTIAL FINAL FOR BATH ROOMS ON 2ND FLOOR. SEE M101. | LYNNS | LYNNS | | H= | P | 3688383 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 06/02/2008 | PARTIAL FINAL FOR CORRIDOR ON 4TH LEVEL. | LYNNS | LYNNS | | H= | P | 3685356 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 05/27/2008 | 3RD FLOOR ELEVATOR LOBBY AND BATH ROOMS OK. | LYNNS | LYNNS | | H= | P | 3682058 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 05/01/2008 | 1ST FLOOR, SHEET M.101 FPB-101 ROUGH DUCT, 2ND FLOOR, SHEET M.102 SHAFT TIE-INS OK, 4TH FLOOR, SHEET M.104, FPB-402 TO BRIDGE LINK ROUGH DUCT OK. | LYNNS | LYNNS | | HD | P | 3669646 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 04/28/2008 | ROUGH DUCT ON 6" ROUND IN HALLWAY ON 2ND FLOOR. | LYNNS | LYNNS | | HD | P | 3667282 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HRP | P | 04/14/2008 | 4- 350# TESTS ON LINE SETS OFF CU-3 AND 4 OK. | LYNNS | LYNNS | | HRP | P | 3586426 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 04/02/2008 | FIRE/SMOKE DAMPERS ON 2ND FLOOR, WWEST SIDE OF SHAFT OK TO COVER. | LYNNS | LYNNS | | HD | P | 3586420 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 04/01/2008 | FIRE/SMOKE DAMPERS ON THIRD FLOOR WEST SIDE OF SHAFT OK TO COVER. | LYNNS | LYNNS | | HD | P | 3586414 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 03/17/2008 | ROUGH DUCT FOR ELEVATOR LOBBY AND 2- BATH ROOMS ON 2ND FLOOR. | LYNNS | LYNNS | | HD | P | 3586408 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HRP | P | 03/06/2008 | 4- 350# TESTS ON REFRIGERATION LINES TO CU-1 AND CU-2 OK. | LYNNS | LYNNS | | HRP | P | 3586402 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 03/03/2008 | CORE AND SHELL.. ROUGH DUCT ABOVE HARD LIDS 3RD FLOOR BATH ROOMS ACCROSS FROM ELEVATORS OK. | JON | JON | | HD | P | 3586395 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 01/30/2008 | FIRE/SMOKE DAMPER FRAMING IN RISER SHAFT OK ON EAST, NORTH AND SOUTH SIDES ON ALL FLOORS. | LYNNS | LYNNS | | HD | P | 3586388 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 01/22/2008 | FIRE/SMOKE DAMPER FRAMING FOR RISER SHAFTS, | LYNNS | LYNNS | | HD | P | 3586381 |
OLSON PLUMBING & HEATING COMPANY | HC | C | 01/11/2008 | OK FOR METER. | LYNNS | LYNNS | | HC | C | 3585846 |
OLSON PLUMBING & HEATING COMPANY | HI | P | 01/11/2008 | 60# TEST ON HOSES FOR TEMP. HEAT. | LYNNS | LYNNS | | HI | P | 3585838 |
OLSON PLUMBING & HEATING COMPANY | HI | P | 01/08/2008 | 60# TEST ON ELEVATE PRESSURE TEMP. MANIFOLD OK. | LYNNS | LYNNS | | HI | P | 3585830 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 07/21/2008 | Certificate of potable water received | KYE | KYE | | P= | C | 3711068 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 07/17/2008 | PENDING POTABLE WATER CERTIFICATE--SPLICES ARE NOW ON PLANS | LYNNIE | LYNNIE | | P= | P | 3710154 |
OLSON PLUMBING & HEATING COMPANY | P= | T | 07/16/2008 | PAID (REC#816762): STILL NO APPROVED PLANS IN SIGHT--REST OK | LYNNIE | LYNNIE | | P= | T | 3709392 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 07/16/2008 | | LYNNIE | LYNNIE | | PTO | C | 3709391 |
OLSON PLUMBING & HEATING COMPANY | P= | R | 07/15/2008 | NOT READY FOR A FINALS | LYNNIE | LYNNIE | | P= | R | 3708520 |
OLSON PLUMBING & HEATING COMPANY | PB+ | R | 07/09/2008 | (PB+ Receipt #814872) NO RE RE RE-APPROVED PLANS ON SITE--ADDED 1 NEW SINK IN ROOM 110 PCT AND 1 NEW BASIN IN ROOM 127 BIO-MED | LYNNIE | LYNNIE | | PB+ | R | 3705178 |
OLSON PLUMBING & HEATING COMPANY | PB+ | P | 07/08/2008 | GET DRAWINGS TO REFLECT WORK--WORK NOT TO PLANS AT THIS TIME---COMBO DRAIN AND VENT SYSTEM ON LINE 3.5 AT COLUMN B REQS A VENT IN THE HORIZONTAL PORTION | LYNNIE | LYNNIE | | PB+ | P | 3704408 |
OLSON PLUMBING & HEATING COMPANY | PRD | C | 06/25/2008 | CANT FIND APPROVED PLANS--DID ROOF DRAIN GET REVISED?--IF NOT -- BY FINALS | LYNNIE | LYNNIE | | PRD | C | 3698313 |
OLSON PLUMBING & HEATING COMPANY | PTO | L | 05/14/2008 | WRONG PERMIT CALLED IN | LEE | LEE | | PTO | L | 3675748 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/26/2008 | DOMESTIC WATER PIPE AT LEVEL 1 RESTROOMS OK | JEFF | JEFF | | PTO | P | 3585984 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/25/2008 | LEVEL 1 RESTROOM DWV OK, DWV ONLY | JEFF | JEFF | | PTO | P | 3585976 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 02/19/2008 | VTR AT MAIN BATHROOMS OK | JEFF | JEFF | | PTO | P | 3585969 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 02/12/2008 | WASTE AND VENT LEVEL 1 THROUGH SECOND FLOOR OK, SECOND FLOOR RESTROOMS OK | JEFF | JEFF | | PTO | P | 3585962 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 02/11/2008 | 3RD FLOOR OK, DOMESTIC WATER TRUNKLINES OK | JEFF | JEFF | | PTO | P | 3585954 |
OLSON PLUMBING & HEATING COMPANY | PTO | R | 12/17/2007 | CAN NOT INVERT WYE BRANCH, LOW TEST, DWV ONLY AT 3RD FLOOR RESTROOMS | JEFF | JEFF | | PTO | R | 3585946 |
OLSON PLUMBING & HEATING COMPANY | PRD | P | 12/04/2007 | WEAT SIDE ROOF DRAINS OK, ROOF DRAINS AT CORRIDOR TO MAIN HOSPITAL REMAIN | JEFF | JEFF | | PRD | P | 3585938 |
OLSON PLUMBING & HEATING COMPANY | PRD | P | 12/03/2007 | UNDERGROUND COMPLETE, EAST SIDE COMPLETE, WEST SIDE RISERS X 2 OK TO 3RD FLOOR | JEFF | JEFF | | PRD | P | 3585930 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 11/27/2007 | | JEFF | JEFF | | PB | C | 3585922 |
OLSON PLUMBING & HEATING COMPANY | PRD | R | 11/27/2007 | APPROVED PLANS STILL NOT REVISED TO SHOW ACTUAL WORK! | JEFF | JEFF | | PRD | R | 3585915 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 11/27/2007 | FUTURE WASTE AND VENT STACKS ONLY AT NE SE SW COLUMNS THROUGH ROOF TEST OK | JEFF | JEFF | | PTO | P | 3585906 |
OLSON PLUMBING & HEATING COMPANY | PRD | R | 11/20/2007 | NO APPROVED PLANS ON SITE, INSPECTION RESULTS PENDING APPROVED PLANS | JEFF | JEFF | | PRD | R | 3585898 |
OLSON PLUMBING & HEATING COMPANY | PTO | R | 11/20/2007 | NO APPROVED PLANS ON SITE, INSPECTION RESULTS PENDING APPROVED PLANS | JEFF | JEFF | | PTO | R | 3585892 |
OLSON PLUMBING & HEATING COMPANY | PRD | P | 11/01/2007 | NORTH 6" STORM FROM 2' INSIDE AT TEST TEE OK, CONTRACTOR IN PROCESS REVISING PLANS | JEFF | JEFF | | PRD | P | 3585877 |
OLSON PLUMBING & HEATING COMPANY | P16 | C | 10/30/2007 | VARIANCE AS WRITTEN: 6071 EAST WOODMEN ROAD – AARON BYBEE, RTA ARCHITECTS, REQUESTS A VARIANCE TO SECTION 413, 2000 UNIFORM PLUMBING CODE, AS AMENDED BY SECTION RBC306.4.9, 2005 PIKES PEAK REGIONAL BUILDING CODE, TO ALLOW LESS THAN THE REQUIRED NUMBER OF PLUMBING FIXTURES IN A NEW STRUCTURE. AARON BYBEE APPEARED. MR. BYBEE SAID THAT THE BUILDING IS FOUR STORIES AND APPROXIMATELY 84,000 SQUARE FEET AT CORE AND SHELL. HE SAID THAT THEY WOULD LIKE TO ALLOW FIVE TOILETS AND | KYE | KYE | | P16 | C | 3585869 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 10/29/2007 | sanitary waste ok, need clarification on engineers comment of 9 of 17 fixtures to be installed on field set of approved plans, has variance for limited number of fixtures? | JEFF | JEFF | | PB | P | 3585862 |
OLSON PLUMBING & HEATING COMPANY | PB | L | 10/25/2007 | CUSTOMER WAS NOT READY WHEN CALLED AT 9:15 | DARYL | DARYL | | PB | L | 3585854 |
COLARELLI CONSTRUCTION, INC. | V= | P | 05/01/2008 | # 1 ELEVATOR ONLY FOR CONSTRUCTION ONLY | JOHNW | JOHNW | | V= | P | 3669881 |