ROBINSON CONSTRUCTION, LLC. | B= | P | 04/19/2008 | Temp CO: NEED FINALS COMPLETED ON MECHANICAL, PLUMBING & FIRE | MINDY | MINDY | | B= | P | 3635190 |
ROBINSON CONSTRUCTION, LLC. | B= | C | 04/09/2008 | | JOHNP | JOHNP | | B= | C | 3635249 |
ROBINSON CONSTRUCTION, LLC. | B= | P | 03/20/2008 | NEED FINALS COMPLETED ON MECHANICAL, PLUMBING & FIRE | JOHNP | JOHNP | | B= | P | 3635242 |
ROBINSON CONSTRUCTION, LLC. | BSP | P | 03/17/2008 | | JOHNP | JOHNP | | BSP | P | 3635235 |
ROBINSON CONSTRUCTION, LLC. | BSP | P | 03/13/2008 | CHECK TO MAKE SURE THE BUSINESS IS NOT OPEN | JOHNP | JOHNP | | BSP | P | 3635226 |
ROBINSON CONSTRUCTION, LLC. | BSP | P | 03/07/2008 | ABOVE GRID OK | JOHNP | JOHNP | | BSP | P | 3635218 |
ROBINSON CONSTRUCTION, LLC. | BSP | P | 02/25/2008 | CEILING GRID IN BREAKROOM | JOHNP | JOHNP | | BSP | P | 3635211 |
ROBINSON CONSTRUCTION, LLC. | BIN | C | 02/05/2008 | | JOHNP | JOHNP | | BIN | C | 3635203 |
ROBINSON CONSTRUCTION, LLC. | BFR | P | 01/24/2008 | WALLS OK | JOHNP | JOHNP | | BFR | P | 3635195 |
MEYER ELECTRIC | E= | C | 03/19/2008 | | TIMA | TIMA | | E= | C | 3635115 |
MEYER ELECTRIC | ER | C | 03/06/2008 | CEILINGS OK | TIMA | TIMA | | ER | C | 3635108 |
MEYER ELECTRIC | ES | C | 03/05/2008 | COMMERCIAL SERVICE: 2- 200 AMP 3 PHASE SERVICES FED FROM METER STACK BY MEYER ELECTRIC: METER SET AT 4323 FOR TEMP- NEED METER SET FOR 4323B | MATTHEW | MATTHEW | | ES | C | 3635100 |
MEYER ELECTRIC | ER | P | 01/23/2008 | WALLS ONLY | GARYL | GARYL | | ER | P | 3635093 |
O.M.A.G.M., INC. | H= | C | 03/20/2008 | GAS FINAL. | LYNNS | LYNNS | | H= | C | 3635154 |
GOLD STAR HEATING & COOLING | H= | C | 03/20/2008 | RECEIVED BALANCE REPORT. | LYNNS | LYNNS | | H= | C | 3635182 |
O.M.A.G.M., INC. | H= | P | 03/19/2008 | BTU CAPACITY OF FLEX GAS CONNECTORS TOO SMALL FOR ROOF TOP UNITS. | NANCY | NANCY | | H= | P | 3635147 |
GOLD STAR HEATING & COOLING | H= | P | 03/04/2008 | NEED BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3635174 |
GOLD STAR HEATING & COOLING | H= | P | 02/29/2008 | NEED TO REPAIR DUCT INSULATION THROUGH OUT, REPLACE GRILLES BACK IN CEILING, NEED BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3635167 |
O.M.A.G.M., INC. | HC | C | 01/24/2008 | OK FOR METER. | NANCY | NANCY | | HC | C | 3635139 |
O.M.A.G.M., INC. | HI | C | 01/24/2008 | 10 LB TEST OK. GAS LINE INSTALLED AS PER PRINTS. | NANCY | NANCY | | HI | C | 3635129 |
O.M.A.G.M., INC. | HI | P | 01/24/2008 | 10 LB TEST OK. NEED ACCESS TO ROOF TO VERIFY INSTALLATION IS TO PLANS. | NANCY | NANCY | | HI | P | 3635122 |
GOLD STAR HEATING & COOLING | HD | P | 01/17/2008 | ROUGH DUCT OK TO INSULATE. NOTE: MUA FOR DRYER WILL BE IN CEILING OF CLOSET. | LYNNS | LYNNS | | HD | P | 3635160 |
HOGAN MECHANICAL, INC. | P= | C | 04/08/2008 | | LYNNIE | LYNNIE | | P= | C | 3635345 |
HOGAN MECHANICAL, INC. | P= | P | 03/18/2008 | 10GAL ELECTRIC WATER HEATER WILL NOT PROVIDE THE MIN 105* REQMT TO ALL 11-SINKS 3-LAVS 1-MOP SINK AND 1-AUTOMATIC CLOTHES WASHING MACHINE--RBC SEC413.11--REST OK | LYNNIE | LYNNIE | | P= | P | 3635338 |
HOGAN MECHANICAL, INC. | PTO | C | 01/16/2008 | BY FINALS WE WILL NEED A LETTER TO SUB CPVC FOR TYPE L COPPER PER PLANS----RCP-1--CHECK FOR A CLOCK IN MECH ROOM OR LEAVE CEILING TILES OUT THROUGHOUT FOR INPECTION OF INSULATION | LYNNIE | LYNNIE | | PTO | C | 3635329 |
HOGAN MECHANICAL, INC. | PB | C | 01/16/2008 | | LYNNIE | LYNNIE | | PB | C | 3635322 |
HOGAN MECHANICAL, INC. | PB | P | 12/21/2007 | PENDING LOCATION OF WASHING MACHINE FLOOR DRAIN BEING IN PLAIN VIEW 2) PLANS ARE CALLING FOR A LINT TRAP? | LYNNIE | LYNNIE | | PB | P | 3635313 |