J.E. DUNN ROCKY MOUNTAIN, INC. | BFR | C | 01/22/2009 | | BERTW | BERTW | | BFR | C | 3793950 |
J.E. DUNN ROCKY MOUNTAIN, INC. | B= | C | 01/22/2009 | | BERTW | BERTW | | B= | C | 3793761 |
J.E. DUNN ROCKY MOUNTAIN, INC. | B= | P | 09/22/2008 | 1)POST OCCUPANT LOAD SIGN FOR ASSEMBLY AREA 2)VERTICLE GRAB BAR MISSING IN ACCESSABLE TOILET ROOM 3)ADJUST PANIC HARDWARE LATCH @ MAIN DOOR | BERTW | BERTW | | B= | P | 3743985 |
J.E. DUNN ROCKY MOUNTAIN, INC. | BSP | P | 06/16/2008 | ABOVE GRID AND ALL RATED WALL FIRECAULKING OK | BERTW | BERTW | | BSP | P | 3692722 |
J.E. DUNN ROCKY MOUNTAIN, INC. | BSP | P | 05/27/2008 | ABOVE HARDLID FIRE CAULKING OK/NEED LOW VOLT CONDUITS ENDS FIRE CAULKED AND INSPECTED | BERTW | BERTW | | BSP | P | 3681613 |
J.E. DUNN ROCKY MOUNTAIN, INC. | BFR | R | 05/23/2008 | NEED A CALL AHEAD NUMBER FOR THE LOCATION OF INSPECTION | TERRYB | TERRYB | | BFR | R | 3681310 |
J.E. DUNN ROCKY MOUNTAIN, INC. | BFR | P | 05/19/2008 | INTERIOR WALLS AND SOFFITS OK/NEED DAMPERS INSPECTED PER MECHANICAL NOTES/NEED ALL 1-HOUR WALL FRAMING INSPECTED | BERTW | BERTW | | BFR | P | 3677791 |
KENNY ELECTRIC SERVICE, INC. | E= | C | 07/14/2008 | | BRET | BRET | | E= | C | 3707041 |
KENNY ELECTRIC SERVICE, INC. | ER | C | 06/24/2008 | ceilings ok | TIMA | TIMA | | ER | C | 3697246 |
KENNY ELECTRIC SERVICE, INC. | ER | P | 05/15/2008 | WALLS OK | TIMA | TIMA | | ER | P | 3676380 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 07/25/2008 | RECIEVED BALANCE REPORT | JON | JON | | H= | C | 3714029 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/19/2008 | NEED BALANCE REPORT. | JON | JON | | H= | P | 3694772 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/18/2008 | NEED TO SEE RETAINING ANGLES AT ALL 8 DAMPERS AT CORRIDOR SIDE. OK FOR TILE. NEED BALANCE REPORT WITH OUTSIDE AIR SHOWN. | JON | JON | | H= | P | 3694092 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 06/03/2008 | FIRE SMOKE DAMPER FRAMING ONLY ON LAST TWO DAMPERS. NEED TO SEE RETAINING ANGLES ON ALL DAMPERS WITH PROPER ACCESS TO DAMPERS BEFORE FINAL AT HARD LIDS STILL NEED FLEX AND DIFFUSERS. | JON | JON | | HD | P | 3685814 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 05/19/2008 | FRAMING OK AT NORTH OVAL FIRE SMOKE DAMPERS X2... STILL NEED 2 SOUTH DAMPERS. | JON | JON | | HD | P | 3677870 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 05/16/2008 | 3- DAMPERS ONLY OK ON FRAMING AND READY FOR ROCK, STILL NEED ALL 4 DAMPERS CALLED FOR INSPECTION AT OVAL DUCTS. | JON | JON | | HD | P | 3677279 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 05/15/2008 | OK FOR WRAP ONLY, FIRE SMOKE DAMPERS ARE NOT READY FOR INSPECTION. | JON | JON | | HD | P | 3676727 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 08/22/2008 | | JEFF | JEFF | | P= | C | 3729474 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 07/28/2008 | water temperature exceeds 110 degrees at both sink and lav | JEFF | JEFF | | P= | P | 3714852 |
HEATING & PLUMBING ENGINEERS, INC | P= | R | 06/17/2008 | WAIVE TRIP FEE, NOT READY, CALLED WRONG INSPECTION | JEFF | JEFF | | P= | R | 3693130 |
HEATING & PLUMBING ENGINEERS, INC | PTO | C | 05/22/2008 | | KYE | KYE | | PTO | C | 3680476 |
HEATING & PLUMBING ENGINEERS, INC | PTO | R | 05/21/2008 | NO TEST AT RELOCATED OR ADDED BATH GROUP AND SINK, CONTRACTOR TO COORDINATE INSPECTION WITH RBD DUE TO ACCESS AND TIME RESTRAINT ISSUES | JEFF | JEFF | | PTO | R | 3679262 |