ACCESS CONSTRUCTION CO., INC. | B= | C | 07/29/2008 | | RICK | RICK | | B= | C | 3715871 |
ACCESS CONSTRUCTION CO., INC. | BFR | C | 07/29/2008 | | RICK | RICK | | BFR | C | 3715870 |
FRONTIER MECHANICAL SYSTEMS INC | BSP | T | 07/25/2008 | PAID (REC#818164) ADDITIONAL PLAN REVIEW TIME: $50 From: RUSSELL Revised plumbing, added booster pump for water | RUSSELL | RUSSELL | | BSP | T | 3714333 |
ACCESS CONSTRUCTION CO., INC. | BSP | T | 06/27/2008 | PAID (REC#818320) ADDITIONAL PLAN REVIEW TIME: $50 From: JOHNJ okd splice on bathroom walls the use of osb, durock , epoxy grout, epoxy paint for non absorbent walls {ibc 1210.2} | JOHNJ | JOHNJ | | BSP | T | 3699639 |
ACCESS CONSTRUCTION CO., INC. | BIN | C | 06/26/2008 | | MIKE | MIKE | | BIN | C | 3698916 |
ACCESS CONSTRUCTION CO., INC. | BFR | P | 06/26/2008 | Interior framing ok,Need all items for porch roof,Received rolling door header size from Mibar Engineering(16479) | MIKE | MIKE | | BFR | P | 3698913 |
ACCESS CONSTRUCTION CO., INC. | BFR | R | 06/25/2008 | Need heat inspection,Need revised rafter ledger attachment,Install rafter clips per design,Install post caps per design,Missing king studs at door openings,Need approved header size @ roll up door (not shown on structural design) | MIKE | MIKE | | BFR | R | 3698432 |
ACCESS CONSTRUCTION CO., INC. | BFI | C | 05/29/2008 | | MIKE | MIKE | | BFI | C | 3683344 |
ACCESS CONSTRUCTION CO., INC. | BFI | R | 05/28/2008 | Work not complete | MIKE | MIKE | | BFI | R | 3682625 |
ACCESS CONSTRUCTION CO., INC. | BFN | C | 05/21/2008 | | MIKE | MIKE | | BFN | C | 3679807 |
ACCESS CONSTRUCTION CO., INC. | BFT | C | 05/21/2008 | | MIKE | MIKE | | BFT | C | 3679806 |
ACCESS CONSTRUCTION CO., INC. | BFT | R | 05/19/2008 | Open hole report is incomplete (Need note indicating existing fill material noted in soils report has been penetrated,Need final soil bearing pressure noted) | MIKE | MIKE | | BFT | R | 3678358 |
ACCESS CONSTRUCTION CO., INC. | BFT | T | 05/16/2008 | PAID (REC#806763) No work has been completed | MIKE | MIKE | | BFT | T | 3677575 |
FOSTER ELECTRIC CORPORATION | E= | C | 07/24/2008 | HAD PHONE CONVERSATION WITH GREG AT FOSTER AND BOOTH COMES PRE WIRED FROM FACTORY AS AN ASSEMBLED UNIT, THEY DID LABEL ALL CIRCUITS | BRET | BRET | | E= | C | 3713768 |
FOSTER ELECTRIC CORPORATION | E= | P | 07/22/2008 | restructure ok, need to meet with electrican on circuits feeding sky ride, missing panel schedule in ride control booth. | BRET | BRET | | E= | P | 3712540 |
FOSTER ELECTRIC CORPORATION | E= | P | 07/17/2008 | west exterior not ready, drive grounds down or install at 45, I thought they were to backfill around ground rods. | BRET | BRET | | E= | P | 3710059 |
FOSTER ELECTRIC CORPORATION | ER | C | 06/24/2008 | | BRET | BRET | | ER | C | 3697739 |
FOSTER ELECTRIC CORPORATION | ES | C | 05/23/2008 | Commercial Service: 300 amp 4/wire ug by foster electric needs, u-guard, overhead terminations, and meters set 1-100 amp and 1-200 amp | BRET | BRET | | ES | C | 3681267 |
FOSTER ELECTRIC CORPORATION | ES | R | 05/21/2008 | clear taps not service rated. need spec sheet to prove otherwise. e-mail info. bret@pprbd.org | BRET | BRET | | ES | R | 3679442 |
FOSTER ELECTRIC CORPORATION | EUG | P | 05/19/2008 | ufer ok | BRET | BRET | | EUG | P | 3677871 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 07/21/2008 | ELECTRIC HEAT. | JON | JON | | H= | C | 3711603 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | C | 06/25/2008 | BATH EXHAUST AND TRANSFER DUCTS OK. | JON | JON | | HD | C | 3698451 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 07/25/2008 | | MARTY | MARTY | | P= | C | 3714440 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 06/20/2008 | | MICK | MICK | | PTO | C | 3696035 |
FRONTIER MECHANICAL SYSTEMS INC | PB | C | 06/04/2008 | | MICK | MICK | | PB | C | 3686950 |