T-BONE CONSTRUCTION, INC. | B= | C | 06/30/2009 | | MIKE | MIKE | | B= | C | 3852681 |
T-BONE CONSTRUCTION, INC. | B= | P | 06/17/2009 | Still need rated door labels | MIKE | MIKE | | B= | P | 3847289 |
T-BONE CONSTRUCTION, INC. | B= | P | 06/15/2009 | Missing exit sign over office fire door, Complete all door hardware & adjust closures, Door fire labels | MIKE | MIKE | | B= | P | 3846134 |
T-BONE CONSTRUCTION, INC. | B= | R | 06/12/2009 | CANCELLED IN THE FIELD, CONTRACTOR NEEDS FIRE FINAL | ED | ED | | B= | R | 3845325 |
T-BONE CONSTRUCTION, INC. | BFR | C | 05/20/2009 | (LAST OF THE FRAMIED WALL INSPECTIONS), BOTH COM ROOMS AND TRAP ROOM FRAMING, AND LID FRAMING OK. | ED | ED | | BFR | C | 3836715 |
T-BONE CONSTRUCTION, INC. | BSP | P | 05/13/2009 | CORRIDOOR AREAS WALLS @ HARDLID INTERSECTION FIRESAFING OK | BERTW | BERTW | | BSP | P | 3833970 |
T-BONE CONSTRUCTION, INC. | BSP | P | 05/12/2009 | FIRECAULKING OK @ 2HR FIRE BARRIER WALL TO UNDERSIDE OF ROOF DECK/2 LAYERS OF TYPE-X SHEETROCK OK BOTH SIDES OF SAME WALL | BERTW | BERTW | | BSP | P | 3833574 |
T-BONE CONSTRUCTION, INC. | BSP | T | 05/06/2009 | PAID (REC#857036) ADDITIONAL PLAN REVIEW TIME: $50 From: DALEH changed gas piping size | DALEH | DALEH | | BSP | T | 3831425 |
T-BONE CONSTRUCTION, INC. | BFR | P | 04/21/2009 | 2HR FIRE BARRIER WALLS AND SOUND WALLS FRAMING OK/NEED FIRE CAULKING AND MINERAL WOOL INSPECTION/NEED ALL OTHER ROUGH INSPECTIONS | BERTW | BERTW | | BFR | P | 3825963 |
T-BONE CONSTRUCTION, INC. | E= | C | 06/11/2009 | | TIMA | TIMA | | E= | C | 3845078 |
T-BONE CONSTRUCTION, INC. | ER | C | 06/04/2009 | CEILINGS COMPLETE | TIMA | TIMA | | ER | C | 3842196 |
T-BONE CONSTRUCTION, INC. | ER | P | 06/01/2009 | CEILINGS IN CONFERENCE ROOM, OPEN OFFICE AND HALLWAY BETWEEN; MARKED ON PLANS | MATTHEW | MATTHEW | | ER | P | 3840770 |
T-BONE CONSTRUCTION, INC. | ER | P | 05/20/2009 | interior walls and hard lids in hall and comm rooms | TIMA | TIMA | | ER | P | 3836526 |
T-BONE CONSTRUCTION, INC. | ER | P | 04/29/2009 | exterior sciff room walls and hall walls ok | TIMA | TIMA | | ER | P | 3828901 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 06/12/2009 | RECIEVED BALANCE REPORT | JON | JON | | H= | C | 3845321 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 06/02/2009 | NEED AIR BALANCE REPORT | JON | JON | | H= | P | 3841125 |
FENTON PLUMBING & HEATING INC | H= | C | 05/29/2009 | GAS FINAL ONLY | JON | JON | | H= | C | 3840212 |
FENTON PLUMBING & HEATING INC | HI | C | 05/29/2009 | REPIPED EXISTING AND ADDED RTU. | JON | JON | | HI | C | 3840198 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 05/15/2009 | OK FOR WRAP. CO SENSOR AT RTU 4 AND BALANCE REPORT BY FINAL. SMOKE DETECTION IF REQUIRED BY FINAL. | JON | JON | | HD | P | 3835096 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 05/11/2009 | SCIF ROOM DUCT ONLY - OK TO WRAP. | JEFFB | JEFFB | | HD | P | 3832908 |
FENTON PLUMBING & HEATING INC | P= | C | 06/08/2009 | CORRECTIONS MADE. | SCOTT | SCOTT | | P= | C | 3843052 |
FENTON PLUMBING & HEATING INC | P= | P | 06/05/2009 | EXPOSE CLEANOUT ON ADA URINAL. TURN DOWN WATER TEMP. CURRENTLY WATER IS 120 DEGREES. | SCOTT | SCOTT | | P= | P | 3842559 |
FENTON PLUMBING & HEATING INC | PTO | C | 05/18/2009 | URINAL NEXT TO DOUBLE LAVS REQS A C/O BY FINALS | LYNNIE | LYNNIE | | PTO | C | 3835872 |
FENTON PLUMBING & HEATING INC | PB | C | 05/12/2009 | | LYNNIE | LYNNIE | | PB | C | 3833727 |