GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 11/09/2009 | | MIKE | MIKE | | B= | C | 3909463 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 11/02/2009 | Need heat final -- Schedule a new Building Final when above items are complete. | MIKE | MIKE | | B= | P | 3906138 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BBB | C | 10/13/2009 | WEST WALL AT TOP OK; COMPLETES BOND BEAMS | DANF | DANF | | BBB | C | 3897595 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 09/30/2009 | "C" CHILLER PAD OK TO POUR | DANF | DANF | | BFT | P | 3891789 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BBB | P | 09/14/2009 | Vestibule door #2 - Top bond beam ok | MIKE | MIKE | | BBB | P | 3884494 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 09/14/2009 | Reviewed shaft wall framing, Researched UL listings, Discussed solutions to framing problems | MIKE | MIKE | | BSP | P | 3884493 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFT | P | 09/01/2009 | Chiller pads "A" & "B" ok | MIKE | MIKE | | BFT | P | 3879681 |
DYNALECTRIC COMPANY | E= | C | 10/29/2009 | | MIKEC | MIKEC | | E= | C | 3905206 |
DYNALECTRIC COMPANY | ER | C | 10/29/2009 | | MIKEC | MIKEC | | ER | C | 3905205 |
MECHONE, INC. | H= | C | 11/03/2009 | TEST AND BALANCE REPORT RECEIVED AND SCANNED. | NANCY | NANCY | | H= | C | 3906325 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 10/19/2009 | MECHANICAL FINAL OK ON CHILLED WATER, HOT WATER AND CONDENSER PIPING. OK. | NANCY | NANCY | | H= | C | 3899966 |
OLSON PLUMBING & HEATING COMPANY | HWP | C | 10/19/2009 | CHILLED WATER, HOT WATER AND CONDENSER WATER PIPING COMPLETE. | NANCY | NANCY | | HWP | C | 3899963 |
MECHONE, INC. | HD | C | 10/19/2009 | AHU-C9-C AND DUCT FOR AHU OK. EXHAUST FAN ON ROOF OK. SENSORS, ALARMS AND STROBES ALL INSTALLED. | NANCY | NANCY | | HD | C | 3899961 |
MECHONE, INC. | H= | P | 10/19/2009 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 3899958 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 10/15/2009 | CHILLER C, CHILLED WATER AND CONDENSER PIPING, 80 LB TESTS OK. AHU-C9C, HEAT COIL, 80 LB TEST OK. PLATE AND FRAME, CHILLED WATER AND CONDENSER WATER, 80 LB TESTS OK. | NANCY | NANCY | | HWP | P | 3898559 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 09/17/2009 | 2- 84# TESTS ON CHILL AND HEATING WATER LINES OK. | LYNNS | LYNNS | | HWP | P | 3886256 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 08/14/2009 | PRESSURE TESTS ON CHILLED WATER PIPING AND CONDENSER WATER PIPING, CHILLER B, OK. | NANCY | NANCY | | HWP | P | 3871497 |
MECHONE, INC. | HD | P | 08/12/2009 | ROUGH DUCT ON EF-1 IN MECH ROOM AND RISER. | LYNNS | LYNNS | | HD | P | 3870628 |