ACCESS CONSTRUCTION CO., INC. | B= | C | 03/16/2010 | All other required Final inspections are complete. (This is a computer generated result) | BERTW | BERTW | | B= | C | 3954524 |
ACCESS CONSTRUCTION CO., INC. | B= | P | 03/12/2010 | Additional Inspections Required: External Agency Inspection Z= by ZONING is not Completed yet (Contact: ngadson@springsgov.com or 385-5982). | BERTW | BERTW | | B= | P | 3953499 |
ACCESS CONSTRUCTION CO., INC. | BFR | C | 03/04/2010 | | BERTW | BERTW | | BFR | C | 3950442 |
ACCESS CONSTRUCTION CO., INC. | BSP | P | 03/04/2010 | TRUSS GUSSET PLATES OK | BERTW | BERTW | | BSP | P | 3950440 |
ACCESS CONSTRUCTION CO., INC. | BFR | P | 02/09/2010 | FRAMING OF TRELLIS IN PROGRESS/TRAINING WITH LEE GUTHIE | BERTW | BERTW | | BFR | P | 3941995 |
ACCESS CONSTRUCTION CO., INC. | BIN | C | 01/26/2010 | | BERTW | BERTW | | BIN | C | 3936968 |
ACCESS CONSTRUCTION CO., INC. | BFR | P | 01/26/2010 | STILL NEED TRELLIS INSPECTED- MISSING SOME TRUSS WEN CONNECTIONS(CUSTOM) AND POST TO PIERSALL ELSE OK | BERTW | BERTW | | BFR | P | 3936962 |
ACCESS CONSTRUCTION CO., INC. | BSP | T | 01/26/2010 | PAID (REC#894104) ADDITIONAL PLAN REVIEW TIME: $50 From: JOHNJ added single page for splice to clarify needs of building inspector, no other changes or additions at all. | JOHNJ | JOHNJ | | BSP | T | 3936582 |
ACCESS CONSTRUCTION CO., INC. | BFR | P | 01/20/2010 | 1)RAFTER-TRUSS SPACING NOT ON DRAWINGS 2)HEADER AND RAFTER SIZING IN TICKET BOOTHS NOT ON DRAWINGS 3)BRACKETS @ WEB TO TRUSS CHORD CONNECTIONS MISSINGS 4)POST TO BEAMS AND PIER CONNECTIONS MISSING 5)REVISE DRAWINGS TO SHOW 4 ADDED WINDOWS 6)STILL NEED TRELLIS INSPECTED | BERTW | BERTW | | BFR | P | 3934836 |
ACCESS CONSTRUCTION CO., INC. | B=R | P | 01/19/2010 | SHINGLE ROOF INSTALLATION OK | BERTW | BERTW | | B=R | P | 3934132 |
ACCESS CONSTRUCTION CO., INC. | BFR | R | 01/19/2010 | NOT READY STILL NEED ELECTRIC INSPECTION | BERTW | BERTW | | BFR | R | 3934131 |
ACCESS CONSTRUCTION CO., INC. | BFN | C | 01/19/2010 | OPEN HOLE ON FILE | BERTW | BERTW | | BFN | C | 3934129 |
ACCESS CONSTRUCTION CO., INC. | BFT | C | 12/17/2009 | -----still need stamped openhole to complete foundation----- all footers for 7 piers at canopy ok. | NATHAN | NATHAN | | BFT | C | 3923802 |
ACCESS CONSTRUCTION CO., INC. | BFI | C | 12/02/2009 | RIGID VERTICALLY OK | BERTW | BERTW | | BFI | C | 3918791 |
ACCESS CONSTRUCTION CO., INC. | BFN | P | 11/30/2009 | stamped open excavation report needed, ok to pour foundations. | NATHAN | NATHAN | | BFN | P | 3917484 |
ACCESS CONSTRUCTION CO., INC. | BSP | T | 11/25/2009 | PAID (REC#887368) ADDITIONAL PLAN REVIEW TIME: $50 From: JOHNJ {2} CLOUDED FOOTERS ARE TO BE ON TOP OF EXISTING, NO OTHER CHANGES TO SPLICE. | JOHNJ | JOHNJ | | BSP | T | 3916856 |
ACCESS CONSTRUCTION CO., INC. | BFT | P | 11/25/2009 | SOILS3000PSF-DESIGN1000PSF/TICKET BOOTH FOOTINGS OK-STILL NEED TO INSPECT CANOPY PADS/NEED STAMPED OPEN HOLE REPORT | BERTW | BERTW | | BFT | P | 3916807 |
FOSTER ELECTRIC CORPORATION | E= | C | 03/09/2010 | advised contractor that emt raceway from meter to building #4 cannot be in contact with the earth. He informed me that the zoo is aware of this and will remove the soil around it. | BRET | BRET | | E= | C | 3952173 |
FOSTER ELECTRIC CORPORATION | ES | P | 02/18/2010 | Commercial Service: 200 amp 4/wire service by foster electric ok to energize contractor to coordinate shutdown with cspu. note install brass address tag, ground rod at panel (ticket booth) and revise plans. | BRET | BRET | | ES | P | 3945424 |
FOSTER ELECTRIC CORPORATION | ER | C | 01/19/2010 | | BRET | BRET | | ER | C | 3934223 |
FOSTER ELECTRIC CORPORATION | EUG | P | 12/14/2009 | fosters work ok zoo needs to install j-box in slab. 1" to 1/2 raceway reducers not permitted | BRET | BRET | | EUG | P | 3922367 |
FOSTER ELECTRIC CORPORATION | EUG | P | 11/20/2009 | ug from service to first j-box | BRET | BRET | | EUG | P | 3914824 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 03/11/2010 | | JON | JON | | H= | C | 3953306 |