BOB MCGRATH CONSTRUCTION LLC | B= | C | 04/23/2010 | Stairs/handrail/guardrail are all existing nonconforming | MIKE | MIKE | | B= | C | 3971496 |
BOB MCGRATH CONSTRUCTION LLC | B= | P | 04/22/2010 | Additional Inspections Required: External Agency Inspection Z= by ZONING is not Completed yet (Contact: ngadson@springsgov.com or 385-5982), OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet. Heat final, Missing HC restroom signs, Missing plumbing protection under HC sink -- Schedule a new Building Final when above items are complete. | MIKE | MIKE | | B= | P | 3970980 |
BOB MCGRATH CONSTRUCTION LLC | BSP | P | 04/16/2010 | Reviewed final inspection ?'s, Ok to move furniture in | MIKE | MIKE | | BSP | P | 3968004 |
BOB MCGRATH CONSTRUCTION LLC | BFR | C | 03/31/2010 | | MIKE | MIKE | | BFR | C | 3960510 |
BOB MCGRATH CONSTRUCTION LLC | BIN | C | 03/31/2010 | Balance of insulation is existing nonconforming | MIKE | MIKE | | BIN | C | 3960509 |
BOB MCGRATH CONSTRUCTION LLC | BSP | P | 03/29/2010 | Termal barrier at foam insulation ok | MIKE | MIKE | | BSP | P | 3959330 |
BOB MCGRATH CONSTRUCTION LLC | BSP | P | 03/25/2010 | Thermal barrier at foam insulation - Cover all exposed foam with fiberglass insulation | MIKE | MIKE | | BSP | P | 3958311 |
BOB MCGRATH CONSTRUCTION LLC | BSP | R | 03/24/2010 | Foam insulation - Thermal barrier not complete | MIKE | MIKE | | BSP | R | 3957934 |
BOB MCGRATH CONSTRUCTION LLC | BSP | R | 03/23/2010 | 1st Floor - Foam insulation sprayed at rim in floor/ceiling assembly, Need to install thermal barrier to code | MIKE | MIKE | | BSP | R | 3957410 |
BOB MCGRATH CONSTRUCTION LLC | BIN | P | 03/23/2010 | 2nd Floor - 1/2" ridgid insulation (R-3) installed at verticle stair enclosure wall | MIKE | MIKE | | BIN | P | 3957407 |
BOB MCGRATH CONSTRUCTION LLC | BFR | P | 03/23/2010 | Received structural modifications inspection report from HCDA(36309), Still need rough inspections & deck frame inspection | MIKE | MIKE | | BFR | P | 3957403 |
BOB MCGRATH CONSTRUCTION LLC | BIN | P | 02/24/2010 | R-13 at walls furred with 3 5/8" studs ok | MIKE | MIKE | | BIN | P | 3947521 |
BOB MCGRATH CONSTRUCTION LLC | BFR | P | 02/23/2010 | Need electric & mechanical rough inspections, Need engineer stamped letter for structural modifications, Complete deck framing | MIKE | MIKE | | BFR | P | 3946812 |
BOB MCGRATH CONSTRUCTION LLC | BFR | P | 02/19/2010 | Need electric & mechanical rough inspections, Need engineering for new windows cut into exterior masonry walls, Complete 1hr vertical stair enclosure, Firestop, Deck framing | MIKE | MIKE | | BFR | P | 3945820 |
BOB MCGRATH CONSTRUCTION LLC | BSP | P | 01/14/2010 | BASE PLATES WET SET INTO CMU WALLS CELLS FOR NEW WINDOWS/NEED ENGINEERING FOR OFFSET PLATES WHERE LOCATIONS VARY FROM PLANS | BERTW | BERTW | | BSP | P | 3932718 |
DUKES ELECTRIC, INC | E= | C | 04/02/2010 | | BRET | BRET | | E= | C | 3961852 |
DUKES ELECTRIC, INC | ER | C | 03/12/2010 | REST OF CEILING | GARYL | GARYL | | ER | C | 3953841 |
DUKES ELECTRIC, INC | ER | P | 02/18/2010 | walls and hardlid ok. | BRET | BRET | | ER | P | 3945214 |
DUKES ELECTRIC, INC | ESL | C | 02/10/2010 | floor boxes 2 locations ok to cover. | BRET | BRET | | ESL | C | 3942385 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 04/23/2010 | RECEIVED BALANCE REPORT | JON | JON | | H= | C | 3971455 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 04/16/2010 | HVAC FINAL PENDING BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 3968008 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 02/22/2010 | ROUGH DUCT OK 1ST AND 2ND FLOOR. NEED ELECTRICAL ROOM VENTILATION AND WATER HEATER SET BEFORE FINAL. WILL NEED AIR BALANCE REPORT. | JON | JON | | HD | P | 3946308 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 04/22/2010 | | LYNNIE | LYNNIE | | P= | C | 3970868 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 04/16/2010 | ALL BUT LAVS AND SINK OK | LYNNIE | LYNNIE | | P= | P | 3968091 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 02/03/2010 | | LYNNIE | LYNNIE | | PB | C | 3939916 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 02/03/2010 | COFFEE SINK WILL REQ A AAV UNDER SINK AT FINAL | LYNNIE | LYNNIE | | PTO | C | 3939915 |