COLARELLI CONSTRUCTION, INC. | B= | C | 11/17/2011 | All other required Final inspections are complete. (This is a computer generated result) | BERTW | BERTW | | B= | C | 4237674 |
COLARELLI CONSTRUCTION, INC. | B= | P | 07/28/2011 | Additional Inspections Required: External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: rdassero@springsgov.com or 385-7396), External Agency Inspection Z= by ZONING is not Completed yet (Contact: mmaloney@springsgov.com or 385-5080), NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet, RYBA ELECTRIC, INC. Electrical Final Inspection is not Completed yet. | BERTW | BERTW | | B= | P | 4184801 |
COLARELLI CONSTRUCTION, INC. | BFR | C | 07/28/2011 | new lights are tented per design | BERTW | BERTW | | BFR | C | 4184787 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 07/14/2011 | phase #3 new doors and infill framing ok/need new 2x4 fluorescent lights tented per approved design | BERTW | BERTW | | BFR | P | 4177402 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 07/01/2011 | phase 3 walls ok | BERTW | BERTW | | BFR | P | 4172000 |
COLARELLI CONSTRUCTION, INC. | BSP | R | 06/29/2011 | reviewed with Kevin ,contractor rep,all new ceiling tile is part of a rated floor celing assembly-need approved design with rbd stamp for inspection of grid system | BERTW | BERTW | | BSP | R | 4170687 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 06/13/2011 | phase #1 ok/pending other roughs completed | BERTW | BERTW | | BFR | P | 4162767 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 06/07/2011 | walls ok pending other rough inspections complete | BERTW | BERTW | | BFR | P | 4159734 |
RYBA ELECTRIC, INC. | E= | C | 11/17/2011 | | MIKEC | MIKEC | | E= | C | 4237673 |
RYBA ELECTRIC, INC. | E= | R | 11/10/2011 | need approved plan on site revised to reflect as built conditions | SHELBY | SHELBY | | E= | R | 4234124 |
RYBA ELECTRIC, INC. | E= | P | 10/25/2011 | NEED PLANS AND ACCESS TO ELECTRIC ROOM. | BRET | BRET | | E= | P | 4226779 |
RYBA ELECTRIC, INC. | E= | P | 07/13/2011 | 118 ok | BRET | BRET | | E= | P | 4176752 |
RYBA ELECTRIC, INC. | ER | P | 07/13/2011 | ceiling ok 118,151 | BRET | BRET | | ER | P | 4176749 |
RYBA ELECTRIC, INC. | ER | P | 07/01/2011 | wall 151
| MIKEC | MIKEC | | ER | P | 4171950 |
RYBA ELECTRIC, INC. | ESL | C | 06/29/2011 | esl for floor box ok | BRET | BRET | | ESL | C | 4170900 |
RYBA ELECTRIC, INC. | E= | P | 06/24/2011 | east room 190-192 | BRET | BRET | | E= | P | 4168777 |
RYBA ELECTRIC, INC. | E= | P | 06/20/2011 | west wing phase one | JOSEPH | JOSEPH | | E= | P | 4166067 |
RYBA ELECTRIC, INC. | ER | P | 06/20/2011 | drop ceilings on east and west wings of phase one | JOSEPH | JOSEPH | | ER | P | 4166065 |
RYBA ELECTRIC, INC. | ER | P | 06/09/2011 | rest of walls | BRET | BRET | | ER | P | 4161514 |
RYBA ELECTRIC, INC. | ER | P | 06/06/2011 | walls ok | BRET | BRET | | ER | P | 4159007 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 08/09/2011 | RECEIVED BALANCE REPORT. | LYNNS | LYNNS | | H= | C | 4190136 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 07/27/2011 | HVAC FINAL PENDING BALANCE REPORT. | LYNNS | LYNNS | | H= | P | 4184181 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 06/28/2011 | 1ST PHASE ONLY | JON | JON | | HD | P | 4170238 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 06/24/2011 | RADIATION DAMPERS ARE TO BE SUPPORTED TO INSTRUCTIONS WITH 4 WIRES AND TO BE VERTICAL TO STRUCTURE. | JON | JON | | HD | P | 4168866 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 06/15/2011 | OK FOR WRAP PHASE ONE, SEE ON SITE WHEN DUCT IS WRAPPED AND RADIATION DAMPERS ARE INSTALLED AND SUPPORTED TO INSTRUCTIONS. | JON | JON | | HD | P | 4164279 |