MAHLER GC GENERAL CONTRACTING COMPANY | B= | C | 10/01/2015 | All other required Final inspections are complete. (This is a computer generated result) | JOND | JOND | | B= | C | 5048527 |
MAHLER GC GENERAL CONTRACTING COMPANY | BE | L | 09/01/2015 | Renewed at 9/1/2015 10:43:18 AM | MINDY | MINDY | | BE | L | 5027557 |
CHARLIE PATERSON CONSTR CO | B= | P | 10/31/2014 | Additional Inspections Required: External Agency Inspection HD= by HEALTHDEPT is not Completed yet, Floodplain Final Inspection is not Completed yet, AFFORDABLE PLUMBING & HEAT,INC Mechanical Final Inspection is not Completed yet, KENT SHEET METAL, INC Mechanical Final Inspection is not Completed yet. | JOND | JOND | | B= | P | 4846087 |
AFFORDABLE PLUMBING & HEAT,INC | BSP | T | 09/16/2014 | PAID (REC#1220166) PLAN SPLICE FEE: $50 by: DALEH for Mechanical | DALEH | DALEH | | BSP | T | 4816629 |
CHARLIE PATERSON CONSTR CO | B= | P | 09/11/2014 | Additional Inspections Required: External Agency Inspection HD= by HEALTHDEPT is not Completed yet, Floodplain Final Inspection is not Completed yet, AFFORDABLE PLUMBING & HEAT,INC Mechanical Final Inspection is not Completed yet, KENT SHEET METAL, INC Mechanical Final Inspection is not Completed yet. 1)exit sign light main door 2)missing all handrails @ exterior stairs and rear ramp 3)remove exit signs from plans not being installed 4)post address on building -- Schedule a new Building Final when above items are complete. | BERTW | BERTW | | B= | P | 4814547 |
CHARLIE PATERSON CONSTR CO | BFR | C | 09/11/2014 | | BERTW | BERTW | | BFR | C | 4814497 |
CHARLIE PATERSON CONSTR CO | BIN | C | 08/07/2014 | | BERTW | BERTW | | BIN | C | 4792935 |
CHARLIE PATERSON CONSTR CO | BIN | P | 08/06/2014 | walls ok | BERTW | BERTW | | BIN | P | 4791925 |
CHARLIE PATERSON CONSTR CO | BFR | P | 08/05/2014 | framing ok pending other roughs completed/letter for framing changes roof truss support beam and door framing on file | BERTW | BERTW | | BFR | P | 4790945 |
CHARLIE PATERSON CONSTR CO | BFR | P | 07/31/2014 | interior ramp ok/check for tempered glass @ final inspection/need interior walls and trusses inspected | BERTW | BERTW | | BFR | P | 4788132 |
CHARLIE PATERSON CONSTR CO | BSP | P | 07/25/2014 | footing size changed for 3 ply microlam support midpoint bearing with roof load above ok/design on file | BERTW | BERTW | | BSP | P | 4784400 |
CHARLIE PATERSON CONSTR CO | BE | L | 02/18/2014 | Renewed at 2/18/2014 10:26:07 AM | TERRYB | TERRYB | | BE | L | 4688198 |
CHARLIE PATERSON CONSTR CO | BE | L | 11/18/2013 | Renewed for 1/2 Fee at 11/18/2013 3:59:57 PM (Receipt#1167063) | JESSIE | JESSIE | | BE | L | 4644005 |
CHARLIE PATERSON CONSTR CO | BE | C | 02/12/2013 | | MINDY | MINDY | | BE | C | 4470837 |
CHARLIE PATERSON CONSTR CO | BSP | P | 08/31/2012 | rec'd eng for concrete porch wall | BLAKE | BLAKE | | BSP | P | 4373937 |
CHARLIE PATERSON CONSTR CO | BFN | C | 08/14/2012 | | BERTW | BERTW | | BFN | C | 4361859 |
CHARLIE PATERSON CONSTR CO | BFT | C | 08/08/2012 | open hole on file | BERTW | BERTW | | BFT | C | 4358112 |
BEAR NECESSITY ELECTRIC INC | E= | C | 09/10/2014 | | MIKEC | MIKEC | | E= | C | 4813166 |
BEAR NECESSITY ELECTRIC INC | ER | P | 08/04/2014 | bathrooms ok, and the common wall of the bathrooms and kitchen also ok-------------------the rest of the kitchen going to be another phase. GC not sure if that will be a different permit or continuation of this project. | DEAN | DEAN | | ER | P | 4789805 |
BEAR NECESSITY ELECTRIC INC | EE | L | 07/31/2014 | Renewed at 7/31/2014 2:30:54 PM | DEAN | DEAN | | EE | L | 4787971 |
BEAR NECESSITY ELECTRIC INC | EE | L | 12/31/2013 | Renewed at 12/31/2013 2:48:58 PM | DEAN | DEAN | | EE | L | 4665033 |
BEAR NECESSITY ELECTRIC INC | ES | C | 12/07/2012 | Commercial Service: new 200 amp oh service | MIKEC | MIKEC | | ES | C | 4436680 |
MAHLER GC GENERAL CONTRACTING COMPANY | FP= | C | 09/21/2015 | | KEITH | KEITH | BDA | FP= | C | 5040787 |
CHARLIE PATERSON CONSTR CO | FP= | R | 07/11/2012 | Entered at Permit Issuance to ensure Floodplain inspections get completed. | KIM | KIM | | FP= | R | 4339525 |
KENT SHEET METAL, INC | HD | P | 04/17/2015 | STILL WAITING FOR PHASE THREE TO START. | NANCY | NANCY | | HD | P | 4937701 |
KENT SHEET METAL, INC | H16 | C | 10/22/2014 | TEST AND BALANCE REPORT RECEIVED FOR PHASE 2. | NANCY | NANCY | | H16 | C | 4839394 |
KENT SHEET METAL, INC | HD | P | 08/05/2014 | PHASE TWO ABOVE CEILING ALL OK, NO ROOF INSPECTION, BY FINAL NEED REVISED PRINTS FOR WATER HEATER, AND COMBUSTION AIR. | KEITHW | KEITHW | | HD | P | 4790935 |
AFFORDABLE PLUMBING & HEAT,INC | HI | P | 07/31/2014 | PHASE TWO (MECHANICAL ROOM AND BATHROOMS). 10 LB TEST OK ON GAS LINE TO FURNACE AND WATER HEATER. NEED REVISED/APPROVED PRINTS SHOWING WATER HEATER GAS LINE. BY FINAL NEED LETTER FROM BLACK HILLS APPROVING 2 LB SYSTEM. | NANCY | NANCY | | HI | P | 4787530 |
AFFORDABLE PLUMBING & HEAT,INC | HE | L | 12/19/2013 | Renewed online for 1/2 Fee at 12/19/2013 9:39:52 AM (RECEIPT #: 1171805) | WEBSITE | WEBSITE | | HE | L | 4659827 |
AFFORDABLE PLUMBING & HEAT,INC | HI | P | 03/26/2013 | UNABLE TO COMPLETE UNTIL PHASE THREE KITCHEN GAS IS INSTALLED. | NANCY | NANCY | | HI | P | 4493492 |
R & R DITCHING, INC | H= | C | 09/05/2012 | UNDERGROUND GAS FINAL OK. | NANCY | NANCY | | H= | C | 4376129 |
R & R DITCHING, INC | HC | C | 09/05/2012 | OK FOR 2 LB METER. | NANCY | NANCY | | HC | C | 4376126 |
R & R DITCHING, INC | HO | C | 09/05/2012 | 10 LB TEST OK. INSTALLED AS PER PRINTS. OK TO COVER TRENCH. | NANCY | NANCY | | HO | C | 4376125 |
AFFORDABLE PLUMBING & HEAT,INC | H= | P | 09/05/2012 | CAN NOT FINAL YET, PHASE 3 NOT INSTALLED ALSO SEE HI NOTES. | NANCY | NANCY | | H= | P | 4376123 |
AFFORDABLE PLUMBING & HEAT,INC | HI | P | 09/05/2012 | PHASE 1, UNIT HEATERS ONLY: 10 LB TEST OK. INSTALLED AS PER PRINTS. STILL NEED TO SEE PHASE 3 INSTALLED, GAS LINES TO KITCHEN EQUIPMENT. FOR FINAL NEED LETTER FROM BLACK HILLS APPROVING 2 LB SYSTEM. LABEL ALL MEDIUM PRESSURE GAS LINES AT A MAXIMUM OF EVERY 10 FEET. | NANCY | NANCY | | HI | P | 4376120 |
AFFORDABLE PLUMBING & HEAT,INC | P= | C | 09/04/2014 | all fixtures on this permit complete. | DICK | DICK | | P= | C | 4809771 |
AFFORDABLE PLUMBING & HEAT,INC | PTO | C | 09/04/2014 | note kitchen and grease drains will be on future permit if kitchen installed. | DICK | DICK | | PTO | C | 4809769 |
AFFORDABLE PLUMBING & HEAT,INC | PTO | P | 07/30/2014 | sanitary only, still need grease and interceptor. bathrooms, hand sink and mech room ok. | DICK | DICK | | PTO | P | 4786787 |
AFFORDABLE PLUMBING & HEAT,INC | PB | P | 07/17/2014 | sanitary line o.k, still need grease line and intercepter installed | JOEL | JOEL | | PB | P | 4778944 |