PEAK PROFESSIONAL CONTRS INC | B= | C | 01/09/2013 | | JOHNP | JOHNP | | B= | C | 4451609 |
PEAK PROFESSIONAL CONTRS INC | BFR | C | 01/09/2013 | | JOHNP | JOHNP | | BFR | C | 4451607 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 10/18/2012 | Walls only OK, no electrical, mechanical or roof modification yet | JOHNP | JOHNP | | BFR | P | 4404425 |
Q-5 INC. | E= | C | 11/13/2012 | | TIMA | TIMA | | E= | C | 4420672 |
Q-5 INC. | ER | C | 11/13/2012 | CEILINGS ROOMS 120F AND 120G OK | TIMA | TIMA | | ER | C | 4420641 |
Q-5 INC. | ES | C | 11/07/2012 | Commercial Service: 1200 amp 3 phase commercial service; 120/208 volt ct's in transformer ok to energize service-------------- note to inspector, checked both sub panels and both ok except they need 1) handle ties, 2) panel directories 3) Arc flash stickers | JOSEPH | JOSEPH | | ES | C | 4417766 |
Q-5 INC. | ER | P | 10/31/2012 | CEILINGS ROOMS 102 AND 102D | TIMA | TIMA | | ER | P | 4412909 |
Q-5 INC. | ES | R | 10/26/2012 | ----------------------------OK FOR RAIN TIGHT CONNECTORS WHERE CONDUITS ENTER TOP OF ENCLOSURE ONLY------------------------- | DEAN | DEAN | | ES | R | 4410305 |
Q-5 INC. | EUG | C | 10/26/2012 | SERVICE LATERAL OK ALSO WENT OVER ITEMS WITH CONTRACTOR | TIMA | TIMA | | EUG | C | 4410084 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 11/30/2012 | LETTER FROM ENGINEER RECEIVED AND SCANNED. | NANCY | NANCY | | H= | C | 4431075 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 11/26/2012 | READINGS FOR EXISTING RTU'S 1, 2 AND 4 OUTSIDE OF +/- 10% ALLOWED. PROVIDE LETTER FROM ENGINEER APPROVING CFM READINGS. | NANCY | NANCY | | H= | P | 4428078 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 11/14/2012 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 4421761 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 11/08/2012 | RTU 5: DROPS, TRUNK LINES AND LATERALS ALL OK, OK TO CLOSE WRAP. STILL NEED TO SEE SMOKE DETECTOR AND ROOF. RTU'S 1, 2, 3, 4 AND 7: ABOVE CEILING ALL OK, OK FOR TILES PER MECHANICAL ONLY. | NANCY | NANCY | | HD | P | 4418301 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 10/29/2012 | RTU 4: SUPPLY RUNS INTO HALLWAY AND OFFICE OK, OK TO CLOSE WRAP. RTU 7: SUPPLY AIR INTO HALLWAY OK, OK TO CLOSE WRAP. | NANCY | NANCY | | HD | P | 4410697 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 10/24/2012 | RTU'S 1, 2 AND 3: ROUGH DUCTS ABOVE CEILING OK, OK TO CLOSE UP WRAP. NEED TO SEE DIFFUSERS INSTALLED. | NANCY | NANCY | | HD | P | 4408224 |