SADDLETREE INC. | B= | C | 05/21/2013 | | JOND | JOND | | B= | C | 4527665 |
SADDLETREE INC. | B= | P | 05/17/2013 | adjust grade around entire structure so that water flows positively away -- Schedule a new Building Final when above items are complete. | BLAKE | BLAKE | | B= | P | 4526340 |
SADDLETREE INC. | BLA | C | 03/11/2013 | | JIMP | JIMP | | BLA | C | 4484887 |
SADDLETREE INC. | BFR | C | 03/04/2013 | | JIMP | JIMP | | BFR | C | 4481104 |
SADDLETREE INC. | BSP | T | 02/28/2013 | PAID (REC#1114035) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: splice to change furnace location | DALEH | DALEH | | BSP | T | 4479415 |
SADDLETREE INC. | BSP | T | 01/23/2013 | PAID (REC#1107255) ADDITIONAL PLAN REVIEW TIME: $50 From: JEFFREY splice - revised engineered framing sheets 7, 8, & 9 prior to insp. | JEFFREY | JEFFREY | | BSP | T | 4458851 |
SADDLETREE INC. | BFD | C | 12/31/2012 | | BLAKE | BLAKE | | BFD | C | 4447216 |
SADDLETREE INC. | BFN | C | 12/31/2012 | received copy of eng inspection report, soils letter/open excavation report, compaction tests and fdtn design/ minimum of 1.5 inches of float req'd for any walls on slab/ 10 % final grade req'd | BLAKE | BLAKE | | BFN | C | 4447215 |
SADDLETREE INC. | BFT | C | 12/31/2012 | rec'd copy of eng inspection report | BLAKE | BLAKE | | BFT | C | 4447214 |
SADDLETREE INC. | BFN | P | 12/06/2012 | AUTHORIZED INSPECTION BY ENGINEER | KIM | KIM | KIM | BFN | P | 4435760 |
SADDLETREE INC. | BFT | P | 12/06/2012 | AUTHORIZED INSPECTION BY ENGINEER | KIM | KIM | KIM | BFT | P | 4435759 |
D & J QUALITY ELECTRIC INC | E= | C | 05/06/2013 | 20 AMP A.C AND ADDITIONAL A.C PREWIRE | MIKEC | MIKEC | | E= | C | 4518220 |
D & J QUALITY ELECTRIC INC | ES | C | 02/28/2013 | Residential Underground: 200 AMP 3/W NEW RES. | TIMA | TIMA | | ES | C | 4479103 |
D & J QUALITY ELECTRIC INC | ER | C | 02/28/2013 | NO MULTI WIRE #8CU -----100 AMP SUB PANEL OK---FINISHED BASEMENT----- | TIMA | TIMA | | ER | C | 4479102 |
BROWN'S HEATING & COOLING, INC | H= | C | 05/09/2013 | Correction made. | MICHAELS | MICHAELS | | H= | C | 4520654 |
BROWN'S HEATING & COOLING, INC | H= | P | 05/08/2013 | Remove insulation from against b-vent, leakage report received. | MICHAELS | MICHAELS | | H= | P | 4519652 |
BROWN'S HEATING & COOLING, INC | H= | P | 05/06/2013 | Need duct leakage report for attic system, b-vent lacks clearance to insulation in mech, Rest ok. Note: full a/c on attic, a/c rough (lineset only) on basement. | MICHAELS | MICHAELS | | H= | P | 4517934 |
BROWN'S HEATING & COOLING, INC | HC | C | 03/04/2013 | RELEASE METER | JACK | JACK | | HC | C | 4480906 |
BROWN'S HEATING & COOLING, INC | HRR | C | 03/04/2013 | Finished basement both A/C units roughed. | JACK | JACK | | HRR | C | 4480891 |
BROWN'S HEATING & COOLING, INC | HRR | R | 03/01/2013 | No approved plans found on site, Re-inspect all. | MICHAELS | MICHAELS | | HRR | R | 4480043 |
KAMPP-L ENTERPRISES, INC. | HI | C | 02/27/2013 | FURNACE, ATTIC FURNACE, 2- W/H, RNG, BBQ, F/P | LEE | LEE | | HI | C | 4478850 |
KAMPP-L ENTERPRISES, INC. | P= | C | 05/02/2013 | HAS PVB | LEE | LEE | | P= | C | 4516571 |
KAMPP-L ENTERPRISES, INC. | P= | P | 04/30/2013 | WATER TURNED OFF AT METER LOOP -- CAULKING INCOMPLETE -- RE-INSP ALL | LEE | LEE | | P= | P | 4514982 |
KAMPP-L ENTERPRISES, INC. | PTO | C | 02/25/2013 | | LEE | LEE | | PTO | C | 4477114 |
KAMPP-L ENTERPRISES, INC. | PB | C | 02/25/2013 | COMPLETED ON 1-8-13 | LEE | LEE | | PB | C | 4477113 |