E & H COMMERCIAL CONTRACTING | B= | C | 08/28/2013 | All other required Final inspections are complete. (This is a computer generated result) | DALE | DALE | | B= | C | 4594593 |
E & H COMMERCIAL CONTRACTING | B= | P | 08/27/2013 | Additional Inspections Required: External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2). | DALE | DALE | | B= | P | 4593887 |
E & H COMMERCIAL CONTRACTING | B= | P | 06/03/2013 | Additional Inspections Required: External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), ARTISAN PIPE SYSTEMS, INC. Plumbing Final Inspection is not Completed yet, RIAL HEATING & AIR COND, INC Mechanical Final Inspection is not Completed yet, TEAM ELECTRIC, INC. Electrical Final Inspection is not Completed yet. phase 1 ok pending other inspections -- Schedule a new Building Final when above items are complete. | DALE | DALE | | B= | P | 4535680 |
E & H COMMERCIAL CONTRACTING | BFN | C | 05/07/2013 | | DALE | DALE | | BFN | C | 4519385 |
E & H COMMERCIAL CONTRACTING | BFT | C | 05/03/2013 | | DALE | DALE | | BFT | C | 4517459 |
E & H COMMERCIAL CONTRACTING | BFR | P | 05/01/2013 | walls ok pending other inspections | DALE | DALE | | BFR | P | 4515912 |
E & H COMMERCIAL CONTRACTING | BFR | R | 05/01/2013 | | DALE | DALE | | BFR | R | 4515534 |
TEAM ELECTRIC, INC. | E= | C | 08/13/2013 | | BRIAN | BRIAN | | E= | C | 4584342 |
TEAM ELECTRIC, INC. | E= | P | 08/12/2013 | see notes on rough | GARYL | GARYL | | E= | P | 4583430 |
TEAM ELECTRIC, INC. | ER | P | 08/12/2013 | Phase 5 lights and recept's | GARYL | GARYL | | ER | P | 4583410 |
TEAM ELECTRIC, INC. | ER | P | 08/02/2013 | phase 2 ceiling ok., phase 5 ceiling ok | GARYL | GARYL | | ER | P | 4577654 |
TEAM ELECTRIC, INC. | E= | P | 07/29/2013 | PHASE 4 --- E= OK. | BRIAN | BRIAN | | E= | P | 4573604 |
TEAM ELECTRIC, INC. | EUG | C | 07/29/2013 | PHASE 5-- UNDER GROUND OK-- | BRIAN | BRIAN | | EUG | C | 4573597 |
TEAM ELECTRIC, INC. | ER | P | 07/17/2013 | phase 4 ceilings only | GARYL | GARYL | | ER | P | 4565242 |
TEAM ELECTRIC, INC. | ER | R | 07/15/2013 | remove low voltage not in use, and strap and secure up off of ceiling tiles | GARYL | GARYL | | ER | R | 4563127 |
TEAM ELECTRIC, INC. | ESL | P | 07/11/2013 | INTERIOR SLAB | MIKEC | MIKEC | | ESL | P | 4561303 |
TEAM ELECTRIC, INC. | ER | P | 07/05/2013 | | MIKEC | MIKEC | | ER | P | 4557775 |
TEAM ELECTRIC, INC. | E= | P | 06/24/2013 | | MIKEC | MIKEC | | E= | P | 4549141 |
TEAM ELECTRIC, INC. | ER | P | 06/24/2013 | WALLS | MIKEC | MIKEC | | ER | P | 4549126 |
TEAM ELECTRIC, INC. | E= | P | 06/20/2013 | phase 3 ceiling ok only | CRAIG | CRAIG | | E= | P | 4547186 |
TEAM ELECTRIC, INC. | EUG | P | 06/11/2013 | Back room floor boxes 2nd phase | GARYL | GARYL | | EUG | P | 4540962 |
TEAM ELECTRIC, INC. | ER | P | 06/06/2013 | phase 2 front ceiling ok | CRAIG | CRAIG | | ER | P | 4537947 |
TEAM ELECTRIC, INC. | E= | P | 06/06/2013 | phase 2 front counter | CRAIG | CRAIG | | E= | P | 4537939 |
TEAM ELECTRIC, INC. | E= | P | 06/03/2013 | phase 2 front ok ------------- phase 1 check breaker locks for hand dryers in panel on phase 2 back ----------- there are 7 phases to this project | CRAIG | CRAIG | | E= | P | 4535036 |
TEAM ELECTRIC, INC. | ER | R | 05/31/2013 | electric ok , data needs to be ran in the front entrance | GARYL | GARYL | | ER | R | 4534817 |
TEAM ELECTRIC, INC. | EUG | P | 05/03/2013 | 5 -- 3/4 " pvc 4 -- 1 " pvc phase 2 front | CRAIG | CRAIG | | EUG | P | 4516733 |
TEAM ELECTRIC, INC. | ER | P | 05/03/2013 | phase 2 front wall ( west side ) only | CRAIG | CRAIG | | ER | P | 4516732 |
TEAM ELECTRIC, INC. | ER | P | 04/29/2013 | phase 1 wall rough only ok | CRAIG | CRAIG | | ER | P | 4513291 |
TEAM ELECTRIC, INC. | EUG | P | 04/22/2013 | phase one of seven under ground slab ( 5- 3/4 " pvs for power and 1--1" pvc for data ) | CRAIG | CRAIG | | EUG | P | 4509571 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 08/26/2013 | TEST AND BALANCE REPORT RECEIVED. | NANCY | NANCY | | H= | C | 4592958 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 07/15/2013 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 4563435 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | C | 07/15/2013 | NOTE: INTERLOCKS ON WATER HEATER INSTALLED AND OPERATIONAL. | NANCY | NANCY | | HD | C | 4563431 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 07/05/2013 | PHASE 2: PROPERLY SEAL VENT PIPES PER MANUFACTURERS INSTRUCTIONS, SEE PAGE 7 OF INSTALLATION MANUAL.. WILL NEED TO SEE TERMINATION ON ROOF AT FINAL. | NANCY | NANCY | | HD | P | 4557530 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 06/03/2013 | PHASE 1: ABOVE CEILING ALL OK EXCEPT STILL NEED TO SEE SMOKE DETECTORS INSTALLED ON AHU2. PHASE 2: WATER HEATER VENT AND COMBUSTION AIR ABOVE CEILING ALL OK EXCEPT NO INTERLOCKS YET. REST OF PHASE 2 NOT INSTALLED. BEFORE FINAL NEED TO SEE ROOF. | NANCY | NANCY | | HD | P | 4535376 |
ARTISAN PIPE SYSTEMS, INC. | P= | C | 07/05/2013 | | LEE | LEE | | P= | C | 4557615 |
ARTISAN PIPE SYSTEMS, INC. | PTO | P | 06/25/2013 | SINK NOT VENTED PER PLANS -- NO STRUCTURAL CONDITIONS -- IF WANTING TO USE AAV NEED ENGINEER TO APPROVE | LEE | LEE | | PTO | P | 4549882 |
ARTISAN PIPE SYSTEMS, INC. | PB | P | 06/12/2013 | demo'd 3" to sinks stack now turned up in wall phase 2 back portion | TIM | TIM | | PB | P | 4541730 |
ARTISAN PIPE SYSTEMS, INC. | P= | P | 05/22/2013 | PHASE 1 -- FLOOR DRAIN LACKS TRAP GUARD -- W/H T&P LACKS AIR GAP --- STILL NEED SINK ROUGH-IN ON PHASE - 2 | LEE | LEE | | P= | P | 4528568 |
ARTISAN PIPE SYSTEMS, INC. | PTO | P | 04/30/2013 | PHASE 1 OK -- HAMMER ARRESTORS BY FINAL | LEE | LEE | | PTO | P | 4514321 |
ARTISAN PIPE SYSTEMS, INC. | PTO | P | 04/29/2013 | PHASE 1 -- COMPLETE SCREW / NAIL PROTECTION AT W-BOX DWV AND TRAP PRIMER -- SUPPORT DWV IN CEILING TO CODE (EVERY 4' AND HORIZ TO VERTICAL) -- LACKS HAMMER ARRESTORS AT W-BOX -- DWV TEST OK | LEE | LEE | | PTO | P | 4513415 |
ARTISAN PIPE SYSTEMS, INC. | PB | P | 04/22/2013 | PHASE 1 -- STACK FOR 4- SINKS AND FLOOR DRAIN OK | LEE | LEE | | PB | P | 4509544 |