PALACE HOMES, INC. | B= | C | 04/28/2014 | | JOND | JOND | | B= | C | 4728337 |
PALACE HOMES, INC. | B= | P | 04/25/2014 | Additional Inspections Required: External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: enijkamp@springsgov.com or 385-5977). still need to pipe sump pit out / need zoning signed off -- Schedule a new Building Final when above items are complete. | JOND | JOND | | B= | P | 4727375 |
PALACE HOMES, INC. | B= | R | 04/24/2014 | Additional Inspections Required: External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: enijkamp@springsgov.com or 385-5977). handrail not done on inside / need egress ladder in north basement bedroom / touch up final grade / need tempered window by deck stairs landing area / need finger groove at deck handrail / sump pump needs to be piped out and needs pump in it due to water in pit / finished basement | JOND | JOND | | B= | R | 4726276 |
PALACE HOMES, INC. | BFR | C | 03/03/2014 | | JOND | JOND | | BFR | C | 4695851 |
PALACE HOMES, INC. | BLA | C | 02/28/2014 | | JOND | JOND | | BLA | C | 4695232 |
PALACE HOMES, INC. | BFR | R | 02/28/2014 | still missing connection at B1 trusses at middle bearing | JOND | JOND | | BFR | R | 4695229 |
PALACE HOMES, INC. | BIN | P | 02/28/2014 | insulation ok, need frame signed off | JOND | JOND | | BIN | P | 4695226 |
PALACE HOMES, INC. | BFR | R | 02/24/2014 | need middle connection at B1 trusses at common wall / plans call for 2x10 window header at back of house / south windows call for 3 - 2x8 headers / ok to insulate | JOND | JOND | | BFR | R | 4691938 |
PALACE HOMES, INC. | BSP | P | 02/14/2014 | front porch roof,posts and beam ok | BERTW | BERTW | | BSP | P | 4687440 |
PALACE HOMES, INC. | BSP | P | 01/22/2014 | deck piers ok | JOND | JOND | | BSP | P | 4675998 |
PALACE HOMES, INC. | BFI | C | 01/08/2014 | | JOND | JOND | | BFI | C | 4668374 |
PALACE HOMES, INC. | BFD | C | 01/08/2014 | ? on getting walkout door area to have positive drainage | JOND | JOND | | BFD | C | 4668373 |
PALACE HOMES, INC. | BFN | C | 01/02/2014 | new design on file / drain usable area | JOND | JOND | | BFN | C | 4665498 |
PALACE HOMES, INC. | BSP | P | 12/30/2013 | new footer ok | JOND | JOND | | BSP | P | 4664147 |
HOMEOWNER | BSP | T | 11/19/2013 | PAID (REC#1172772) PLAN SPLICE FEE: $54.17 by: DANM for Construction: Splice: Basement changes | DANM | DANM | | BSP | T | 4644462 |
ELEVATION HOMES, LLC | B16 | P | 09/04/2013 | See notes | BOB | BOB | | B16 | P | 4597774 |
ELEVATION HOMES, LLC | BFT | C | 08/16/2013 | engineer letter on file | JOND | JOND | | BFT | C | 4587388 |
ELEVATION HOMES, LLC | BFD | C | 08/16/2013 | | JOND | JOND | | BFD | C | 4587387 |
ELEVATION HOMES, LLC | BFI | C | 08/16/2013 | | JOND | JOND | | BFI | C | 4587386 |
ELEVATION HOMES, LLC | BFN | C | 08/16/2013 | engineer letter on file / design, soils and open hole on file / drain usable area | JOND | JOND | | BFN | C | 4587385 |
ELEVATION HOMES, LLC | BFN | P | 07/02/2013 | AUTHORIZED INSPECTION BY ENGINEER | TERRI | TERRI | TERRI | BFN | P | 4555579 |
ELEVATION HOMES, LLC | BFT | P | 07/02/2013 | AUTHORIZED INSPECTION BY ENGINEER | TERRI | TERRI | TERRI | BFT | P | 4555578 |
PEAK ELECTRIC INC. | E= | C | 04/18/2014 | A.C PREWIRE | MIKEC | MIKEC | | E= | C | 4722841 |
PEAK ELECTRIC INC. | ES | C | 02/21/2014 | Residential Underground: NEW 200 AMP SERVICE | MIKEC | MIKEC | | ES | C | 4691254 |
PEAK ELECTRIC INC. | ER | C | 02/21/2014 | | MIKEC | MIKEC | | ER | C | 4691240 |
AIR CONCEPTS HEATING & COOLING | H= | C | 04/15/2014 | Corrections made. | MICHAELS | MICHAELS | | H= | C | 4720829 |
AIR CONCEPTS HEATING & COOLING | H= | P | 04/10/2014 | Seal furnace termination on outside, need T&P discharge on w/h, rest ok. Note: FB, high/low transfer in wall, a/c rough(coil and lineset), no mantel. | MICHAELS | MICHAELS | | H= | P | 4718373 |
AIR CONCEPTS HEATING & COOLING | HC | C | 02/21/2014 | RELEASE METER | KEITHW | KEITHW | | HC | C | 4690989 |
AIR CONCEPTS HEATING & COOLING | HRR | C | 02/21/2014 | OK NOTES: DIRECT VENT FURNACE, FINISHED BASEMENT, ROUGH A/C WITH COIL AND LINE SET, 6" OSA | KEITHW | KEITHW | | HRR | C | 4690988 |
AIR CONCEPTS HEATING & COOLING | HRR | P | 02/20/2014 | NO MECHANICAL PLANS ON SITE | KEITHW | KEITHW | | HRR | P | 4690198 |
DOUBLE J GAS, INC. | HI | C | 02/19/2014 | 10 PSI TEST OK NOTES: 1 1/4" GAS LINE, FURNACE, WATER HEATER, BBQ, RANGE, FIREPLACE | KEITHW | KEITHW | | HI | C | 4689913 |
JOLLY PLUMBING & HEATING INC. | P= | C | 04/17/2014 | FINISHED BASEMENT, NO IRRIGATION. | DICK | DICK | | P= | C | 4721973 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 02/18/2014 | | TIM | TIM | | PTO | C | 4688127 |
JOLLY PLUMBING & HEATING INC. | PB | C | 01/22/2014 | | LEE | LEE | | PB | C | 4676320 |
JOLLY PLUMBING & HEATING INC. | PB | R | 01/21/2014 | NOT READY BY 3:30 -- NO ATTEMPT TO TEST DWV -- WATER SERVICE INCOMPLETE -- WAIVED TRIP-FEE | LEE | LEE | | PB | R | 4675417 |