ELDER CONSTRUCTION, INC. | B= | C | 10/08/2014 | All other required Final inspections are complete. (This is a computer generated result) | BOBF | BOBF | | B= | C | 4830509 |
ELDER CONSTRUCTION, INC. | B= | P | 08/15/2014 | Additional Inspections Required: External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). building okay / pending Zoning | BOBF | BOBF | | B= | P | 4798181 |
ELDER CONSTRUCTION, INC. | B= | R | 06/26/2014 | Additional Inspections Required: External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), CONTRACT MECHANICAL SVC INC Plumbing Final Inspection is not Completed yet. Stair rails, guards on ramp; stair nosing repaired; plumbing final; unit numbers | JOHNP | JOHNP | | B= | R | 4765756 |
ELDER CONSTRUCTION, INC. | BLA | C | 05/13/2014 | | BOBF | BOBF | | BLA | C | 4737402 |
ELDER CONSTRUCTION, INC. | BLA | P | 05/02/2014 | North & West sides | JOHNP | JOHNP | | BLA | P | 4731531 |
ELDER CONSTRUCTION, INC. | BSP | T | 05/01/2014 | PAID (REC#1192532) ADDITIONAL PLAN REVIEW TIME: $50 From: SHELBY Changes to the residential part of this plan to clearly delineate the scope. See MEP | SHELBY | SHELBY | | BSP | T | 4730969 |
ELDER CONSTRUCTION, INC. | BSP | P | 05/01/2014 | PLAN SPLICE: (No Fee) by: DANM for Construction: Truss changes | DANM | DANM | | BSP | P | 4730932 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/29/2014 | triple 2x12 header in place on west end upper level exterior | BOBF | BOBF | | BSP | P | 4729369 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/17/2014 | | BOBF | BOBF | | BSP | P | 4722293 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/16/2014 | truss laterals okay / additional draftstop at truss break complete | BOBF | BOBF | | BSP | P | 4721753 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/10/2014 | Firecaulk at 2nd floor bath fans OK | JOHNP | JOHNP | | BSP | P | 4717779 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/08/2014 | 2nd floor - firecaulk of new bath fan vents OK | JOHNP | JOHNP | | BSP | P | 4715942 |
ELDER CONSTRUCTION, INC. | BFR | P | 04/04/2014 | Front breeze way walls only -- hold downs OK, need headers/trimmers exposed
| JOHNP | JOHNP | | BFR | P | 4714666 |
ELDER CONSTRUCTION, INC. | BFN | C | 04/01/2014 | Open hole & engineer's inspection letters picked up, no drain required | JOHNP | JOHNP | | BFN | C | 4712300 |
ELDER CONSTRUCTION, INC. | BFT | C | 04/01/2014 | Engineer's inspection letters picked up | JOHNP | JOHNP | | BFT | C | 4712294 |
ELDER CONSTRUCTION, INC. | BSP | P | 04/01/2014 | Trusses - need revised truss engineering, laterals & attic draft stop - Brad - 499-9247 | JOHNP | JOHNP | | BSP | P | 4712291 |
ELDER CONSTRUCTION, INC. | BSP | P | 02/04/2014 | inspections assigned to john p and bob f | BLAKE | BLAKE | | BSP | P | 4682356 |
MATRIX ELECTRIC, INC. | E= | C | 06/03/2014 | SHOW ROOM ON SERATE PERMIT | TIMA | TIMA | | E= | C | 4749854 |
MATRIX ELECTRIC, INC. | E= | P | 06/02/2014 | units are numbered from west to east starting with 101 ..... all units first floor except 103 check smokes for arc fault protection ---- show unit under a different permit and contractor ---- 3ard floor except 303 bed room closet switched with pantry light and bed room light won't come on --------- all of second floor needs inspected | CRAIGS | CRAIGS | | E= | P | 4748967 |
MATRIX ELECTRIC, INC. | E= | R | 05/29/2014 | in all units ensure back of cabinet is cut out with ample room to remove microwave receptacle ---- arc shield or open back of cabinet to allow ample room to remove receptacle --- change receptacle to tamper proof at refer. | CRAIGS | CRAIGS | | E= | R | 4747457 |
MATRIX ELECTRIC, INC. | ER | P | 04/17/2014 | OK to close up walls --- please call in an inspection after all wire is pulled and made up and before devices are installed | CRAIGS | CRAIGS | | ER | P | 4721886 |
MATRIX ELECTRIC, INC. | ER | P | 04/16/2014 | 3rd floor ok to sheet rock ceilings -- need wire pulled and made up for next inspection --- told the general contractor any work done until the prints are revised is at his own risk --- call back in for walls tomorrow | CRAIGS | CRAIGS | | ER | P | 4721126 |
MATRIX ELECTRIC, INC. | ER | R | 04/11/2014 | plans are stamped interior remodel need to conform to 2011 nec --- general contractor to change permit description | CRAIGS | CRAIGS | | ER | R | 4718825 |
MATRIX ELECTRIC, INC. | ER | R | 04/09/2014 | first floor 101--- 106if built in microwave is used need dedicated 20 amp circuit ----- arc fault all modified circuits ---- no permit for spec unit need permit and inspections ( electrician on site said they had nothing to do with it ) | CRAIGS | CRAIGS | | ER | R | 4717013 |
MATRIX ELECTRIC, INC. | ER | P | 04/04/2014 | 2nd floor rough units #201 - 206 --------- inter - lock smoke detectors in each unit | TOMC | TOMC | | ER | P | 4714574 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | H= | C | 04/22/2014 | THIS CONTRACTOR SCOPE OF WORK COMPLETE | ROBERTV | ROBERTV | | H= | C | 4724389 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | H= | P | 04/11/2014 | CHECK ROOF TERMINATIONS, REST OK | ROBERTV | ROBERTV | | H= | P | 4718641 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | C | 04/11/2014 | INSULATION OK. | ROBERTV | ROBERTV | | HD | C | 4718637 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 04/10/2014 | 1ST AND 3RD BATHROOM EXHAUST FANS AND DUCTING OK, NEED INSULATION ON EXPOSED DUCTS IN ATTIC, NEED TO CHECK ROOF TERMINATION AT FINAL. | ROBERTV | ROBERTV | | HD | P | 4717870 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 04/09/2014 | (2ND FLOOR) -- EXHAUST FANS OK, BUILDING WILL LOOK AT PLATE DUCT PENETRATIONS BEFORE CONCEAL | ROBERTV | ROBERTV | | HD | P | 4716982 |
ENVIRONMENTAL HEATING & AIR CONDITIONING INC. | HD | P | 04/03/2014 | SECOND FLOOR. ALL BATHROOM EXHAUST DUCTS ON SECOND FLOOR OK. NO FANS INSTALLED YET, WHEN FANS ARRIVE ON SITE INSTALL AND CALL FOR INSPECTION. BUILDING TO DETERMINE IF VENTS IN ATTIC NEED TO BE IN A CHASE, ALSO TO PROVIDE INFORMATION REGARDING IF THERE IS A SIZE LIMITATION ON ROOF PENETRATIONS. | NANCY | NANCY | | HD | P | 4714197 |
CONTRACT MECHANICAL SVC INC | P= | C | 06/27/2014 | | JOEL | JOEL | | P= | C | 4766857 |
CONTRACT MECHANICAL SVC INC | P= | P | 06/05/2014 | need dishwasher / high loops installed, 302 lacks kitchen sink rest ok except unit 104 its on a separate permit and different contractor | TIM | TIM | | P= | P | 4751678 |
CONTRACT MECHANICAL SVC INC | PTO | C | 04/04/2014 | | TIM | TIM | | PTO | C | 4714559 |