BUILTRITE BUILDERS | B= | C | 08/21/2014 | finished basement, deck in | DALE | DALE | | B= | C | 4801274 |
BUILTRITE BUILDERS | B= | P | 08/19/2014 | Additional Inspections Required: External Agency Inspection HD= by HEALTHDEPT is not Completed yet, Mechanical Final Inspection is not Completed yet, Plumbing Final Inspection is not Completed yet. complete all other inspections / insulate wall at basement / landing at garage -- Schedule a new Building Final when above items are complete. | DALE | DALE | | B= | P | 4799272 |
BUILTRITE BUILDERS | BLA | C | 06/24/2014 | | CHRISM | CHRISM | | BLA | C | 4764577 |
BUILTRITE BUILDERS | BIN | C | 06/12/2014 | | CHRISM | CHRISM | | BIN | C | 4756730 |
BUILTRITE BUILDERS | BFR | C | 06/11/2014 | | CHRISM | CHRISM | | BFR | C | 4756014 |
BUILTRITE BUILDERS | BFR | R | 06/10/2014 | need TBE6 on A6 truss, eng letters for truss details on file | CHRISM | CHRISM | | BFR | R | 4754797 |
BUILTRITE BUILDERS | BFR | R | 06/09/2014 | ok to insulate, back rock electric panel in common wall, truss repair eng letters, ST22 straps @CG2 girder, TBE6s at A6 trusses front wall, chase b-vent and patch roof, HUS28 hangers at AG2 girder, H2.5s at common wall | CHRISM | CHRISM | | BFR | R | 4754007 |
BUILTRITE BUILDERS | BSP | P | 04/18/2014 | rear porch and posts ok, front porch roof ok, no posts | CHRISM | CHRISM | | BSP | P | 4722971 |
BUILTRITE BUILDERS | BSP | R | 04/17/2014 | rear porch roof, missing SDS screws in ledger | CHRISM | CHRISM | | BSP | R | 4722133 |
BUILTRITE BUILDERS | BSP | R | 03/04/2014 | wrong inspection called in | ED | ED | | BSP | R | 4696669 |
BUILTRITE BUILDERS | BSP | R | 03/04/2014 | wrong inspection called in. | ED | ED | | BSP | R | 4696667 |
BUILTRITE BUILDERS | BFI | C | 02/24/2014 | R-10 at walkout walls | CHRISM | CHRISM | | BFI | C | 4691926 |
BUILTRITE BUILDERS | BFD | C | 02/24/2014 | soils on file drain usable isolate and float | CHRISM | CHRISM | | BFD | C | 4691925 |
BUILTRITE BUILDERS | BFN | C | 02/24/2014 | design and eng report on file | CHRISM | CHRISM | | BFN | C | 4691924 |
BUILTRITE BUILDERS | BFT | C | 02/24/2014 | eng report on file | CHRISM | CHRISM | | BFT | C | 4691917 |
BUILTRITE BUILDERS | BFN | P | 02/06/2014 | AUTHORIZED INSPECTION BY ENGINEER | BPHILLIPS | BPHILLIPS | BPHILLIPS | BFN | P | 4683657 |
BUILTRITE BUILDERS | BFT | P | 02/06/2014 | AUTHORIZED INSPECTION BY ENGINEER | BPHILLIPS | BPHILLIPS | BPHILLIPS | BFT | P | 4683656 |
POSITIVE ELECTRIC, LLC | E= | C | 08/04/2014 | back deck soffit outlets have been blanked for final- ------- 40 amp a/c-------- | MATTHEW | MATTHEW | | E= | C | 4789580 |
POSITIVE ELECTRIC, LLC | E= | R | 08/01/2014 | can't have gfci test in soffit above back deck | MATTHEW | MATTHEW | | E= | R | 4789034 |
POSITIVE ELECTRIC, LLC | E= | R | 07/31/2014 | remove wiring to garage floor outlet, correct basement bedroom closet light clearance, no power to basement bedroom smoke, where's the ufer?, where's the gfci protection for x-mas lights, -----------wet bar rough only, master bath light above tub not installed at time of final, -----------------40 amp a/c ok--------------- | MATTHEW | MATTHEW | | E= | R | 4787936 |
POSITIVE ELECTRIC, LLC | ER+ | C | 06/11/2014 | 2/0 ser to sub - panel | TOMC | TOMC | | ER+ | C | 4756081 |
POSITIVE ELECTRIC, LLC | ER | C | 05/23/2014 | finished basement, 2-20 | MATTHEW | MATTHEW | | ER | C | 4745070 |
POSITIVE ELECTRIC, LLC | ES | C | 05/23/2014 | Residential Underground: 200 amp 3/w: new res------- meter is set need seal | MATTHEW | MATTHEW | | ES | C | 4745063 |
POSITIVE ELECTRIC, LLC | ER | R | 05/21/2014 | NOT READY---- | BRIAN | BRIAN | | ER | R | 4743085 |
POSITIVE ELECTRIC, LLC | ES | R | 05/21/2014 | Not ready----------------------- | BRIAN | BRIAN | | ES | R | 4743084 |
POSITIVE ELECTRIC, LLC | EUG | C | 03/03/2014 | 4/0 urd ok pvc box in slab ok | TOMC | TOMC | | EUG | C | 4695970 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | C | 08/19/2014 | finished basement, a/c installed, transfer openings | TED | TED | | H= | C | 4799564 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HC | C | 06/03/2014 | RELEASE METER | MARK | MARK | | HC | C | 4750174 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | C | 06/03/2014 | Return corrected. Ok. | MARK | MARK | | HRR | C | 4750172 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | P | 05/30/2014 | Still need to pan off the return under bath tub on main level. Rest ok. | MARK | MARK | | HRR | P | 4748431 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | P | 05/29/2014 | Need panning for return under tub on main level. B vent on main level coming undone at ceiling height. Need to secure. Note: Fin Bsmnt and a/c rough. | MARK | MARK | | HRR | P | 4747413 |
RIDGEVIEW PLUMBING | HI | C | 05/15/2014 | 1 1/4'' furnace, 2-water heaters, 2-fireplaces, 2-bbq | TED | TED | | HI | C | 4739506 |
RIDGEVIEW PLUMBING | P= | C | 08/15/2014 | potable water certificate sent to scanning. rest ok, pvb installed, finished basement. | DICK | DICK | | P= | C | 4798227 |
RIDGEVIEW PLUMBING | PTO | C | 05/15/2014 | POTABLE WATER CERTIFICATE BY FINAL. | GABE | GABE | | PTO | C | 4739165 |
RIDGEVIEW PLUMBING | PWO | C | 03/05/2014 | | TIM | TIM | | PWO | C | 4697198 |
RIDGEVIEW PLUMBING | PB | C | 03/04/2014 | base ok. | DICK | DICK | | PB | C | 4696039 |
RIDGEVIEW PLUMBING | PB | P | 02/28/2014 | pending stub out under foundation. | DICK | DICK | | PB | P | 4695365 |