GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 09/29/2014 | All other required Final inspections are complete. (This is a computer generated result) | BERTW | BERTW | | B= | C | 4824850 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 07/22/2014 | Additional Inspections Required: External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), COLORADO SHEET METAL CO., INC. Mechanical Final Inspection is not Completed yet. | BERTW | BERTW | | B= | P | 4781091 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 07/22/2014 | | BERTW | BERTW | | BFR | C | 4781064 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 06/17/2014 | Firecaulk corridor wall complete | JOHNP | JOHNP | | BSP | P | 4759385 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/13/2014 | framing for fluoro room #1002 and DBL door entry framing as noted on approved plans sheet A110; will need inspection above DBL door for smoke partition
| DAN | DAN | | BFR | P | 4757359 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 05/12/2014 | inspections assigned to bert or john p | BLAKE | BLAKE | | BSP | P | 4736724 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 05/12/2014 | Phase 1 walls OK | JOHNP | JOHNP | | BFR | P | 4736681 |
GREEN ELECTRIC INC | E= | C | 09/29/2014 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 4824864 |
GREEN ELECTRIC INC | E= | C | 09/29/2014 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 4824849 |
GREEN ELECTRIC INC | E= | C | 07/07/2014 | | CRAIGS | CRAIGS | | E= | C | 4771670 |
GREEN ELECTRIC INC | ER | C | 07/02/2014 | | CRAIGS | CRAIGS | | ER | C | 4770490 |
GREEN ELECTRIC INC | ER | R | 07/01/2014 | need each end of every fixture tiles removed so i can see fixture supports ----- can't look from one spot and see other fixtures ----- DO NOT ! Cover ceilings until inspections are completed !!!!!!!!!!! | CRAIGS | CRAIGS | | ER | R | 4769166 |
GREEN ELECTRIC INC | ER | R | 06/13/2014 | x ray walls #1 inspected by craig 6/13 | BRET | BRET | | ER | R | 4757305 |
GREEN ELECTRIC INC | ER | P | 06/12/2014 | room 1 walls OK | CRAIGS | CRAIGS | | ER | P | 4759135 |
GREEN ELECTRIC INC | ER | C | 05/21/2014 | | CRAIGS | CRAIGS | | ER | C | 4742865 |
GREEN ELECTRIC INC | ER | C | 05/21/2014 | FIRE ALARM INSPECTION: | CRAIGS | CRAIGS | | ER | C | 4742862 |
GREEN ELECTRIC INC | ER | P | 05/12/2014 | FIRE ALARM INSPECTION: BOX AND STUB IN X-RAY #2 | BRIAN | BRIAN | | ER | P | 4737039 |
GREEN ELECTRIC INC | ER | P | 05/12/2014 | WALLS IN X-RAY # 2 | BRIAN | BRIAN | | ER | P | 4737035 |
COLORADO SHEET METAL CO., INC. | H= | C | 07/25/2014 | TEST AND BALANCE REPORT RECEIVED AND SCANNED. LETTER FROM ENGINEER APPROVING REPORT DUE TO LOW CFM READINGS ON DD-06 RECEIVED AND SCANNED. | NANCY | NANCY | | H= | C | 4784596 |
COLORADO SHEET METAL CO., INC. | HD | C | 07/08/2014 | ULTRASOUND DD1-20 AND 1-21 OK, OK TO WRAP. FLEX AND DIFFUSERS OK. HALL DD1-7 OK, OK TO WRAP. FLUORO ROOM 1 AND FLUORO CONTROL ROOMS ABOVE CEILING ALL OK AND COMPLETE, FOR FINAL PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | HD | C | 4772174 |
COLORADO SHEET METAL CO., INC. | HD | P | 06/19/2014 | FLUORO SUB WAIT AREA: DD1-12 AND DUCT OK, OK TO WRAP. FLUORO 1 CONTROL ROOM: SUPPLY GOING INTO CONTROL ROOM OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 4761431 |
COLORADO SHEET METAL CO., INC. | HD | P | 05/21/2014 | FLUORO ROOM 2: ABOVE CEILING ALL OK. | NANCY | NANCY | | HD | P | 4743020 |