PEAK PROFESSIONAL CONTRS INC | B= | C | 08/26/2015 | | BERTW | BERTW | | B= | C | 5022799 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 08/05/2015 | all items from previous inspection complete except there is a space larger than 4" sphere at guard rail on patio where it meets the building wall -- Schedule a new Building Final when above items are complete. | DANE | DANE | | B= | P | 5008275 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 06/22/2015 | 1)main exterior stairs missing handrails per approved plans 2)rear stairs >6" sphere @ tread riser areas both stairs 3)install all accessible parking signs per approved plans 4)install guard rail system per plans @ south patio area -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | BERTW | BERTW | | B= | P | 4978077 |
PEAK PROFESSIONAL CONTRS INC | BFR | C | 05/08/2015 | Engineer letter from Mike Orsillo, #17931 for Structural elements of building picked up 4/22/15 and reviewed 5/8/15 , and per phone conversation with Jeremy completes framing. | DAN | DAN | | BFR | C | 4951769 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 04/22/2015 | Exterior wall framing OK / Letter on file for structural steel | JEREMYA | JEREMYA | | BFR | P | 4940395 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 04/21/2015 | Inspected all fire retardant treated plywood used in EIFIS assembly | JEREMYA | JEREMYA | | BSP | P | 4939587 |
FENTON PLUMBING & HEATING INC | BSP | T | 03/16/2015 | PAID (REC#1250515) PLAN SPLICE FEE: $50 by: RUSSELL for Mechanical: Revised gas to 3 suites | RUSSELL | RUSSELL | | BSP | T | 4917308 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 02/10/2015 | Bond beam at tops of walls for planters at south side of building OK | JEREMYA | JEREMYA | | BSP | P | 4899872 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 01/29/2015 | Footings for wall and planters at front of building OK | JEREMYA | JEREMYA | | BSP | P | 4892842 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 01/28/2015 | PLAN SPLICE: (No Fee) by: SHELLEY for Construction: revised detail for retaining wall | SHELLEY | SHELLEY | | BSP | P | 4892423 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 01/27/2015 | Open hole on file for retaining wall at front of building | JEREMYA | JEREMYA | | BSP | P | 4890936 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 01/20/2015 | inspection for rear ramp areas footings for CMU walls ok pending open hole report/IE line,I6 thru I13 ok see details on S.1 and S1,1 detail A.2__________notice retaining wall in front of building footing was not inspected due to not part of foundation design in approved plan set- contractor to get with PM and resolve this before any inspections can be done on this area of job | BERTW | BERTW | | BSP | P | 4887490 |
FENTON PLUMBING & HEATING INC | BSP | T | 01/07/2015 | PAID (REC#1240081) ADDITIONAL PLAN REVIEW TIME: $50 From: TCRIPPEN new splice pages see plan review notes | TCRIPPEN | TCRIPPEN | | BSP | T | 4881839 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 01/06/2015 | Roof insulation OK | JEREMYA | JEREMYA | | BSP | P | 4880802 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 12/23/2014 | R-21.1 installed at roof deck OK | JEREMYA | JEREMYA | | BSP | P | 4877049 |
PEAK PROFESSIONAL CONTRS INC | BBB | C | 10/24/2014 | | JOHNP | JOHNP | | BBB | C | 4841240 |
PEAK PROFESSIONAL CONTRS INC | BFT | C | 10/23/2014 | Pad cap on entry pad | JOHNP | JOHNP | | BFT | C | 4840380 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 10/16/2014 | Canopy pads OK, need open excavation observation letter | JOHNP | JOHNP | | BFT | P | 4835747 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 10/15/2014 | Line E, 6-8; bearing & top of wall. Line K - bearing (pending letter from engineer) & top of wall | JOHNP | JOHNP | | BBB | P | 4834802 |
PEAK PROFESSIONAL CONTRS INC | BBB | R | 10/14/2014 | Not ready | JOHNP | JOHNP | | BBB | R | 4833859 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 10/13/2014 | ok for hcda eng to do bond beam inspection at grid K | BLAKE | BLAKE | | BBB | P | 4833460 |
PEAK PROFESSIONAL CONTRS INC | BBB | R | 10/09/2014 | Canceled | JOHNP | JOHNP | | BBB | R | 4831619 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 10/08/2014 | I 5.7 grid line - truss bearing & top of wall - OK | JOHNP | JOHNP | | BBB | P | 4830612 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 10/06/2014 | North wall - top of wall; West wall, North 1/2 - 20'4" -- Both OK | JOHNP | JOHNP | | BBB | P | 4828727 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 10/02/2014 | Open excavation letter picked up | JOHNP | JOHNP | | BFT | P | 4827110 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 10/02/2014 | Grid line E @ 16'3"; Grid line 13 @ lintles | JOHNP | JOHNP | | BBB | P | 4827108 |
PEAK PROFESSIONAL CONTRS INC | BFI | C | 09/04/2014 | | JEREMYA | JEREMYA | | BFI | C | 4809985 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 08/08/2014 | Footings OK / Partial pending all exterior pads | JEREMYA | JEREMYA | | BFT | P | 4793305 |
EL PASO ELECTRIC, LLC. | E= | C | 06/17/2015 | | MIKEC | MIKEC | | E= | C | 4974966 |
EL PASO ELECTRIC, LLC. | E= | C | 06/03/2015 | FIRE ALARM INSPECTION: | MIKEC | MIKEC | | E= | C | 4965809 |
EL PASO ELECTRIC, LLC. | ER | C | 06/03/2015 | FIRE ALARM INSPECTION: | MIKEC | MIKEC | | ER | C | 4965806 |
EL PASO ELECTRIC, LLC. | EUG | P | 03/25/2015 | INTERIOR SLAB WEST SIDE | MIKEC | MIKEC | | EUG | P | 4923123 |
EL PASO ELECTRIC, LLC. | EUG | P | 03/16/2015 | No one on site, walked it with Joe the superintendent, tele for bldg I is ok, and pedestrian walk way to damaged light feed ok to cover in front of bldg | GARYL | GARYL | | EUG | P | 4917353 |
EL PASO ELECTRIC, LLC. | EUG | R | 03/12/2015 | NOT READY | MIKEC | MIKEC | | EUG | R | 4916101 |
EL PASO ELECTRIC, LLC. | ES | C | 02/20/2015 | Commercial Service: NEW 200 AMP 3PH 4W 120/208V NEED HOUSE METER SET FED FROM BUSSED GUTTER | MIKEC | MIKEC | | ES | C | 4906709 |
EL PASO ELECTRIC, LLC. | ES | R | 02/18/2015 | NOT READY | MIKEC | MIKEC | | ES | R | 4904709 |
EL PASO ELECTRIC, LLC. | ER | P | 01/12/2015 | EXTERIOR SOFFIT LIGHTS | MIKEC | MIKEC | | ER | P | 4883843 |
FENTON PLUMBING & HEATING INC | H= | C | 05/06/2015 | GAS FINAL OK. NOTE: ONLY TWO METERS SET FOR SHELL FINAL. | NANCY | NANCY | | H= | C | 4949940 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 04/30/2015 | MECHANICAL FINAL OK. | NANCY | NANCY | | H= | C | 4946432 |
FENTON PLUMBING & HEATING INC | HC | C | 04/02/2015 | OK TO SET METERS FOR UNITS 100, 120, 130, 140, 150, 160, 180 AND 190 (ALL UNITS ON THIS BUILDING). | NANCY | NANCY | | HC | C | 4928562 |
FENTON PLUMBING & HEATING INC | HI | C | 04/02/2015 | UNIT 160: TWO 10 LB TESTS OK. | NANCY | NANCY | | HI | C | 4928552 |
FENTON PLUMBING & HEATING INC | HC | P | 04/01/2015 | OK FOR METER RELEASE ON THE FOLLOWING UNITS - 100 - 120 - 130 - 140 - 150 - 180 - 190 | JERRYF | JERRYF | | HC | P | 4927796 |
FENTON PLUMBING & HEATING INC | HI | P | 04/01/2015 | TEST OK ON THE FOLLOWING UNITS 100 - 120 - 130 - 140 - 150 - 180 - 190 - LOW TEST ON GROUND AND ROOF GAUGES ON 160 MEDIUM PRESSURE - NEED MEDIUM LABELS ON ROOF COMPLETED RETEST AND RE INSPECT THIS LINE - ALL PIPING PER PLAN - - REST OK | JERRYF | JERRYF | | HI | P | 4927795 |
FENTON PLUMBING & HEATING INC | HC | L | 02/25/2015 | NOT READY | JERRYF | JERRYF | | HC | L | 4908219 |
FENTON PLUMBING & HEATING INC | HI | L | 02/25/2015 | NEED APPROVED PLANS - NO PERSONNEL ONSITE TO CHECK FOR PLANS - NEED ALL PERMANENT SUITE LABELS IN PLACE FOR METER RELEASE - ROOF TO ICY - STOPPED INSPECTION | JERRYF | JERRYF | | HI | L | 4908218 |
FENTON PLUMBING & HEATING INC | P= | C | 05/15/2015 | core and shell plumbing complete. | DICK | DICK | | P= | C | 4955613 |
FENTON PLUMBING & HEATING INC | PTO | C | 05/15/2015 | core and shell plumbing rough complete. | DICK | DICK | | PTO | C | 4955598 |
FENTON PLUMBING & HEATING INC | PRD | C | 03/27/2015 | ok | DICK | DICK | | PRD | C | 4924764 |
FENTON PLUMBING & HEATING INC | PRD | P | 12/15/2014 | underground roof drains o.k | JOEL | JOEL | | PRD | P | 4871571 |
FENTON PLUMBING & HEATING INC | PB | C | 12/12/2014 | | JOEL | JOEL | | PB | C | 4870416 |
FENTON PLUMBING & HEATING INC | PB | P | 12/11/2014 | east side grease line needs test, sanitary o.k | JOEL | JOEL | | PB | P | 4869806 |
FENTON PLUMBING & HEATING INC | PRD | P | 12/11/2014 | cannot use sdr 35 pipe into building | JOEL | JOEL | | PRD | P | 4869799 |