BECKRICH CONSTRUCTION, LLC. | B= | C | 05/13/2015 | All other required Final inspections are complete. (This is a computer generated result) | DALE | DALE | | B= | C | 4953452 |
BECKRICH CONSTRUCTION, LLC. | B= | P | 05/07/2015 | finished basement, deck in. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | DALE | DALE | | B= | P | 4951116 |
BECKRICH CONSTRUCTION, LLC. | BIN | C | 12/22/2014 | | DAN | DAN | | BIN | C | 4876705 |
BECKRICH CONSTRUCTION, LLC. | BLA | P | 12/19/2014 | columns not complete? | DALE | DALE | | BLA | P | 4875505 |
BECKRICH CONSTRUCTION, LLC. | BFR | C | 12/17/2014 | | DALE | DALE | | BFR | C | 4873762 |
BECKRICH CONSTRUCTION, LLC. | BSP | T | 12/12/2014 | PAID (REC#1237148) PLAN SPLICE FEE: $50 by: DANM for Construction: Revised beams on main level floor and deck ledger | DANM | DANM | | BSP | T | 4870950 |
BECKRICH CONSTRUCTION, LLC. | BSP | P | 12/05/2014 | porch posts ok | DALE | DALE | | BSP | P | 4865859 |
BECKRICH CONSTRUCTION, LLC. | BSP | P | 12/02/2014 | porch lid ok, no posts / rear deck frame ok | DALE | DALE | | BSP | P | 4863010 |
BECKRICH CONSTRUCTION, LLC. | BSP | P | 11/10/2014 | porch piers ok | DALE | DALE | | BSP | P | 4851405 |
BECKRICH CONSTRUCTION, LLC. | BFD | C | 09/12/2014 | | DALE | DALE | | BFD | C | 4814897 |
BECKRICH CONSTRUCTION, LLC. | BFI | C | 09/12/2014 | | DALE | DALE | | BFI | C | 4814887 |
BECKRICH CONSTRUCTION, LLC. | BFN | C | 09/08/2014 | drain usable / float / ufer in | DALE | DALE | | BFN | C | 4811374 |
BECKRICH CONSTRUCTION, LLC. | BFT | P | 09/05/2014 | need open hole, ok to pour at own risk, rear pads (circled and dated ) on plans ok as well | ED | ED | | BFT | P | 4810811 |
HOMERUN ELECTRONICS, INC. | E= | C | 05/04/2015 | 30 amp a/c | MATTHEW | MATTHEW | | E= | C | 4948666 |
HOMERUN ELECTRONICS, INC. | ES | C | 11/25/2014 | Residential Underground: 200 amp 3/w new res. seal meter | CRAIG | CRAIG | | ES | C | 4860056 |
HOMERUN ELECTRONICS, INC. | ER | C | 11/25/2014 | 3 - 20 2 - 10/3 6/3 cu 2 - 6/3 al finished basement | CRAIG | CRAIG | | ER | C | 4860052 |
HOMERUN ELECTRONICS, INC. | EUG | C | 10/08/2014 | service lateral ran from pole to home | MATTHEW | MATTHEW | | EUG | C | 4831065 |
BRUNO'S MECHANICAL INC. | H= | C | 05/05/2015 | correction made | TED | TED | | H= | C | 4949311 |
BRUNO'S MECHANICAL INC. | H= | R | 04/28/2015 | Unable to inspect, floors being finished. | MARK | MARK | | H= | R | 4944312 |
BRUNO'S MECHANICAL INC. | H= | T | 04/24/2015 | PAID (REC#1258207): no fireplace install paper work found, rest ok, transfer openings installed | TED | TED | | H= | T | 4942484 |
BRUNO'S MECHANICAL INC. | H= | R | 04/16/2015 | need paper work for both fireplaces to check mantel clearance, need combustion air for water heater, mech. room not large enough for 40,000 btu water heater, need clearance around water heater b vent from pex, note: finished basement, a/c installed | TED | TED | | H= | R | 4937211 |
BRUNO'S HEATING & COOLING | HC | C | 12/16/2014 | RELEASE METER | MICHAELS | MICHAELS | | HC | C | 4872701 |
BRUNO'S HEATING & COOLING | HRR | C | 12/16/2014 | Correction made. | MICHAELS | MICHAELS | | HRR | C | 4872699 |
BRUNO'S HEATING & COOLING | HRR | P | 12/15/2014 | Fireplaces still lack clearance on sides, other correction made. Trip fee waived. | MICHAELS | MICHAELS | | HRR | P | 4871417 |
BRUNO'S HEATING & COOLING | HRR | P | 12/04/2014 | Fireplaces lack clearance to framing on sides, dryer vent lacks nail protection, rest ok. Note: duct design, finished basement, 6" osa, a/c rough(coil and lineset), direct vent furnace. AT FINAL: check door hardware to vault or fan switch for ventilation in vault. | MICHAELS | MICHAELS | | HRR | P | 4865118 |
DOUBLE J GAS, INC. | HI | C | 11/14/2014 | 10 lb test ok. Note: 1 1/4" main. F, w/h, rng, 2- f/p and fut. bbq. | MARK | MARK | | HI | C | 4853699 |
PACIFIC PLUMBING, INCORPORATED | P= | C | 05/04/2015 | CORRECTIONS MADE , POTABLE WATER CERT TO SCANNING | GABE | GABE | | P= | C | 4948216 |
PACIFIC PLUMBING, INCORPORATED | P= | P | 05/01/2015 | loose shower arm at master, anchor hose bib in front of house, only allowed maximum 6 inches above floor for T/P drain, need potable water cert, rest ok, pvb installed, finished basement. | TAYLOR | TAYLOR | | P= | P | 4947925 |
HOMEOWNER | PWO | C | 12/02/2014 | POTABLE WATER CERT BY FINAL | GABE | GABE | | PWO | C | 4863071 |
PACIFIC PLUMBING, INCORPORATED | PTO | C | 11/12/2014 | NOTE : FINISHED BASEMENT .PVB INSTALLED . POTABLE WATER CERT BY FINAL | GABE | GABE | | PTO | C | 4852434 |
PACIFIC PLUMBING, INCORPORATED | PB | C | 09/19/2014 | WATER STUBBED UNDER FOOTER. | GABE | GABE | | PB | C | 4819523 |