CONSTRUCTION BY GENESIS, INC. | B= | C | 07/06/2015 | All other required Final inspections are complete. (This is a computer generated result) | TOMG | TOMG | | B= | C | 4986471 |
CONSTRUCTION BY GENESIS, INC. | B= | P | 06/16/2015 | . Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | TOMG | TOMG | | B= | P | 4974457 |
CONSTRUCTION BY GENESIS, INC. | BLA | C | 02/12/2015 | items from previous inspection complete | DANE | DANE | | BLA | C | 4901773 |
CONSTRUCTION BY GENESIS, INC. | BLA | R | 02/06/2015 | lath not complete around door to deck and door to patio and window in walk out/need box extension on light at garage service door | DANE | DANE | | BLA | R | 4897955 |
CONSTRUCTION BY GENESIS, INC. | BIN | C | 02/06/2015 | | DANE | DANE | | BIN | C | 4897952 |
CONSTRUCTION BY GENESIS, INC. | BFR | C | 02/02/2015 | items from previous inspection complete | DANE | DANE | | BFR | C | 4894702 |
CONSTRUCTION BY GENESIS, INC. | BFR | P | 01/27/2015 | OK to insulate/attach steel beam between garage doors to steel post/window at front in living room calls for 3K each end/need HTS16 at T19 at rear of 3rd car bay/nail off hanger on T46 truss/need hardware on joists over powder room that are resting on non-bearing wall/secure bottom of steel post in front east bedroom in basement/secure top plate of steel post to beam in rec room/nail off inverted hangers at floor joists in gargae | DANE | DANE | | BFR | P | 4891156 |
CONSTRUCTION BY GENESIS, INC. | BSP | R | 12/26/2014 | cancelled over phone by Ed | JOND | JOND | | BSP | R | 4877963 |
CONSTRUCTION BY GENESIS, INC. | BTR | C | 12/17/2014 | spoke with ed 334-1021 of genesis homes/ front porch roof will be a copper product that does not require batten strips | BLAKE | BLAKE | | BTR | C | 4873046 |
CONSTRUCTION BY GENESIS, INC. | BTR | R | 12/16/2014 | front porch area still not done (no batten strips installed) at 2:53 pm/ pay trip fee and recall when ready/ trip fee waived 12/17 after conversation with ed | BLAKE | BLAKE | | BTR | R | 4872802 |
CONSTRUCTION BY GENESIS, INC. | BTR | R | 12/08/2014 | not done over front porch / need to daylight sidewall flashings | JOND | JOND | | BTR | R | 4867254 |
CONSTRUCTION BY GENESIS, INC. | BSP | P | 11/06/2014 | portal frame ok, will check straps at frame | JOND | JOND | | BSP | P | 4849534 |
CONSTRUCTION BY GENESIS, INC. | BSP | R | 11/05/2014 | front and rear porch ok / portal frame at garage header not done, missing straps | JOND | JOND | | BSP | R | 4849082 |
CONSTRUCTION BY GENESIS, INC. | BSP | P | 10/13/2014 | piers ok | JOND | JOND | | BSP | P | 4833670 |
CONSTRUCTION BY GENESIS, INC. | BFT | C | 10/06/2014 | engineer letter on file | JOND | JOND | | BFT | C | 4829179 |
CONSTRUCTION BY GENESIS, INC. | BFN | C | 10/06/2014 | engineer letter on file / design, open hole and soils report on file / drain usable area | JOND | JOND | | BFN | C | 4829178 |
CONSTRUCTION BY GENESIS, INC. | BFD | C | 10/06/2014 | | JOND | JOND | | BFD | C | 4829177 |
CONSTRUCTION BY GENESIS, INC. | BFI | C | 10/06/2014 | | JOND | JOND | | BFI | C | 4829175 |
POSITIVE ELECTRIC, LLC | E= | C | 06/05/2015 | 1-30 1-40 AMP A.C'S | MIKEC | MIKEC | | E= | C | 4968190 |
POSITIVE ELECTRIC, LLC | ER | C | 01/07/2015 | | MIKEC | MIKEC | | ER | C | 4881898 |
POSITIVE ELECTRIC, LLC | ES | C | 01/07/2015 | Residential Underground: NEW 200 AMP SERVICE | MIKEC | MIKEC | | ES | C | 4881801 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | C | 06/09/2015 | Duct leakage report received. | STEVEC | STEVEC | | H= | C | 4970000 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | P | 06/08/2015 | Pending duct leakage report. Note: self closing sealed door to basement bedroom, mantle clearances good, rest o.k. | STEVEC | STEVEC | | H= | P | 4968817 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HC | C | 01/13/2015 | RELEASE METER | KEITHW | KEITHW | | HC | C | 4884418 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | C | 01/13/2015 | ALL ISSUES RESOLVED NOTES: COMBUSTION AIR AT FINAL, WILL NEED SELF-CLOSING DOOR TO MECHANICAL ROOM, DIRECT VENT FURNACE AND BOILER, ROUGH A/C | KEITHW | KEITHW | | HRR | C | 4884417 |
CORNERSTONE PLUMBING INC | HI | C | 01/05/2015 | 10 PSI TEST OK | KEITHW | KEITHW | | HI | C | 4880552 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | P | 12/30/2014 | Boiler terminations turned up (need boiler and venting instructions ). Missing return air panning in bed 5 ceiling (end cap?). Has craft room been turned into bedroom (mech access through room). Basement fireplace vent lacks clearance (re inspect to roof). Framing to living room fireplace too low (bowing clearance plate). Need proper nail protection for dryer duct. Equipment and duct match design. By final - need duct leakage report. At final - Combustion air to mech, mech door with closer?, condensate lines and vent terminations. Note: 6" OSA to return, finished basement and A/C rough. | MARKB | MARKB | | HRR | P | 4878964 |
CORNERSTONE PLUMBING INC | HI | P | 12/29/2014 | LOW TEST. 2 INCH LINE IN. 1 FURNACE, 2 WATER HEATERS, 1 BOILER, 1 RANGE, 3 FIREPLACES, 1 BBQ (ON DECK), 1 FUTURE FIREPIT ( 195,000 BTU'S MAX WHEN INSTALLED). | NANCY | NANCY | | HI | P | 4878631 |
J D PLUMBING AND HEATING LLC | P= | C | 05/20/2015 | finished basement, pvb installed | DICK | DICK | | P= | C | 4958104 |
J D PLUMBING AND HEATING LLC | P= | T | 05/19/2015 | PAID (REC#1262808) house locked 1:45 | DICK | DICK | | P= | T | 4957332 |
J D PLUMBING AND HEATING LLC | PTO | C | 11/24/2014 | NOTE : FINISHED BASEMENT , IRRIGATION STUB . FALL PROTECTION REQUIRED | GABE | GABE | | PTO | C | 4859621 |
J D PLUMBING AND HEATING LLC | PB | C | 10/10/2014 | | LEE | LEE | | PB | C | 4833002 |