R.G. BRINKMANN COMPANY | B= | C | 11/16/2015 | | JANE | JANE | | B= | C | 5080101 |
R.G. BRINKMANN COMPANY | B= | P | 10/19/2015 | Temp CO: Temp CO: okay per John Welton to give another TCO. ( Expires: 11/18/2015 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 5060455 |
R.G. BRINKMANN COMPANY | B= | P | 09/03/2015 | Temp CO: need more time with getting zoning signed off ( Expires: 10/3/2015 12:00:00 AM) | REBECCA | REBECCA | | B= | P | 5029434 |
R.G. BRINKMANN COMPANY | B= | P | 08/05/2015 | Temp CO: partials for some departments ( Expires: 9/4/2015 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 5007991 |
R.G. BRINKMANN COMPANY | B= | P | 08/04/2015 | . Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: Janet at 322-2028), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, FRONTIER MECHANICAL INC Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 5007512 |
R.G. BRINKMANN COMPANY | B= | P | 07/31/2015 | replace all thumb turn bolts at front doors and ALL vision center doors with double keyed cylinders / need all MEP's and outside agencies completed. -- Schedule a new Building Final when above items are complete. | NATHAN | NATHAN | | B= | P | 5005523 |
R.G. BRINKMANN COMPANY | B= | P | 07/02/2015 | need all final inspections, need shelving and columns bolted to floor / all outside agencies must be have partialed final inspections, THIS IS NOT A FINAL INSPECTION. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection Z= by ZONINGF is not Completed yet (Contact: Janet at 322-2028), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BOCHNAK MECHANICAL, INC. Mechanical Final Inspection is not Completed yet, BOCHNAK MECHANICAL, INC. Plumbing Final Inspection is not Completed yet, FRONTIER MECHANICAL INC Mechanical Final Inspection is not Completed yet, MARK YOUNG CONSTRUCTION, INC. Electrical Final Inspection is not Completed yet, MARK YOUNG CONSTRUCTION, INC. Mechanical Final Inspection is not Completed yet, MORNING STAR ELEVATOR, LLC. Mechani | NATHAN | NATHAN | | B= | P | 4986282 |
R.G. BRINKMANN COMPANY | BSP | P | 06/05/2015 | no inspection is needed for grid ceiling installation | NATHAN | NATHAN | | BSP | P | 4967420 |
R.G. BRINKMANN COMPANY | BFR | P | 05/11/2015 | need all tops of walls and deli bulkhead braced to rigid ceiling / frame okay otherwise at all walls between 11-8, B-F. | NATHAN | NATHAN | | BFR | P | 4952056 |
R.G. BRINKMANN COMPANY | BSP | T | 05/06/2015 | PAID (REC#1260512) ADDITIONAL PLAN REVIEW TIME: $50 From: TCRIPPEN new splice | TCRIPPEN | TCRIPPEN | | BSP | T | 4950316 |
R.G. BRINKMANN COMPANY | BFR | P | 05/06/2015 | with all completed required inspection light steel framing at 5 line south to 1 line and A-H is okay | NATHAN | NATHAN | | BFR | P | 4949946 |
R.G. BRINKMANN COMPANY | BFR | R | 05/05/2015 | All superintendents in a meeting and I do not know what was called in for inspection. Recall inspection at your convenience. | NATHAN | NATHAN | | BFR | R | 4948966 |
R.G. BRINKMANN COMPANY | BFR | P | 05/01/2015 | ALL LIGHT STEEL STUD WALLS AND HARD LID AT 1-3.5AND H-E.3 OKAY WITH ALL COMPLETED REQUIRED INSPECTIONS | NATHAN | NATHAN | | BFR | P | 4947331 |
R.G. BRINKMANN COMPANY | BFR | P | 04/30/2015 | bathroom walls, backing with hardlid frame okay and snack bar walls with all completed inspections. | NATHAN | NATHAN | | BFR | P | 4946913 |
R.G. BRINKMANN COMPANY | BFR | P | 04/28/2015 | with all completed MEP's frame of WALLS ONLY okay at 1st and 2nd floors between 3.5-2, F.1-H. | NATHAN | NATHAN | | BFR | P | 4944636 |
R.G. BRINKMANN COMPANY | BFR | P | 04/27/2015 | need backing at walls room 302 and studs are cut at plumbing wall / mid height stud bracing at stair wall 109 missing / interior walls at 3.5-2 H-G.7 and G.7-F.2, 2.7-2 okay at 1st and 2nd floors / receiving office walls and Demonstration room walls okay | NATHAN | NATHAN | | BFR | P | 4943588 |
FRONTIER MECHANICAL INC. | BSP | T | 04/22/2015 | PAID (REC#1258418) ADDITIONAL PLAN REVIEW TIME: $50 From: RUSSELL Mechanical splice | RUSSELL | RUSSELL | | BSP | T | 4940899 |
R.G. BRINKMANN COMPANY | BFR | P | 03/31/2015 | pilaster framing at west side okay / | NATHAN | NATHAN | | BFR | P | 4927066 |
R.G. BRINKMANN COMPANY | BFR | P | 03/25/2015 | entry / foyer framing , pilaster framing and corrections at North, East and South sides | NATHAN | NATHAN | | BFR | P | 4923701 |
R.G. BRINKMANN COMPANY | BSP | T | 03/24/2015 | PAID (REC#1253244) PLAN SPLICE FEE: $50 by: JIMA for Construction: splice : added canopy plans | JIMA | JIMA | | BSP | T | 4922161 |
R.G. BRINKMANN COMPANY | BFR | P | 03/17/2015 | west side vestibule framing okay only south side not done / attachment of front center and rear center and NE corner pilaster partialed only not completed need steel to steel attachments finished not all pilasters looked at. | NATHAN | NATHAN | | BFR | P | 4918460 |
R.G. BRINKMANN COMPANY | BFR | P | 03/06/2015 | roof truss repair and replacement and CMU wall progress. | NATHAN | NATHAN | | BFR | P | 4912861 |
R.G. BRINKMANN COMPANY | BFR | P | 01/30/2015 | exterior CMU wall to final roof elevation at East,West and South sides complete / interior post column attachment and grouting okay at entire. | NATHAN | NATHAN | | BFR | P | 4893847 |
R.G. BRINKMANN COMPANY | BFN | P | 01/23/2015 | grouting at column bases, pot holes at interior holding water interior drain is being added first trench being dug at north west side | NATHAN | NATHAN | | BFN | P | 4889595 |
R.G. BRINKMANN COMPANY | BFR | P | 01/23/2015 | column, truss and bracing attachment A-C.6 , 4-11 | NATHAN | NATHAN | | BFR | P | 4889591 |
R.G. BRINKMANN COMPANY | BFN | P | 12/30/2014 | progress check on entire foundation and training. | NATHAN | NATHAN | | BFN | P | 4878758 |
R.G. BRINKMANN COMPANY | BFT | P | 11/24/2014 | wall at line 13 F-C.6 / footer 11 to C.6, C.6 11-13 / B 11-8 | NATHAN | NATHAN | | BFT | P | 4859401 |
R.G. BRINKMANN COMPANY | BFT | P | 11/14/2014 | POC JIM BROWN for SAMS CLUB 314-488-0486 / pre construction and site walk for sams club. | NATHAN | NATHAN | | BFT | P | 4853997 |
MARK YOUNG CONSTRUCTION, INC. | E= | C | 07/29/2015 | | BRIAN | BRIAN | | E= | C | 5003782 |
BIBLE ELECTRIC, INC. | E= | C | 07/23/2015 | SITE LIGHTING AND OUTSIDE----- | BRIAN | BRIAN | | E= | C | 4999405 |
BIBLE ELECTRIC, INC. | E= | P | 07/16/2015 | CASH DROPS---ELECTRONICS DROPS------ | BRIAN | BRIAN | | E= | P | 4994906 |
MARK YOUNG CONSTRUCTION, INC. | E= | R | 06/26/2015 | CAN NOT USE SO CORD AS A PERMANENT WIRING METHOD-------NEED TO GROUND THE J BOXES ON THE EQUIPMENT---- | BRIAN | BRIAN | | E= | R | 4982151 |
MARK YOUNG CONSTRUCTION, INC. | E= | R | 06/26/2015 | NO ONE ON SITE @ 4:10-----LEFT MESSAGE ON CALL AHEAD #------ | BRIAN | BRIAN | | E= | R | 4982122 |
BIBLE ELECTRIC, INC. | E= | P | 06/23/2015 | ENTRY----TIRE CENTER--- | BRIAN | BRIAN | | E= | P | 4979321 |
BIBLE ELECTRIC, INC. | E= | P | 06/19/2015 | SHIP/RECIV----1 ST FLOOR OFFICES / PHARMACY----CAFE-----BATHROOMS-------NORTH SIDE BEHIND COOLERS-- | BRIAN | BRIAN | | E= | P | 4977375 |
BIBLE ELECTRIC, INC. | E= | P | 06/10/2015 | PHARMACY-----SHIP / RECEIVING-----DEMO--- | BRIAN | BRIAN | | E= | P | 4970980 |
BIBLE ELECTRIC, INC. | ER | P | 06/10/2015 | CEILINGS AT BAKERY ----RESTAURANT | BRIAN | BRIAN | | ER | P | 4970964 |
BIBLE ELECTRIC, INC. | E= | P | 06/05/2015 | 2ND FLOOR OFFICES------FRESH OFFICES --DEMO----CUSTOMER BATHROOMS------EMPLOYEE BATHROOM------MOP CLOSET----- | BRIAN | BRIAN | | E= | P | 4968066 |
BIBLE ELECTRIC, INC. | ER | P | 06/05/2015 | CEILINGS----DEMO, FRESH OFFICES----SHIP AND RECEIVING ---- | BRIAN | BRIAN | | ER | P | 4968049 |
BIBLE ELECTRIC, INC. | ER | P | 06/02/2015 | GRID CEILING IN RECEIVING OFFICES--------- | BRIAN | BRIAN | | ER | P | 4965288 |
BIBLE ELECTRIC, INC. | EP | C | 06/02/2015 | LRX---LBC---- | BRIAN | BRIAN | | EP | C | 4965286 |
BIBLE ELECTRIC, INC. | ER | P | 05/28/2015 | GRID CEILING------PHARMACY---VISION-----2ND FLOOR----- | BRIAN | BRIAN | | ER | P | 4962516 |
BIBLE ELECTRIC, INC. | EP | P | 05/20/2015 | panel L3D------ | BRIAN | BRIAN | | EP | P | 4958349 |
BIBLE ELECTRIC, INC. | ER | P | 05/20/2015 | hard lids in employee bathrooms | BRIAN | BRIAN | | ER | P | 4958342 |
BIBLE ELECTRIC, INC. | E= | R | 05/15/2015 | NOT READY | BRIAN | BRIAN | | E= | R | 4955564 |
BIBLE ELECTRIC, INC. | ER | P | 05/15/2015 | HARD LIDS-----OFFICE--PHARMACY-- | BRIAN | BRIAN | | ER | P | 4955563 |
BIBLE ELECTRIC, INC. | EP | P | 05/14/2015 | CEILING HUNG TRANSFORMER--- | BRIAN | BRIAN | | EP | P | 4954869 |
BIBLE ELECTRIC, INC. | ER | P | 05/06/2015 | WALLS AT SHIP/ REC.----BUS BARS--------EP---SEE PLANS | BRIAN | BRIAN | | ER | P | 4950337 |
BIBLE ELECTRIC, INC. | ES | P | 05/04/2015 | Commercial Service: 3000 AMP 4-W --480 VOLT-------OK TO SET METER------- | BRIAN | BRIAN | | ES | P | 4948627 |
BIBLE ELECTRIC, INC. | ER | P | 05/04/2015 | WALLS AT BAKERY------ | BRIAN | BRIAN | | ER | P | 4948621 |
BIBLE ELECTRIC, INC. | ER | P | 05/01/2015 | RTUS ---FANS----COMPRESSOR HOUSES ON THE ROOF----- | BRIAN | BRIAN | | ER | P | 4947709 |
BIBLE ELECTRIC, INC. | ER | P | 04/29/2015 | WALLS IN SNACK SHAK------BATHROOM HARD LIDS ---------WALLS IN PRODUCE-------SEE PLANS------- | BRIAN | BRIAN | | ER | P | 4945827 |
BIBLE ELECTRIC, INC. | ER | P | 04/22/2015 | WALLS AT PHARMACY---BATHROOMS ---EYE CENTER---- ALL OF -2ND FLOOR EMPLOYEE AREA----- | BRIAN | BRIAN | | ER | P | 4940658 |
BIBLE ELECTRIC, INC. | EUG | P | 04/08/2015 | POLE LIGHTS----------STILL NEED POLE LIGHTS AT FUELING STATION AREA------ | BRIAN | BRIAN | | EUG | P | 4932250 |
BIBLE ELECTRIC, INC. | ESL | P | 02/26/2015 | dock levelers, conduit to edc2, edc3, h5p1 not complete to electric room ends at south column. | BRET | BRET | | ESL | P | 4909205 |
BIBLE ELECTRIC, INC. | EUG | P | 01/23/2015 | SERVICE SECONDARY OK----INFORMED CONTRACTOR THIS IS A CSU INSPECTION---- | TIMA | TIMA | | EUG | P | 4889407 |
BIBLE ELECTRIC, INC. | EUG | P | 12/09/2014 | edc #1 secondary under foundation call csu for inspection 3-2"pvc under electric room slab only | BRET | BRET | | EUG | P | 4867668 |
BIBLE ELECTRIC, INC. | EUG | P | 12/04/2014 | between 3 poles s.e entry marked on plans | BRET | BRET | | EUG | P | 4864665 |
BIBLE ELECTRIC, INC. | EUG | P | 12/02/2014 | WEST PARKING LOT OK | TIMA | TIMA | | EUG | P | 4862834 |
BIBLE ELECTRIC, INC. | EUG | R | 11/26/2014 | could not locate area that need inspection or contractor. | BRET | BRET | | EUG | R | 4861036 |
BIBLE ELECTRIC, INC. | EUG | P | 11/24/2014 | ufer ok | BRET | BRET | | EUG | P | 4859321 |
BIBLE ELECTRIC, INC. | EUG | R | 10/30/2014 | NOT READY | TIMA | TIMA | | EUG | R | 4845054 |
FRONTIER MECHANICAL INC. | H= | C | 11/13/2015 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5078432 |
FRONTIER MECHANICAL INC. | H= | P | 10/13/2015 | SEVERAL TEST AND BALANCE READINGS OUTSIDE +/- ON THE FOLLOWING RTU'S 12 - 18 - 22 - 24 AND 25 - CONTRACTOR PLEASE REVIEW TAB REPORT AND RESUBMIT WHEN CORRECTIONS ARE MADE | JERRYF | JERRYF | | H= | P | 5055792 |
BOCHNAK MECHANICAL, INC. | H= | C | 07/24/2015 | ALL OK - ALL TIE DOWNS AND REGS. INSTALLED | JERRYF | JERRYF | | H= | C | 5000460 |
FRONTIER MECHANICAL INC. | H= | P | 07/13/2015 | PARTIAL PENDING TAB REPORT - REST OK | JERRYF | JERRYF | | H= | P | 4991384 |
MARK YOUNG CONSTRUCTION, INC. | H= | C | 07/09/2015 | REFRIGERATION ALL COMPLETE | JON | JON | | H= | C | 4990196 |
MORNING STAR ELEVATOR, LLC. | HE= | C | 07/06/2015 | STATE ID CP15-000304--MCP ON SITE | JOHNW | JOHNW | | HE= | C | 4986382 |
FRONTIER MECHANICAL INC. | HD | P | 06/18/2015 | NEED THE FOLLOWING FOR FUTURE INSPECTION - ALL METAL WASHABLE SURFACE COMPLETED AT BOTH HOODS AND SEALED - INTERLOCKS VERIFIED AND ALL APPLIANCES INSTALLED - APPROVED GASKETS AT 2 GREASE FANS - REMOVE SILICON AT BOTTOM OF SMALL HOOD - SECURE AND LIGHT TEST EXHAUST HOOD COLLAR TO DUCT CONNECTION AT LARGE HOOD - TAB REPORT - CONTRACTOR REVIEW ALL NOTES BEFORE NEXT INSPECTION (((((( NOTE INSPECTOR UNABLE TO VERIFY WELD AT SMALL HOOD DUE TO BEING COVERED AND CONTRACTOR DID NOT WANT TO REMOVE OUTER COVER | JERRYF | JERRYF | | HD | P | 4975690 |
MARK YOUNG CONSTRUCTION, INC. | HWP | P | 06/16/2015 | PRESSURE TEST OK ON ALL LINES TO CASE'S AND WALK INS - | JERRYF | JERRYF | | HWP | P | 4974177 |
FRONTIER MECHANICAL INC. | HD | P | 06/16/2015 | NEED ALL GREASE FAN GASKETS AND GREASE FAN HINGE KITS SECURED PROPERLY AT CURBS REST OK ROOF OK - NEED ALL WASHABLE SURFACE COMPLETED AT HOODS - BRACE WATER HEATER FLUE - BRACE EXHAUST DUCT AT MOP SINK AREA AT LOADING DOCK - SECURE B VENTS AT EXHAUST COLLARS AT 2 OVENS - NEED INSTALL MANUAL FOR TUBE HEATERS - NEED LIGHT TEST ON ALL GREASE HOOD COLLAR TO DUCT CONNECTIONS - TAB REPORT - CONTRACTOR REVIEW ALL NOTES FROM PREVIOUS INSPECTIONS BEFORE CALLING FINAL INSPECTIONS - | JERRYF | JERRYF | | HD | P | 4974175 |
FRONTIER MECHANICAL INC. | H= | P | 06/11/2015 | NEED THE FOLLOWING FOR NEXT INSPECTION - NON COMBUSTIBLE WASH ABLE SURFACE TO TO EXTEND ABOVE AND EXTEND BEYOND SIDES OF HOOD CURRENTLY STOPS BEHIND AT SNACK BAR - LIGHT TEST ON ALL GREASE DUCT COLLAR CONNECTIONS AT ALL HOODS - INSTALL MANUAL FOR FOR GREASE DUCT AND TUBE HEATERS AT AUTOMOTIVE - NEED TO HAVE CONSULT WITH SENIOR INSPECTOR ON REVERSED HOOD AT ROTESSARIE PAGE GM2 OF PLANS - 1ST AND 2ND FLOOR OFFICE AREAS ALL GRILLES COMPLETE | JERRYF | JERRYF | | H= | P | 4971316 |
FRONTIER MECHANICAL INC. | HD | P | 06/02/2015 | ABOVE CEILING SA/RA RUN OUTS AND GRILLES ARE COMPLETE - NEED CONSULT ON HOOD CLEARANCES WITH SENIOR INSPECTOR | JERRYF | JERRYF | | HD | P | 4964864 |
MARK YOUNG CONSTRUCTION, INC. | HRP | P | 05/15/2015 | 350# OK ON 6 SETS - NEED ALL INTERIOR INSPECTED | JERRYF | JERRYF | | HRP | P | 4955300 |
FRONTIER MECHANICAL INC. | HD | P | 05/13/2015 | THE FOLLOWING AREAS ARE OK - LOADING DOCK AREA - GREASE HOOD WALLS OK - ALL MAIN FLOOR SALES AREA - NEED THE FOLLOWING FOR FUTURE INSPECTION - GREASE DUCT AND TUBE HEATER INSTALL MANUALS - CONFIRM TRANSFER TO AIR COMPRESSOR ROOM - REMOTE INDICATORS FOR ALL SMOKE SHUTDOWN ???? - NEED ROOF INSPECTION AT 2 GREASE FANS AND UNIT HEATER B VENT AT ENTRY WAY - REST OF ROOF OK | JERRYF | JERRYF | | HD | P | 4953770 |
BOCHNAK MECHANICAL, INC. | HI | P | 05/13/2015 | ALL ROOF LINES CAPPED - CONTRACTOR REVIEW ALL NOTES FOR FUTURE INSPECTION | JERRYF | JERRYF | | HI | P | 4953769 |
BOCHNAK MECHANICAL, INC. | HC | C | 05/13/2015 | OK FOR METER RELEASE | JERRYF | JERRYF | | HC | C | 4953768 |
BOCHNAK MECHANICAL, INC. | HO | P | 05/12/2015 | THIS INSPECTION WAS FOR ALL PIPING ON ROOF - PARTIAL PENDING ALL OPEN LINES ON ROOF BEING CAPPED BEFORE METER CAN BE RELEASED - NEED THE FOLLOWING FOR FUTURE INSPECTION - ALL INTERIOR DROPS COMPLETED , AIR TESTED AND INSPECTED - ALL LABELS AND STRAPS INSTALLED - ALL REGS AND FINAL CONNECTIONS ON ROOF | JERRYF | JERRYF | | HO | P | 4952879 |
FRONTIER MECHANICAL INC. | HD | P | 04/28/2015 | THIS INSPECTION FOR 1ST AND 2ND FLOOR MEZZANINE -ABOVE CEILING OK IN ALL HARD LID AREAS - ALL SA/RA RUN OUTS COMPLETE - AT FINAL CONFIRM ALL DAMPER CONTROLS HAVE ACCESS | JERRYF | JERRYF | | HD | P | 4944198 |
FRONTIER MECHANICAL INC. | HD | P | 04/16/2015 | ALL SA/RA AND UPPER AND LOWER EXHAUST ABOVE CEILING OK ON LOWER SOUTH MEZZANINE AREA - STILL NEED EF 9 RUN OUTS INSPECTED - BY FINAL CONFIRM ALL SMOKE SHUTDOWN AND REMOTE INDICATORS | JERRYF | JERRYF | | HD | P | 4937544 |
FRONTIER MECHANICAL INC. | HD | P | 03/27/2015 | ABOVE CEILING SA/RA OK FOR WRAP AT FLOOR MEZZANINE - STILL ALL EXHAUST DUCT AT EF10 COMPLETED | JERRYF | JERRYF | | HD | P | 4924589 |
MARK YOUNG CONSTRUCTION, INC. | HRP | L | 03/11/2015 | INSPECTION CANCELED BY CONTRACTOR | JERRYF | JERRYF | | HRP | L | 4915487 |
BOCHNAK MECHANICAL, INC. | P= | C | 07/23/2015 | OK. | TAYLOR | TAYLOR | | P= | C | 4999019 |
BOCHNAK MECHANICAL, INC. | PTO | C | 07/23/2015 | OK. | TAYLOR | TAYLOR | | PTO | C | 4999018 |
BOCHNAK MECHANICAL, INC. | PB | C | 07/23/2015 | underground complete | DICK | DICK | | PB | C | 4999001 |
BOCHNAK MECHANICAL, INC. | PRD | C | 07/22/2015 | roof drains #6, #7, #8 ok per plan on P6. | TAYLOR | TAYLOR | | PRD | C | 4998518 |
BOCHNAK MECHANICAL, INC. | PTO | P | 07/06/2015 | vent through roof needs to be 3 inch for S.O. interceptor. | TAYLOR | TAYLOR | | PTO | P | 4986856 |
BOCHNAK MECHANICAL, INC. | PRD | P | 07/01/2015 | roof drains #1, #2, #3 ok per plans on P6. | TAYLOR | TAYLOR | | PRD | P | 4984784 |
BOCHNAK MECHANICAL, INC. | P= | P | 06/29/2015 | rear FPWH and emergency eye wash ok. | TAYLOR | TAYLOR | | P= | P | 4982657 |
BOCHNAK MECHANICAL, INC. | P= | P | 06/25/2015 | receiving and employee restrooms, meat, produce, bakery ok. | TAYLOR | TAYLOR | | P= | P | 4980481 |
BOCHNAK MECHANICAL, INC. | P= | P | 06/24/2015 | snack bar, pharmacy, optical, auto, mezzanine, south mens and womens restrooms ok. | TAYLOR | TAYLOR | | P= | P | 4979727 |
BOCHNAK MECHANICAL, INC. | P= | P | 06/23/2015 | need aav at pharmacy sink, trap guards at all floor drains, need T/P drain and pan drain installed along with expansion device for auto center, optical sinks need mixing valves. | TAYLOR | TAYLOR | | P= | P | 4978876 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/26/2015 | all above ceiling dwv, H2O, and hybrid ok, need to install vent for S.O. interceptor, note-check eye wash supply lines and FPWH by final. | TAYLOR | TAYLOR | | PTO | P | 4960296 |
BOCHNAK MECHANICAL, INC. | PRD | P | 05/22/2015 | roof drains #4,#5,#9 and #10 ok per plan on P6. | TAYLOR | TAYLOR | | PRD | P | 4959478 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/12/2015 | produce prep walls only ok. | TAYLOR | TAYLOR | | PTO | P | 4952832 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/08/2015 | receiving dock restroom and drinking fountain walls only ok, meat prep, deli, rotisserie prep walls only ok. | TAYLOR | TAYLOR | | PTO | P | 4951535 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/07/2015 | bakery and demo room walls only ok, associates bathroom and janitor room walls only ok. | TAYLOR | TAYLOR | | PTO | P | 4950617 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/06/2015 | bakery and demo room ( dwv test ok, need nail protection throughout, wraps on stacks, test H2O in walls.) | TAYLOR | TAYLOR | | PTO | P | 4949731 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/05/2015 | auto restroom and sinks walls only ok. | TAYLOR | TAYLOR | | PTO | P | 4949201 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/04/2015 | auto restroom and sinks ( nail protection through out, install and anchor closet flange, need clean out for urinal, install trap primer lines, note check access for hammer arrestor in bathroom by final. | TAYLOR | TAYLOR | | PTO | P | 4948245 |
BOCHNAK MECHANICAL, INC. | PTO | P | 05/01/2015 | snack bar area ok. | DICK | DICK | | PTO | P | 4947435 |
BOCHNAK MECHANICAL, INC. | PTO | P | 04/30/2015 | main public restrooms ok | DICK | DICK | | PTO | P | 4946500 |
BOCHNAK MECHANICAL, INC. | PTO | P | 04/29/2015 | leak at 2 inch vent at southeast public bathroom, need to install H2O in southeast family bathroom. | TAYLOR | TAYLOR | | PTO | P | 4945368 |
BOCHNAK MECHANICAL, INC. | PTO | P | 04/27/2015 | office and mezzanine area as marked on field plan. | DICK | DICK | | PTO | P | 4943661 |
BOCHNAK MECHANICAL, INC. | PB | P | 03/31/2015 | need mechanical or PE stamped letter on approving offset in roof drain. 2 drains ok from tank underground to inside building. | DICK | DICK | | PB | P | 4927089 |
BOCHNAK MECHANICAL, INC. | PB | P | 03/23/2015 | all sanitary and grease waste ok, need under ground prd training with Tayler. | DICK | DICK | | PB | P | 4921843 |
BOCHNAK MECHANICAL, INC. | PB | P | 03/19/2015 | all grease waste ok. | DICK | DICK | | PB | P | 4920195 |
BOCHNAK MECHANICAL, INC. | PB | P | 03/02/2015 | all sanitary mains ok as marked on field plans GP1 | DICK | DICK | | PB | P | 4910508 |
BOCHNAK MECHANICAL, INC. | PB | P | 02/25/2015 | as marked on field plan GP1 | DICK | DICK | | PB | P | 4908369 |
BOCHNAK MECHANICAL, INC. | PB | P | 02/20/2015 | all dwv south of 3 line as marked on field planes. | DICK | DICK | | PB | P | 4906207 |
BOCHNAK MECHANICAL, INC. | PB | P | 02/17/2015 | dwv as marked on field plans P1 and P2. | DICK | DICK | | PB | P | 4903241 |