JOURNEY HOMES CS, LLC | B= | C | 04/29/2015 | unfinished basement with a/c, deck frame okay | NATHAN | NATHAN | | B= | C | 4945641 |
JOURNEY HOMES CS, LLC | BSP | P | 04/13/2015 | 2 deck piers okay | NATHAN | NATHAN | | BSP | P | 4934532 |
JOURNEY HOMES CS, LLC | BIN | C | 04/07/2015 | | NICK | NICK | | BIN | C | 4931177 |
JOURNEY HOMES CS, LLC | BFR | C | 04/07/2015 | Items corrected | NICK | NICK | | BFR | C | 4931174 |
JOURNEY HOMES CS, LLC | BFR | P | 04/06/2015 | missing monoposts / garage door blocks / anchor bolt side garage wall / 9 1/2" LSL above window in kitchen / center gusset at A5 over living room bottom cord / plumbing vents through the roof / 3/4" osb at dead air chases / fill in rim at stairs for stud bearing / | NATHAN | NATHAN | | BFR | P | 4930243 |
JOURNEY HOMES CS, LLC | BSP | P | 03/31/2015 | Portal frame OK | NICK | NICK | | BSP | P | 4926919 |
JOURNEY HOMES CS, LLC | BSP | R | 03/30/2015 | Need 3" nail grid pattern for narrow brace wall / Need to install 1000lb strap on interior of narrow brace wall detail / Porch lid and posts OK | NICK | NICK | | BSP | R | 4925607 |
JOURNEY HOMES CS, LLC | BFT | C | 02/26/2015 | Void under pad installed | BRIANB | BRIANB | | BFT | C | 4908784 |
JOURNEY HOMES CS, LLC | BFT | P | 02/25/2015 | need to address voided pad that is not voided. | NATHAN | NATHAN | | BFT | P | 4908546 |
JOURNEY HOMES CS, LLC | BFN | C | 02/25/2015 | engineer letter of foundation and ufer inspection picked up | NATHAN | NATHAN | | BFN | C | 4908591 |
JOURNEY HOMES CS, LLC | BFD | C | 02/25/2015 | drain is usable to sump and street / float 1.5" / final grade 10% to defined 2% grade | NATHAN | NATHAN | | BFD | C | 4908595 |
JOURNEY HOMES CS, LLC | BFN | P | 02/09/2015 | AUTHORIZED INSPECTION BY ENGINEER | MINDY | MINDY | MINDY | BFN | P | 4899243 |
JOURNEY HOMES CS, LLC | BFT | P | 02/09/2015 | AUTHORIZED INSPECTION BY ENGINEER | MINDY | MINDY | MINDY | BFT | P | 4899242 |
FOUNTAIN VALLEY ELECTRICAL, LLC | E= | C | 04/27/2015 | A/C INSTALLED--25 AMP--- | TIMA | TIMA | | E= | C | 4943403 |
FOUNTAIN VALLEY ELECTRICAL, LLC | ES | C | 04/03/2015 | Residential Underground: NEW 150 AMP SERVICE | MIKEC | MIKEC | | ES | C | 4928930 |
FOUNTAIN VALLEY ELECTRICAL, LLC | ER | C | 04/03/2015 | NO CEN. VAC. UNFINISHED BASEMENT | MIKEC | MIKEC | | ER | C | 4928926 |
IMS HEATING & AIR, INC. | H= | C | 04/24/2015 | ok note un-finished basement | DAVIDH | DAVIDH | | H= | C | 4943024 |
IMS HEATING & AIR, INC. | HC | C | 04/03/2015 | RELEASE METER | DAVIDH | DAVIDH | | HC | C | 4928809 |
IMS HEATING & AIR, INC. | HRR | C | 04/03/2015 | corrections made | DAVIDH | DAVIDH | | HRR | C | 4928806 |
IMS HEATING & AIR, INC. | HRR | P | 04/02/2015 | dryer is missing nail protection 6"osa unfinished basement no a/c | DAVIDH | DAVIDH | | HRR | P | 4928703 |
FENTON PLUMBING & HEATING INC | HI | C | 04/02/2015 | 10 lb test ok note 1 " line 1 furn,w/h | DAVIDH | DAVIDH | | HI | C | 4928702 |
FENTON PLUMBING & HEATING INC | P= | C | 04/28/2015 | corrections made. | TAYLOR | TAYLOR | | P= | C | 4944878 |
FENTON PLUMBING & HEATING INC | P= | P | 04/27/2015 | water heater and meter loop was not installed at top out and now is undersized, rest ok, pvb installed, unfinished basement. | TAYLOR | TAYLOR | | P= | P | 4943847 |
FENTON PLUMBING & HEATING INC | PTO | C | 04/02/2015 | corrections made. | TAYLOR | TAYLOR | | PTO | C | 4928657 |
FENTON PLUMBING & HEATING INC | PTO | P | 04/01/2015 | cannot have 2 traps on 1 trap arm for master shower and tub, set and trap master tub, rest ok, check meter loop and water heater by final. | TAYLOR | TAYLOR | | PTO | P | 4927844 |
FENTON PLUMBING & HEATING INC | PB | C | 03/16/2015 | | TAYLOR | TAYLOR | | PB | C | 4917838 |