GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 06/22/2015 | | BERTW | BERTW | | BFR | C | 4977704 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 06/22/2015 | | BERTW | BERTW | | B= | C | 4977701 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B16 | P | 05/28/2015 | Duct assembly in room 7165 built per UL Design U469 / Shaft liner installed per UL / Above ceiling penetrations all sealed | JEREMYA | JEREMYA | | B16 | P | 4962740 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | T | 05/28/2015 | PAID (REC#1264354) AFTER-HOURS INSPECTION: $200 From: TERRI 5/28/15 7:30 p.m. | TERRI | TERRI | | BFR | T | 4962084 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | T | 05/26/2015 | PAID (REC#1263827) PLAN SPLICE FEE: $50 by: JIMA for Construction: splice : changed framing around fire damped | JIMA | JIMA | | BSP | T | 4960603 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B16 | P | 05/18/2015 | Framing at doors 7154a & 7156a OK / Discussed on-site with Chris Luna, GE Johnson, Mechanical contractor and Jon Brazier, RBD Mech. Senior, the requirements for the framing of the dampers. Still needing to see a detail for the support of the damper framing at the horizontal assembly near door 7154a. Also discussed issues with the framing for the damper in the exam room across from nurses station. Will need a detail for cable bundle penetrations above door 7156a. | JEREMYA | JEREMYA | | B16 | P | 4955932 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 05/15/2015 | Met with Chris, GE super, about W6 walls above ceiling in exam room / Need arch. detail for supporting construction / Will also need detail for how to seal penetrations in shaft liner at ducts | JEREMYA | JEREMYA | | BFR | P | 4955145 |
E LIGHT ELECTRIC SERVICES, INC | E= | C | 06/22/2015 | | CRAIGS | CRAIGS | | E= | C | 4977738 |
E LIGHT ELECTRIC SERVICES, INC | E= | C | 06/22/2015 | FIRE ALARM INSPECTION: | CRAIGS | CRAIGS | | E= | C | 4977485 |
E LIGHT ELECTRIC SERVICES, INC | ER | C | 06/22/2015 | FIRE ALARM INSPECTION: F/A and relays OK | CRAIGS | CRAIGS | | ER | C | 4977484 |
E LIGHT ELECTRIC SERVICES, INC | E= | R | 06/19/2015 | FIRE ALARM INSPECTION: not ready | CRAIGS | CRAIGS | | E= | R | 4977413 |
E LIGHT ELECTRIC SERVICES, INC | ER | P | 06/19/2015 | FIRE ALARM INSPECTION: smoke detector in the center of two halls OK ---------- the rest not ready -- open 120 volt boxes --- fire alarm cable hanging --- no cable or bushing in other boxes | CRAIGS | CRAIGS | | ER | P | 4977411 |
MECHONE, INC. | H= | C | 06/02/2015 | | JON | JON | | H= | C | 4965452 |
MECHONE, INC. | H= | P | 05/29/2015 | PENDING PICTURES FOR REVIEW THAT ARE REQUESTED BY CONTRACTOR FOR RETAINING ANGLES AT NEW EGRESS DOOR AND TRANSFER DAMPER. REST OK | JON | JON | | H= | P | 4963615 |
MECHONE, INC. | H= | T | 05/28/2015 | PAID (REC#1264489) AFTER-HOURS INSPECTION: $200 From: TERRI 5/29/15 5:30 p.m. | TERRI | TERRI | | H= | T | 4962604 |
MECHONE, INC. | HD | P | 05/27/2015 | Inspected damper support frame per engineered drawing. Need to see frame installed in place along with damper in shaft wall construction. Also inspected material for joining the 2 studs together noted on previous inspections on other 60x30 damper. Double studs were not installed as required per instructions for this damper. engineer provided a damper support letter to meet intent of damper instructions. Upon inspection it was determined the material used by the General contractor was not the proper gauge thickness per engineered drawing. Inspection on this damper was rejected and needs to be re inspected and engineered drawing to be followed or provide a new splice with the material the GC elected to use. | JON | JON | | HD | P | 4961807 |
MECHONE, INC. | HD | T | 05/26/2015 | PAID (REC#1263887) AFTER-HOURS INSPECTION: $200 From: RITA fire damper | RITA | RITA | | HD | T | 4960848 |
MECHONE, INC. | HD | P | 05/16/2015 | STILL HAVE ISSUE WITH 2ND 60X30 DAMPER, DOES NOT HAVE DOUBLE STUDS ON BOTH VERTICAL SIDES OF DAMPER. 2- FIRE SMOKE DAMPER OPENINGS OK AT NEW EGRESS DOORWAY. WILL NEED TO SEE ALL RETAINING SUPPORT ANGLES IN PLACE, ALONG WITH ACCESS DOORS AND CEILING LABELING WHEN READY. CONSULTED WITH JOB SUPERINTENDENT AND MECHANICAL CONTRACTOR FOR SHAFT LINER DUCT PENETRATION. THERE IS NO SUPPORTING CONSTRUCTION SHOWN ON THE PLANS FOR THIS FIRE SMOKE DAMPER OR THE ASSEMBLY ITSELF. ENGINEER TO ADDRESS AND PROVIDE A SHEET NOTE ALONG WITH THE DETAIL THE BUILDING INSPECTOR REQUIRES. THE SHEET NOTE MUST INDICATE THE SUPPORTING DESIGN WILL MEET ALL THE REQUIREMENTS FROM THE GREEN HECK INSTALLATION INSTRUCTIONS. MUST FOLLOW M-SHEET NOTES FOR SMOKE DETECTORS FOR DAMPERS AND VERIFIY WITH FIRE ALARM CONTRACTOR, APPEARS REMOTE INDICATORS WILL BE REQUIRED FOR SMOKE DETECTORS, MUST VERIFY BEFORE FINAL. | JON | JON | | HD | P | 4955931 |
MECHONE, INC. | HD | T | 05/15/2015 | PAID (REC#1262119) AFTER-HOURS INSPECTION: $200 From: TERRI 5/16 | TERRI | TERRI | | HD | T | 4955083 |
MECHONE, INC. | HD | P | 05/14/2015 | 2- 12 ROUND DAMPERS OK ON FRAMING. 1- 60 X 30 OK ON FRAMING. 2ND 60 X 30 HAS ISSUE WIITH ONLY SINGLE STUDS. 1- 60 X 20 INSTALLED IN VERTICAL SHAFT LINER DOES NOT MEET INSTALLATION INSTRUCTIONS HAS NO FLOOR TO CEILING SUPPORT. | JON | JON | | HD | P | 4955020 |