EL PASO COUNTY GOVERNMENT | B= | C | 08/28/2015 | All other required Final inspections are complete. (This is a computer generated result) | BERTW | BERTW | | B= | C | 5024374 |
EL PASO COUNTY GOVERNMENT | B= | P | 08/13/2015 | . Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2). | BERTW | BERTW | | B= | P | 5014116 |
EL PASO COUNTY GOVERNMENT | BFR | C | 08/13/2015 | | BERTW | BERTW | | BFR | C | 5014114 |
EL PASO COUNTY GOVERNMENT | BSP | T | 08/06/2015 | PAID (REC#1279206) ADDITIONAL PLAN REVIEW TIME: $50 From: RUSSELL Eliminated I.T. scope of work | RUSSELL | RUSSELL | | BSP | T | 5008981 |
EL PASO COUNTY GOVERNMENT | BSP | T | 07/27/2015 | PAID (REC#1277981) PLAN SPLICE FEE: $50 by: DOUG for Electrical | DOUG | DOUG | | BSP | T | 5000976 |
EL PASO COUNTY GOVERNMENT | BFR | P | 06/22/2015 | remainder of framing complete pending mech. rough and elect. rough | DANE | DANE | | BFR | P | 4977749 |
EL PASO COUNTY GOVERNMENT | BFR | P | 06/12/2015 | framing of new partition walls in hall 3 including lab, office 3, exam 5, break room, storage room, and office/exam room OK / new soffit in exam 3 OK / Exam room 2 is to have no demo of walls and cabinets in it and cabinets are 15 1/2" from door where plan calls 18" minimum. | DANE | DANE | | BFR | P | 4972307 |
EL PASO COUNTY GOVERNMENT | E= | C | 08/03/2015 | | MIKEC | MIKEC | | E= | C | 5006811 |
EL PASO COUNTY GOVERNMENT | ER | P | 06/19/2015 | REST OF WALLS | MIKEC | MIKEC | | ER | P | 4977150 |
EL PASO COUNTY GOVERNMENT | ER | P | 06/11/2015 | WALLS RMS 1065,66,67,68,69,69A,69B | MIKEC | MIKEC | | ER | P | 4971869 |
MECHONE, INC. | H= | C | 08/13/2015 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT RECEIVED. | NANCY | NANCY | | H= | C | 5013699 |
MECHONE, INC. | H= | P | 08/12/2015 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5013597 |
EL PASO COUNTY GOVERNMENT | H= | C | 08/12/2015 | PIPING FINAL OK. | NANCY | NANCY | | H= | C | 5013596 |
MECHONE, INC. | H16 | C | 07/29/2015 | WHEN EL PASO COUNTY CALLS FOR HWP INSPECTION PIPING HAS ALREADY BEEN LOOKED AT. PIPING OK, UNDER WORKING PRESSURE NO VISIBLE LEAKS. LABEL SUPPLY AND RETURN LINES TO VAV FOR FINAL. | NANCY | NANCY | | H16 | C | 5003329 |
MECHONE, INC. | H= | P | 07/29/2015 | NEED EL PASO COUNTY TO ATTACH AS A HEATING CONTRACTOR FOR THE PIPING TO THE VAV. NEED REVISED/APPROVED PRINTS DELETING WORK IN "IT" AREA. PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5003328 |
MECHONE, INC. | HD | C | 07/29/2015 | ABOVE CEILING ALL OK. | NANCY | NANCY | | HD | C | 5003316 |
EL PASO COUNTY GOVERNMENT | P= | C | 08/12/2015 | per plan. | DICK | DICK | | P= | C | 5013001 |
EL PASO COUNTY GOVERNMENT | PTO | C | 06/11/2015 | per plan | DICK | DICK | | PTO | C | 4971858 |
EL PASO COUNTY GOVERNMENT | PB | C | 06/03/2015 | | DICK | DICK | | PB | C | 4966039 |