CUVALA CONSTRUCTION, INC. | B= | C | 02/16/2016 | corrections completed | ERICR | ERICR | | B= | C | 5134968 |
CUVALA CONSTRUCTION, INC. | B= | P | 12/23/2015 | Need hearth for wood burning stove to be 16" from glass, is only 12" at time of inspection / Everything else OK -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | NICK | NICK | | B= | P | 5104895 |
CUVALA CONSTRUCTION, INC. | BLA | C | 10/20/2015 | | DANE | DANE | | BLA | C | 5061588 |
CUVALA CONSTRUCTION, INC. | BIN | C | 10/14/2015 | | DANE | DANE | | BIN | C | 5057755 |
CUVALA CONSTRUCTION, INC. | BFR | C | 10/13/2015 | letter received for deck post on pier and strap and anchor installed / items from previous inspection complete/ trusses OK | DANE | DANE | | BFR | C | 5056523 |
CUVALA CONSTRUCTION, INC. | BFR | P | 10/12/2015 | OK to insulate / need anchor bolts within 12" of plate breaks in garage / missing the ST22 strap on south facing wall below master "glass block" window / no truss details on site - still need to inspect truss bracing / NOTE: double walled stove pipe used = 6" minimum from finished wall - single wall = 18" from finished wall per installation guide / still need engineering for post not bearing on pier at deck. | DANE | DANE | | BFR | P | 5055429 |
CUVALA CONSTRUCTION, INC. | BSP | P | 09/24/2015 | front and rear porch lids and rear porch cover post OK / deck framing and all posts except SW post OK / need letter for southwest deck post only setting 1/2 on pier | DANE | DANE | | BSP | P | 5043788 |
CUVALA CONSTRUCTION, INC. | BSP | P | 08/18/2015 | Deck piers OK | DANE | DANE | | BSP | P | 5017191 |
CUVALA CONSTRUCTION, INC. | BFI | C | 08/18/2015 | horizontal insulation under heated slab at basement level OK | DANE | DANE | | BFI | C | 5017180 |
CUVALA CONSTRUCTION, INC. | BFI | R | 08/04/2015 | will need to inspect horizontal ridged insulation after backfill | DANE | DANE | | BFI | R | 5007620 |
CUVALA CONSTRUCTION, INC. | BFD | C | 08/04/2015 | usable drain OK / daylights left rear corner | DANE | DANE | | BFD | C | 5007619 |
CUVALA CONSTRUCTION, INC. | BFN | C | 08/04/2015 | engineer inspection report on file / 2500 PSF / usable drain / 10% grade / open hole on file / soils report on file / design on file / Eufer noted | DANE | DANE | | BFN | C | 5007618 |
CUVALA CONSTRUCTION, INC. | BFT | C | 08/04/2015 | engineer inspection report on file | DANE | DANE | | BFT | C | 5007617 |
CUVALA CONSTRUCTION, INC. | BFT | P | 07/28/2015 | AUTHORIZED INSPECTION BY ENGINEER | TERRI | TERRI | TERRI | BFT | P | 5002905 |
CUVALA CONSTRUCTION, INC. | BFN | P | 07/28/2015 | AUTHORIZED INSPECTION BY ENGINEER | TERRI | TERRI | TERRI | BFN | P | 5002904 |
PORCH ELECTRIC, INC. | E= | C | 12/17/2015 | 30 amp a.c | MIKEC | MIKEC | | E= | C | 5101291 |
PORCH ELECTRIC, INC. | ES | C | 10/02/2015 | Residential Underground: 200 amp service new res. | BRET | BRET | | ES | C | 5049174 |
PORCH ELECTRIC, INC. | ER | C | 10/02/2015 | no mcc,no vac, #8 CU TO RANGE. 10 nm A/ rough C contractor to add receptacle to kitchen counter top west and n.e bedroom closet wall at entry. seal nipple. | BRET | BRET | | ER | C | 5049171 |
HOGAN MECHANICAL, INC. | H= | C | 12/18/2015 | Louver door to mechanical open to stairs, A/C complete rest o.k. | STEVEC | STEVEC | | H= | C | 5102259 |
HOGAN MECHANICAL, INC. | HWP | C | 10/09/2015 | Test good. Main floor ready to pour. | STEVEC | STEVEC | | HWP | C | 5054571 |
ARROW HAWK HEATING, LLC | HC | C | 10/09/2015 | RELEASE METER | STEVEC | STEVEC | | HC | C | 5053837 |
ARROW HAWK HEATING, LLC | HRR | C | 10/09/2015 | Attention Building, wood burning stove main floor, gas ran to location for future gas fireplace. | STEVEC | STEVEC | | HRR | C | 5053836 |
ARROW HAWK HEATING, LLC | HRR | P | 10/05/2015 | Venting to wood burner main floor not installed. Note: Air handler in attic, line-set to exterior, provide duct leakage report by final. Steve C added to notes 10/7/15 duct leakage report received. | STEVEC | STEVEC | | HRR | P | 5050906 |
O.M.A.G.M., INC. | HI | C | 10/02/2015 | 10# test o.k. 1"1/2 main, boiler, dryer, range, fireplace. outdoor bbq. | STEVEC | STEVEC | | HI | C | 5049758 |
HOGAN MECHANICAL, INC. | HWP | P | 08/14/2015 | Test good, ready to pour basement only. | STEVEC | STEVEC | | HWP | P | 5015316 |
HOGAN MECHANICAL, INC. | P= | C | 12/22/2015 | corrections made. | TAYLOR | TAYLOR | | P= | C | 5103639 |
HOGAN MECHANICAL, INC. | P= | P | 12/21/2015 | waive trip fee, need to secure and install drain 90 for pvb, rest ok. | TAYLOR | TAYLOR | | P= | P | 5102579 |
HOGAN MECHANICAL, INC. | P= | R | 12/18/2015 | install sprinkler back flow, leak under laundry sink, powder bath lav, basement lav, note: finished basement | TED | TED | | P= | R | 5102017 |
HOGAN MECHANICAL, INC. | PTO | C | 10/02/2015 | corrections made. | TAYLOR | TAYLOR | | PTO | C | 5049289 |
HOGAN MECHANICAL, INC. | PTO | P | 10/01/2015 | need hammer arrestors at washer, anchor meter, low test dwv at powder bath, rest ok, finished basement. | TAYLOR | TAYLOR | | PTO | P | 5048550 |
HOGAN MECHANICAL, INC. | PB | C | 08/10/2015 | IPC 2012 or 2009 ok | DICK | DICK | | PB | C | 5011053 |