MASTER BILT HOMES, INC. | B= | C | 01/11/2016 | | DAN | DAN | | B= | C | 5113978 |
MASTER BILT HOMES, INC. | B= | P | 01/04/2016 | Need to install hand rail for garage steps -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | NICK | NICK | | B= | P | 5109043 |
MASTER BILT HOMES, INC. | BLA | C | 11/06/2015 | | DANE | DANE | | BLA | C | 5074326 |
MASTER BILT HOMES, INC. | BSP | P | 11/06/2015 | deck framing OK | DANE | DANE | | BSP | P | 5074315 |
MASTER BILT HOMES, INC. | BIN | C | 10/27/2015 | | DANE | DANE | | BIN | C | 5066338 |
MASTER BILT HOMES, INC. | BFR | C | 10/23/2015 | | DANE | DANE | | BFR | C | 5064368 |
MASTER BILT HOMES, INC. | BSP | P | 10/05/2015 | 3 deck piers OK | DANE | DANE | | BSP | P | 5050729 |
MASTER BILT HOMES, INC. | BFD | C | 08/26/2015 | drain entire structure with sump exterior at south west corner of house. | DAN | DAN | | BFD | C | 5022886 |
MASTER BILT HOMES, INC. | BFD | R | 08/24/2015 | Excavation observation letter dated Aug. 19, 2015 requires entire structure for drain requirements. have habitable space installed from March 12, 2015 subsurface soil investigation | DAN | DAN | | BFD | R | 5020924 |
MASTER BILT HOMES, INC. | BFN | C | 08/24/2015 | foundation design and open excavation and sub soils on file, from Entech; ISO, flaot, drain entire, 5% slope from foundation. Ufer OK ; 2,400 psf. | DAN | DAN | | BFN | C | 5020904 |
MASTER BILT HOMES, INC. | BFT | C | 08/24/2015 | engineer observation for footer from Entech, Joe Goode Jr. #23725 | DAN | DAN | | BFT | C | 5020901 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | C | 12/16/2015 | CORRECTIONS MADE-- | BRIAN | BRIAN | | E= | C | 5099919 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | R | 12/15/2015 | locked 2:30 | BRET | BRET | | E= | R | 5099419 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | R | 12/14/2015 | NO ACCESS WET CONCRETE | MIKEC | MIKEC | | E= | R | 5098613 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | R | 12/10/2015 | gfci hallway receptacle with in 6' of powder room sink., install breaker lock for oven unit. note a/c pre-wire | BRET | BRET | | E= | R | 5096555 |
FIRST RATE ELECTRICAL SERVICES, INC. | ER | C | 10/09/2015 | no cen. vac | MIKEC | MIKEC | | ER | C | 5054673 |
FIRST RATE ELECTRICAL SERVICES, INC. | ES | C | 10/07/2015 | Residential Underground: NEW 200 AMP SERVICE | MIKEC | MIKEC | | ES | C | 5052562 |
FIRST RATE ELECTRICAL SERVICES, INC. | ER | R | 10/07/2015 | PLUMBING HARD PIPING NOT COMPLETED | MIKEC | MIKEC | | ER | R | 5052561 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | C | 12/18/2015 | High lows to mechanical open to stairs, rest o,k, | STEVEC | STEVEC | | H= | C | 5101882 |
SPRINGS GAS, INC. | HC | C | 10/22/2015 | RELEASE METER | TAYLOR | TAYLOR | | HC | C | 5063375 |
SPRINGS GAS, INC. | HI | C | 10/22/2015 | 10 lb test ok, 1 1/4 main, 1 furnace, 1 water heater, 1 fireplace, 1 range. | TAYLOR | TAYLOR | | HI | C | 5063373 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | C | 10/02/2015 | Corrections made. Venting to water heater complete. | STEVEC | STEVEC | | HRR | C | 5049705 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | P | 09/29/2015 | Returns upper missing blocking, B-vent lacks 1" clearance at sheeting upper, more support/strap needed at furnace pvc vent in bay, extend RA in soffit/basement, seal plumbing at RA in bay above mechanical room. Note: duct design, basement finish, equipment matches, outside air to return, line-set only, check venting to water heater by final. | STEVEC | STEVEC | | HRR | P | 5046614 |
JOLLY PLUMBING & HEATING INC. | P= | C | 12/09/2015 | corrections made. | TAYLOR | TAYLOR | | P= | C | 5095209 |
JOLLY PLUMBING & HEATING INC. | P= | P | 12/08/2015 | could not inspect master shower ( tile work being done ), need hammer arrestor at ice maker, rest ok, pvb installed, finished basement. | TAYLOR | TAYLOR | | P= | P | 5093897 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 10/15/2015 | correction made for PTO+. | TAYLOR | TAYLOR | | PTO | C | 5058335 |
JOLLY PLUMBING & HEATING INC. | PTO+ | P | 10/09/2015 | need to seal around 2 inch shower drain in return air, rest ok. | TAYLOR | TAYLOR | | PTO+ | P | 5054073 |
JOLLY PLUMBING & HEATING INC. | PTO | P | 09/24/2015 | PTO + needs to be complete,note- check water heater and meter at final for proper sizing at final, finished basement. | TAYLOR | TAYLOR | | PTO | P | 5043539 |
JOLLY PLUMBING & HEATING INC. | PB | C | 09/03/2015 | | TAYLOR | TAYLOR | | PB | C | 5029737 |