AVALON DEVELOPMENT COMPANY LLC | B= | C | 11/18/2016 | Sign Off. Mech finals complete | JEREMYA | JEREMYA | | B= | C | 5348082 |
AVALON DEVELOPMENT COMPANY LLC | BE | L | 11/17/2016 | Renewed at 11/17/2016 11:20:38 AM | NELIDA | NELIDA | | BE | L | 5347245 |
AVALON DEVELOPMENT COMPANY LLC | B= | P | 12/08/2015 | Still missing mechanical completion on All Seasons permit. Recall once this is complete. This is all that is holding the final sign off up. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): ALL SEASONS HTG & A/C Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 5093718 |
AVALON DEVELOPMENT COMPANY LLC | B= | P | 11/30/2015 | Cancelled at call ahead -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), ALL SEASONS HTG & A/C Mechanical Final Inspection is not Completed yet, MITCHELL HEATING, LLC Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 5088243 |
AVALON DEVELOPMENT COMPANY LLC | BSP | P | 11/20/2015 | PLAN SPLICE: (No Fee) by: DANM for Construction: Add two small closets for pool chemical storage | DANM | DANM | | BSP | P | 5082951 |
ALL SEASONS HEATING AND AIR CONDITIONING | BSP | T | 11/20/2015 | PAID (REC#1301048) PLAN SPLICE FEE: $50 by: DALEH for Mechanical | DALEH | DALEH | | BSP | T | 5082887 |
AVALON DEVELOPMENT COMPANY LLC | BSP | T | 11/19/2015 | PAID (REC#1301050) PLAN SPLICE FEE: $50 by: DOUG for Electrical: switch and fan in two rooms | DOUG | DOUG | | BSP | T | 5082576 |
TUSCANY HOMES LLC | B= | P | 10/29/2015 | non-absorbent wall covering installed at pool toilet room / OK pending fire final and H=. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), ALL SEASONS HTG & A/C Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5068861 |
TUSCANY HOMES LLC | B= | P | 10/28/2015 | need non-absorbent wall covering in new spliced in bathroom off of pool / need fire final / need heat final -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), ALL SEASONS HTG & A/C Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5067892 |
FAIRWAY PLUMBING & HEATING, INC. | BSP | T | 10/15/2015 | PAID (REC#1293497) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing slice 10/15/15 | TCRIPPEN | TCRIPPEN | | BSP | T | 5058300 |
TUSCANY HOMES LLC | BSP | P | 10/15/2015 | PLAN SPLICE: (No Fee) by: DANM for Construction: Add sink | DANM | DANM | | BSP | P | 5058277 |
TUSCANY HOMES LLC | BFR | P | 10/01/2015 | need to brace all of the partition walls at second floor offices to roof system - can check at final thru ceiling grid / discussed accessibility with superintendent Isaac / need to attach a mechanical permit and have inspections / frame OK pending other rough inspections | DANE | DANE | | BFR | P | 5048964 |
MEYER ELECTRIC | E= | C | 11/25/2015 | | MIKEC | MIKEC | | E= | C | 5087703 |
MEYER ELECTRIC | E= | P | 10/21/2015 | ------------------------Partial by Dean, 2 exhaust fans have been added to the scope of this project.------------------------ | GARYL | GARYL | | E= | P | 5062931 |
MEYER ELECTRIC | E= | R | 10/20/2015 | Label 2nd floor panels, reversed polarity on existing recept by new treadmill recept., 1st floor: pull panel covers check for shared neutrals..... | GARYL | GARYL | | E= | R | 5061937 |
MEYER ELECTRIC | ER | P | 09/30/2015 | walls marked on approved drawings --- 1st and 2nd floor offices | CRAIGS | CRAIGS | | ER | P | 5047854 |
MEYER ELECTRIC | ER | P | 09/29/2015 | need approved prints on site, some walls up stairs ok, need to check prints to see what was done and scope of work | GARYL | GARYL | | ER | P | 5047015 |
ALL SEASONS HEATING AND AIR CONDITIONING | H= | C | 12/14/2015 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT RECEIVED. | NANCY | NANCY | | H= | C | 5097867 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | C | 12/04/2015 | MECHANICAL FINAL OK. LETTER FROM ENGINEER APPROVING EXHAUST TERMINATION LOCATION RECEIVED AND SCANNED. | NANCY | NANCY | | H= | C | 5091631 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | P | 12/01/2015 | TEST AND BALANCE REPORT FOR EF-1 AND EF-3 RECEIVED AND SCANNED. EF-1 TERMINATES WITHIN 10 FEET OF A DOOR. | NANCY | NANCY | | H= | P | 5089624 |
ALL SEASONS HEATING AND AIR CONDITIONING | H= | P | 11/30/2015 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT FOR SUPPLY AIR AND EF-2. | NANCY | NANCY | | H= | P | 5088337 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | P | 11/30/2015 | EF-3 TERMINATES WITHIN 10 FEET OF A DOOR, SEE IMC 501.2.1 OTHER PRODUCT CONVEYING PRODUCTS. PROVIDE TEST AND BALANCE REPORT FOR EF-1 AND EF-3. | NANCY | NANCY | | H= | P | 5088330 |
ALL SEASONS HEATING AND AIR CONDITIONING | H= | P | 11/19/2015 | NEED 2 EXHAUST FANS ADDED TO PERMIT / EF 1 AND NEW FAN AT STORAGE ROOM AT POOL - REVISE PLAN SHOWING NEW ROUTING OF BATH FAN VENTS TO 1ST FLOOR EXTERIOR - REST OF 1ST FLOOR OK - NEED TAB REPORT | JERRYF | JERRYF | | H= | P | 5082736 |
ALL SEASONS HEATING AND AIR CONDITIONING | HD | P | 10/21/2015 | SECOND FLOOR ABOVE CEILING OK. FIRST FLOOR NOT READY. CEILING NOT OPEN TO SEE NEW WORK ABOVE FAMILY ASSIST AND CHANGING AREA. WHY DOES YOUR SCOPE OF WORK LIST FIVE NEW ROOFTOP UNITS? PRINTS SHOW EQUIPMENT AS EXISTING. | NANCY | NANCY | | HD | P | 5062289 |
FAIRWAY PLUMBING & HEATING, INC. | P= | C | 10/27/2015 | PLAN SPLICED TO SHOW NEW BATH ROOM , WATER HEATER IN ALL LAVS TEMPERED | GABE | GABE | | P= | C | 5066953 |
FAIRWAY PLUMBING & HEATING, INC. | PTO | C | 10/21/2015 | 2nd floor sink and drinking fountain | TED | TED | | PTO | C | 5062316 |
FAIRWAY PLUMBING & HEATING, INC. | PTO | P | 10/16/2015 | pool side bathroom walls and ceiling ok, check aav access at final | TED | TED | | PTO | P | 5059267 |
FAIRWAY PLUMBING & HEATING, INC. | PB | C | 10/01/2015 | G.C needs mechanical permit attachment | JOEL | JOEL | | PB | C | 5048588 |