BRYAN CONSTRUCTION, INC. | B= | C | 10/07/2016 | All other required Final inspections are complete. (This is a computer generated result) | NICK | NICK | | B= | C | 5312831 |
BRYAN CONSTRUCTION, INC. | B= | P | 10/06/2016 | Building final OK pending mechanical final complete. Additional Inspections Required (computer generated): HEATING & PLUMBING ENGRS, INC Mechanical Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 5312054 |
BRYAN CONSTRUCTION, INC. | BSP | T | 07/08/2016 | PAID (REC#1340545) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Sheets .01, 1.0, 2.0, 3.0, 4.0, 4.1----To add servery to scope | SHELBY | SHELBY | | BSP | T | 5240517 |
BRYAN CONSTRUCTION, INC. | BE | L | 05/16/2016 | Renewed at 5/16/2016 3:45:59 PM | JANE | JANE | | BE | L | 5200538 |
HEATING & PLUMBING ENGINEERS, INC | BSP | P | 01/14/2016 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing | TCRIPPEN | TCRIPPEN | | BSP | P | 5116439 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | EUG | C | 05/26/2016 | 1--3/4 pvc conduit to a light pole OK | CRAIGS | CRAIGS | | EUG | C | 5208863 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 05/26/2016 | | CRAIGS | CRAIGS | | E= | C | 5208861 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 04/06/2016 | from mdp to transformer disconnect on load side of the 7.5 transformer OK ----- need the paper work on the pumps and manufacturers installation instructions | CRAIGS | CRAIGS | | ER | P | 5170939 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | EUG | C | 03/22/2016 | 2--3/4 pvc to the grease interceptor ---OK | CRAIGS | CRAIGS | | EUG | C | 5159825 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 10/07/2016 | ALL HVAC WORK WAS TEMPORARY AND ALL HAS BEEN REMOVED | JERRYF | JERRYF | | H= | C | 5312830 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 10/03/2016 | | JOEL | JOEL | | P= | C | 5308378 |
HEATING & PLUMBING ENGINEERS, INC | P= | P | 08/29/2016 | kitchen and dish washing area | TED | TED | | P= | P | 5279963 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 08/11/2016 | vent tie ins cooler room and hot bar area | TED | TED | | PB | P | 5266685 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 08/08/2016 | phase 9 part 2- grease line to hot bar area, tie ins for cooler area ok | TED | TED | | PB | P | 5263505 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 08/04/2016 | phase 9 part 2- cooler area grease drain less tie ins, also eye wash area tie ins ok | TED | TED | | PB | P | 5261412 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 08/02/2016 | continuation of phase 9 part 2 grease drain less tie ins | TED | TED | | PB | P | 5259433 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 07/27/2016 | phase 9 part 2- sanitary tie ins, grease main insulation ok, phase 9 part 1 continuation into kitchen around eye wash station less tie ins ok | TED | TED | | PB | P | 5254840 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 07/26/2016 | phase 9 part 2 start, sanitary less tie ins, grease main less tie ins and insulation ok | TED | TED | | PB | P | 5253749 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 06/22/2016 | branch capped at main, phase 5-B | TED | TED | | PB | P | 5228009 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 06/21/2016 | need to hard cap abandoned branch at main | TED | TED | | PB | P | 5226896 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 06/08/2016 | start of phase 9 tie ins ok | TED | TED | | PB | P | 5217323 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 06/07/2016 | start of phase 9 less tie ins | TED | TED | | PB | P | 5216253 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 05/25/2016 | phase 8.2 tie ins ok | TED | TED | | PB | P | 5207606 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 05/24/2016 | phase 8.2, test and design ok, less tie ins | TED | TED | | PB | P | 5206607 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 05/23/2016 | field cancel | TED | TED | | PB | P | 5205449 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 05/16/2016 | phase 8 tie ins | TED | TED | | PB | P | 5199740 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 05/13/2016 | phase 8, grease line less tie ins, sewer less tie ins (hallway) | TED | TED | | PB | P | 5198812 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 04/27/2016 | tie in's for phase 3 ok. | TAYLOR | TAYLOR | | PB | P | 5185559 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 04/20/2016 | phase 3, basement grease piping, dish room main to heat tape box area, less tie ins | TED | TED | | PB | P | 5180603 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 04/05/2016 | phase 4 tie ins complete, phase 7-- first part of base less tie ins ok to cover | TED | TED | | PB | P | 5169539 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/10/2016 | phase 6 tie ins ok | TED | TED | | PB | P | 5151940 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 03/02/2016 | phase 2, 4'' stub for future bathrooms (inside only, not through outside footer at this time) | TED | TED | | PB | P | 5146015 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 02/16/2016 | phase 4 & 6, sanitary sewer less tie ins, ok | TED | TED | | PB | P | 5134293 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/26/2016 | 3rd section grease line ok | TED | TED | | PB | P | 5123208 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/25/2016 | 2nd section ok | TED | TED | | PB | P | 5121983 |
HEATING & PLUMBING ENGINEERS, INC | PB | P | 01/14/2016 | 1 section to out of building o.k to insulate | JOEL | JOEL | | PB | P | 5116643 |